FAC review, 10/27 D. Schultz 1 e-Beams System Update Injector System Installation has started. Linac System Preparing for ’06 installation. Controls System.
FAC, 10/12/06 D. Schultz 1 e-Beams Systems Update Linac Injector Undulator Production MMF commissioning ARR David Schultz.
Hal Tompkins FEE/FEL June 16, FEE/FEL Commissioning Overview By Hal Tompkins Photon Beam Systems Deputy.
FAC, 4/20/06 D. Schultz 1 e-Beams System Update Linac System Preparing for downtime installation. Injector System Installation has started. Undulator System.
Jose Chan and Kathleen Ratcliffe FAC Review- LTU/DUMP installation Status & 6/16/08 1 Linac Installation Status, Schedule.
Richard M. Boyce FAC April 16, LCLS Installation & Planning Integration process – IMT 2007 Installation Planning BTH.
Mark Reichanadter LCLS FAC April 20-21, 2006 Meeting of the LCLS Facilities Advisory Committee LCLS Project Management M.
FAC, 4/16/07 D. Schultz 1 e-Beams Systems Update People ARR Linac Installation Undulator Production MMF Operations David Schultz.
John Arthur Photon October 29, Photon Systems Update FAC recommendations Current status New plan for Photon Systems.
Richard M. Boyce FAC October 29-31, Installation Planning Integration process – IMT update Installation Planning &
LCLS Linac System Management Linac Coherent Light Source Stanford Synchrotron Radiation Laboratory Stanford Linear Accelerator Center.
D. Schultz FAC 6/17/08 1 e-Beams Systems Update People Progress the last review LTU and Dump Installation Status Undulator.
Stephen Milton Undulator System 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.
Hamid Shoaee LCLS FAC Controls June 17, LCLS Control System Personnel Linac & BC2 Controls progress LTU, Dump Controls.
Eric Bong LCLS FAC Injector-Linac System October 27, 2005 Injector –Linac System Overview E. Bong LCLS FAC October 27, 2005.
Hamid Shoaee LCLS FAC Review – October Control System Overview Hamid Shoaee Controls System Manager Injector control system commissioning & Support.
Geoff Pile LCLS Und. System Fabrication FAC 29 th, 30 th & 31 st October 2007 LCLS Undulator System Fabrication Schedule FAC.
C.E. Rago Inj/Lin Design & 4_20_06 1 Injector / Linac Design & Fabrication C.E. Rago FAC Review 04_20_06.
FAC, 10/12/06 D. Schultz 1 Readiness for 2007 Startup Linac Injector Controls ARR David Schultz.
David Schultz Accelerator Readiness Dec. 2, ‘08 SLAC National Accelerator Laboratory 1 Undulator Complex Status LCLS Introduction.
Experimental Facilities Planning
Injector Performance Requirements Conventional Facilities Update
LCLS Linac Update Brief Overview L1 & BC1 Progress LTU & E-Dump Status Continuing Resolution Impact.
Injector –Linac Status & Schedule E. Bong LCLS FAC October 12, 2006
LTU/Undulator Installation Status
LCLS Undulator System Detailed Report
e-Beams Systems Update
Installation of Photon Beam Transport to FEH
Linac/BC1 Commissioning P
Electron Beam Systems ETC and Methodology
Injector / Linac Installation Current Status
Linac (WBS 1.2.2) Vinod Bharadwaj April 23, 2002
LCLS Commissioning P. Emma, et al
Details supporting the increase
Project Status Review May 13-15, 2008.
LCLS Undulator System Status and Schedule
Integrated Safety and Environmental Management
Electron Beam Systems Wrap-up
LCLS Undulator System Production Management
LCLS Undulator System Status
LCLS Injector Commissioning P
2007 Downtime Controls Installation
Shutdown Planning & Installation Schedule
LCLS Personnel Protection System and Beam Containment System
E-Beams Systems Manager
LTU/Undulator Installation Status
LCLS Undulator System Status and Schedule
Control System Overview Hamid Shoaee LCLS Control System Manager
LCLS Operation in 2009 Roger A. Erickson
Linac Coherent Light Source Transition to Operations 11 July 2007
Installation Status & Operational Readiness Process
P. Emma, for the LCLS Commissioning Team LCLS DOE Review May 14, 2009
Electron Beam Systems ETC and Methodology
Injector/Linac Design Status C. E
Undulators Subgroup Summary April FAC Review K. Robinson, J
LCLS Undulator System Detailed Report
Undulator Assembly and Installation Planning
LCLS e- Beams System Overview
Undulator Alignment Plan
BC2 / Linac Installation Coordination Kathleen Ratcliffe
X-Ray Endstation Systems (XES) 2006 Schedule
LINAC System Engineering / Design Status C.E. Rago
LCLS Control System Personnel Linac & BC2 Controls progress
DOE Status Meeting of the LCLS Project
LCLS e- Beams Systems Manager
Injector/Linac RF Status
Control System Overview Hamid Shoaee LCLS Control System Manager
Presentation transcript:

e-Beams Systems Update David Schultz People ARR Linac Installation Undulator Production MMF Operations CR Impact

New responsibilities in Linac and Undulator Jose Chan is the new Control Account Manager for LCLS Injector and Linac Systems, taking over from Eric Bong. Geoff Pile is the new Control Account Manager for Undulator Systems at ANL, taking over from Steve Milton.

Injector Accelerator Readiness Review Safety Assessment Document The LCLS SAD for Injector Commissioning was approved Jan. 24th. Accelerator Readiness Review (ARR) The ARR for Injector Commissioning was held October 31st. The committee (in part) reconvened March 14th. The four pre-start items were cleared by the time the ARR report was released. Four comments from the SSO were also addressed. Approval to commission was given April 4th.

Injector Accelerator Readiness Review

Injector Commissioning Injector Commissioning is underway. Commissioning has been impeded by faulty hardware Problems with quality of fabrication and installation of diagnostics Instituted an RFI sign-off sheet, requiring approval from physics, engineering, controls, and metrology. First electrons from the gun 4/5/07 Courtesy P. Emma

2007 Commissioning Sector 21 Sector 20 Laser BLM BC1 LX L1 Ins/SAB stopper BLM BC1 LX L1 Ins/SAB Wall See P. Emma’s talk

Installation Schedule 6 MeV 135 MeV 250 MeV 4.30 GeV 13.6 GeV Linac-0 L =6 m Linac-X L =0.6 m rf gun L0-a,b Linac-1 L 9 m Linac-2 L 330 m Linac-3 L 550 m BTH west 25-1a 30-8c ...existing linac 21-3b 24-6d 21-1 b,c,d X undulator L =130 m BC2 L 22 m BC1 L 6 m DL2 L =275 m Now commissioning 2007 down SLAC linac tunnel research yard

LCLS Installation and Commissioning Time-Line June 29, 2007 rmb DRAFT X-Ray tunnel/FEH Install X-Rays in FEH LTU/Und/Dump FEE/NEH Install First Spont. Light CF Early Occupancy X-Ray Systems Checkout - Commission e- beam & Photon Systems Checkout CD-4b CD-4a S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M 2007 2008 2009 PPS PPS 2010 Photon Flux Measurements Controls checkout Re-commission Inj/BC2 to SL2 Operations LTU/Und/FEE Commissioning NEH Operations Linac/BC2 Commissioning linac/BC2 Install FEL Commissioning

’07 Downtime Installation Sept., Oct., Nov. 2007, a very tight schedule. Installation of BC2 and L3, not L2. Installation to support BTH-West Cable plant installation through the BSY Coordinated through the AD downtime schedule IRR held March 16th. All hardware is RFI or in the shop. Cable plant inst. schedule is tight. Scheduling and coordination between the different disciplines will be vital. See breakout talks

’08 Installation LTU/Undulator/Dump Readiness milestone for Early Occupancy installation held constant at Nov. 1, 2007 Begin installation with: Metrology Beamline supports Cable plant Installation scheduling coordinated by R. M. Boyce Installation contracts need to go to bid this summer. Designs are being completed to support this. See breakout talk

Undulator Systems Components Beam Finder Wire parts are in fabrication. Wire card a SLAC responsibility, design underway. RF Beam Position Monitor in production. Body fabrication is in procurement. First 3-BPM test results look promising, tests are ongoing Vacuum Chamber – next slide These systems are all near the critical path. Quadrupole magnets’ 1st article in measurement at ANL. Support/Mover system fabrication award made. WPM/HLS FDR was held March 22nd Production moving forward See G. Pile’s talk

Undulator vacuum chamber - 1 As described last October, two competing designs were carried to the prototype stage, SS ‘4-Weld’ and Al ‘Clamshell’. A review of Undulator Vacuum Chamber Design Options, was held Feb. 22nd Permeability was a significant concern, and measurements and simulations were presented at the review The 4-Weld design was selected to remain the baseline. Recent measurements of the undulator field inside the SS vacuum chamber have raised concerns. Physics requirements on field variations have been refined. Short scale field variations cannot be measured with sufficient accuracy to remove doubt. No satisfactory QA process for permeability is in hand. The project needs to pursue other alternatives.

Undulator vacuum chamber - 2 The following course of action is being pursued: Stainless steel design Production has been stopped Al extrusion design Fastest option to a full scale prototype, and production Accelerate machining trials & internal polishing tests Cu tube design Develop to the prototype stage as an option for 800eV operations. Al clamshell design Pursue polishing trials on existing chamber samples See breakout talks

Undulator Magnetic Measurement All 40 undulators are at SLAC. The MMF is in production mode, but behind schedule. 6 undulators finished magnetically, but not RFI. Undulators need support shims which have been redesigned and are being remade. Production rate of 1 per week has been demonstrated. “Exceptional” cases continue to be a problem. Adjusting the gap at the rough tuning stage requires a larger-than-specified range of wedge spacers. A broader range of spacers are on order. See breakout talk

CR Impact Uncertainty as to which programs could continue and which needed to be deferred. Led to lost efficiency and lost time. Procurements were put on hold until the impact of the CR was resolved. Linac and Controls BC2, L3 2007 installation was held to schedule. LTU, Und., Dump schedules set to accomplish CD-4a. Additional manpower is needed to recover lost time. Additional costs are needed to speed procurements.

CR Impact Undulator work at ANL The transfer of funding to ANL was slowed until the impact of the CR was resolved. Significant procurements at ANL were put on hold. Delays in ANL deliveries results in delays to Undulator assembly at SLAC Undulator assembly and installation is on the CD-4a critical path Additional manpower and costs are needed to recover lost time.

Issues The ’07 downtime Linac installation schedule is very tight. The schedule shows completion of installation Hardware availability is being closely monitored Controls checkout (last) is at risk. The Undulator vacuum chamber design is changing This is on the critical path. A task force has been formed to manage the parallel options being pursued. Cost and schedule plans for these options are developed. The MMF is in production. Have not yet sustained production throughput.