Thursday Morning/Afternoon

Slides:



Advertisements
Similar presentations
8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
Advertisements

Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
MD#2 News & Plan Tue – Wed (19. – 20.6.) DayTimeMDEiCMP Tue06: GeV  4 TeV: Ramp for chromaticity - missed A 08:00Ramp down 10: GeV: Large.
Lot’s of time lost due to cryo problem in IR8. Major impact, therefore review of MD program… Start discussion here, please let us know your input. Will.
Friday to Saturday 02:00: Machine closed. 09:00: Cryogenics all OK. Preparing pre-cycle. 10:00: Pre-cycle started. 11:30: Pre-cycle finished. 14:00: Beam.
Tuesday 17 th April 04:00 Prepare second fill for v/d Meer scans. 06:22 Stable beams, v/d Meer scans for Alice and LHCb. 13:20 End v/d Meer scans.Dump.
MD Wed – Sat DayTimeMD Wed06:00UPS repair, ATS optics checks w/o beam 12:00Cycle, test ATS optics w/o beam 16: TeV: BPM offset determination for.
LHC Fri 6 & Sat 7 Nov :00 End instabilities MD, dump to refresh air at dump TDE cavern 08:00 Access for vacuum team at the TDE starting 10:30 Access.
Thursday 20 th April 01:53 RCBV17.R7B2 tripped as happened few days ago: SIS intercepted. 05:54 Stable beams, 1380b, still RF problems B1, abort gap cleaning.
04h36: Cryo problem in arc 81. Access. 09h14: Injection.  TI8 injection collimator setup.  Testing new sequence.  New version of vacuum application.
:30 meetingEBH 1  No beam during the morning:  4:15 – 9: V distributor: Recovery after electrical interruption  access for TI services.
Tue 23/8 – Wed 24/8 09:00 Start 90 m optics run – Preparation and verification of the collimation functions – Re-generation of functions for Transverse.
Ralph Assmann, Giulia Papotti, Frank Zimmermann 25 August 2011
MD Planning Fri – Sat (26. – 27.8.)
LHC Commissioning with Beam
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
Cryo Problem MD Planning Tue (1.11.) C B Day Time MD MP Tue 01:00
Day :00-11:30: Optics at 3.5 TeV Optics re-measured with AC-dipole. Excellent reproducibility. Small emittance increase from AC-dipole. Collapsed.
Monday Recover after trip of RB.A81  Cause of the trip not clear. MP3? 09:00-13:00 Re-inject and Injection verification. In parallel investigations on.
-9:00: Test IP transverse adjustment (CMS) and optics verification.
Friday 15th June 01:11 Injection.
Wednesday 21 March 2012.
Saturday 21st April 00:33 Interlock during ramp on BLM HV
MD Report 24 June 2012 Machine coordinators: Barbara Holzer, Mike Lamont MD Coordinators: Ralph Assmann, Giulia Papotti, Frank Zimmermann MD#2 News & Plan.
Monday h00: Ramp 10 A/s (chromaticity, crossing angle non-closure, beta-beating): At 7m and 3.5m, put in one by one crossing angles, calculated.
Summary of week 7 Hardware Commissioning:
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Thursday morning – optics correction
Summary of Week 13 G. Arduini, B. Holzer
MD#4 Progress MD Coordinators: Giulia Papotti, Frank Zimmermann
Summary of Week 16 G. Arduini, J. Wenninger
MD#2 News & Plan Tue – Wed (19. – 20.6.)
Mon 22/8 – Tue 23/8 00:07 stable beams #2040. Initial luminosities: 2.1x1033 cm-2s-1 18:00 Programmed dump. End of physics #2040. ~83 pb-1 in ~18 hours.
Thursday 10th May - morning
Saturday 2/4/ :00-09:00 Problems with SPS:
Friday Morning 3:44 – 15:04 stable beams Fill (dumped by operator)
Tuesday 20 March 2012.
Summary of Week 26 Main aims: G. Arduini, B. Holzer, M. Lamont
MD#2 News & Plan Tue – Wed (19. – 20.6.)
Monday February 28th 8h00: Injection
MD#4 Progress MD Coordinators: Giulia Papotti, Frank Zimmermann
Wire almost entirely through beam before BLM triggers dump
LHC Morning Meeting - G. Arduini
Yesterday morning Held 1647 for a while – SPS kicker problem
Saturday 7th May Sat – Sun night
Summary Thursday h21: Stable beams fill #1303.
Summary of week 19 Machine Coordinators: G. Arduini, M. Lamont Main aim: Luminosity production.
Monday :20 beta beat corrections during squeeze for flat machine finished Afterwards fixing issues at injection: BPM rephrasing for B2 solved.
Monday 24 October hours of 25ns MD
Wednesday 10:00 test of the un-squeeze to 90 m at 4 TeV.
MD#2 News & Plan Tue – Wed (19. – 20.6.)
Thursday 04/11 - Morning Access until ~13:00 Pre-cycle Proton checks:
90m "proper" VdM scans in the 90m/10m optics
Tue/Wed 12/ :00 Probe beam back again
Thursday 26th July 13:21 Fill 2880 beam dumped
MD Planning Fri – Sat (1. – 2.7.)
Summary for LPC (March 7th, Ralph Assmann)
Friday 14th September 03:15 Beta* at 1 km. Optics measurements, see yesterday. 07:00 Dump. 08:00 Refill with 3 nominal bunches for high beta. 11:15 Beams.
LHC Morning Meeting - G. Arduini
Thu 04:00 Fill #2729 Stable Beams. Initial lumi 6.5e33 cm-2 s-1.
Summary Tuesday h23: Machine closed. Precycle started.
Week 25 Summary Coordinators: Mike Lamont and Barbara Holzer
Wednesday 23/2 Thanks CRYO!!!.
Fri :52 Stable beams fill #2536
Wednesday h18: 228b fill lost just before start of ramp.
Another Immortal Fill….
Tuesday 24/5 Fill # :00 Stable beam fill # bunches
Tuesday End of fill 1393 Movement of suspicious Roman pots OK
Tuesday
Monday 152 bunch operation summary
Presentation transcript:

Thursday 21.6.2012 Morning/Afternoon 8:00 – 16:00 High beta* MD (part 1) 16:30 – 17:00 during ramp down: BPM temperature calibration, Eva Calvo: Is seems like the expert tool had a bug, and the gradients in the FECs were not actualized. The values for the cfv-sr6-bpmint1 have been introduced manually however. The temperature compensation for those channels should normally be better now. The values of cfv-sr6-bpmint2 did not appear on the screen. I will check the files tomorrow morning. And try to setting them up manually also. 17:00 – 18:30 Access for: AC Dipole repair Diamond BLMs: change dynamic range for UFO MD Install temperature probes for Head-Tail monitor 19:00 reboot cfv-ux45-acsc8b2t (to re-set RF 8B2)

Night 18:45 – 2:00 MKI UFO MD Settup tests without beam took longer than anticipated due to problems with setting IQC IPOC limits related to kicker wave forms 144 bunches B1 was OK (losses at 20%) but B2 triggered beam loss that dumped (high emittance bunches)  Transfer line steering TI8  losses at 30% ~ 1 hour of measurements with 1236 bunches two different emittance levels per ring of ~3umrad and ~1.5umrad 1:53 dumped by spark on UA87 injection kickers the ecloud solenoids were off for the MD (for about 10 minutes) higher vacuum pressure at the MKIs 1:57 ventilation door opened in UL26  access till 3:00 Recovery from MD, undoing all changes 4:30 MD on Scraping, diffusion and re-population Planned: 8:00 MD on Fast Losses using ADT

Accesses RCBV29.L3B1 (in fault since Tuesday 19:00) TI wants an access in PM18 (Pompe 2 Eau mixte) TCLIB.6R2.B1 electronics and LVDT sensor. MAD PM15: motors of inner doors not working (at least 4 hours). TOTEM vacuum gauge (3 hours). MCBV18.L4B1 and RCO.A12.B1 to be repaired / changed.

Draft MD Planning Thu – Fri (21. – 22.6.) Day Time MD EiC MP Thu 06:00 Ramp down 08:00 450 GeV  4 TeV: High beta* (1) A 16:00 18:00 450 GeV: MKI UFO studies C Fri 04:00 450 GeV  4 TeV: Scraping, diffusion and Repopulation Study and fast losses (with ADT) C+C 12:00 14:00 450 GeV: Injection and Q20 optics 22:00 450 GeV: RF cavity phase modulation for 25ns B Ghislain Mirko Alick Ghislain Verena Mirko 21-06-12 MD#2 News & Plan 21 June 2012

Draft MD Planning Sat – Mon (23. – 25.6.) Day Time MD EiC MP Sat 06:00 450 GeV  4 TeV: High beta* (2) A 14:00 Ramp down 16:00 450 GeV: Transverse Damper studies cancelled 22:00 Sun 00:00 450 GeV  4 TeV: Collimation (impedance, nominal settings) C 08:00 450 GeV: Beam Instrumentation (BSRT, BGI, wire scan, BPM nonlinearities) A/B/C 450 GeV  4 TeV: Test ramp for emittance calibration B/C 20:00 450 GeV: Dynamic Aperture MD Mon Technical Stop Alick Enrico Mirko Alick Enrico Mirko Alick 21-06-12 MD#2 News & Plan 21 June 2012

END

Thursday 21.6.2012 Morning 8:00 – 16:00 High beta* MD (part 1). Helmut, Jorg, Mirko, Matteo, Stefano, Laurette, beta-measurement team et al.: Main aim: get to beta* = 500 m in IP1&5 and measure and correct optics 3 probe bunches per beam, initial intensity ~3e10 per beam. The first 3 hours were mainly on re-commissioning of the 90 m optics with parallel separation on, and turned out to be rather sensitive on chromaticity which was measured and corrected in several steps to 90 m. Collimators were opened up at 90 m for the de-squeeze to 500 m. The de-squeeze from 90 to 500 m worked very well without any significant losses. The second half of the MD time was spent on optics measurements and corrections at 500 m. Unfortunately, the AC dipol beam 1 horizontal plane was faulty and requires and access to reset. Measured the optics B1 V and B2 H/V. The beta-beat even without correction was mostly within +/- 20 %. Corrections were calculated online and implemented and the optics quickly re-measured before the scheduled end of the MD at 16:00.

Summary Optics Measurements at 500m Beam1 The AC dipole malfunctioned in the H-plane of Beam1. A global correction for beam1 was calculated using data from the 90m commissioning on Monday night where some initial measurements at 500m were made. Optics was re-measured with the global correction implemented, kicking only in the V-plane with the AC dipole. There is no usable data for the B1 H-plane from today's MD Beam2 Optics measurements were performed on and off momentum with no correction applied. Local corrections were calculated for IP1 IP5 and IP6. Optics was re-measured on-momentum with local corrections implemented. A global correction was calculated on the phase. Optics was re-measured with local and global corrections implemented.