R. Losito – LHC Performance Workshop Chamonix Jan 2010

Slides:



Advertisements
Similar presentations
Chamonix 2010: January 27 th Session 6 – Radiation To Electronics: R2E Summary Radiation 2 Electronics Session th January 2010 Radiations to Electronics.
Advertisements

K. Potter RADWG & RADMON Workshop 1 Dec WELCOME TO THE 4th RADWG & RADMON WORKSHOP 1 December 2004.
LHC Beam Dumping system
Consolidation and Upgrade of the LHC Experimental Vacuum Sectors
R2E Weekly Report status AT/MB/MC – 4 th R2E Project Meeting – 7 th April 2011.
Christophe Delamare EDMS Accelerator Consolidation Workshop GS/ASE activities.
Proposal for Decisions 2007 Work Baseline M.Jonker for the Cocost* * Collimation Controls Steering Team.
J. G. Weisend II Deputy Head of Accelerator Projects April 2, 2014 Actions at ACCSYS Resulting from the Recommendations of the Annual Review.
Safe-Room Status Intermediate ‘Conclusions’ M. Brugger (based on HSE discussion)
Status and possibilities for the irradiation facility in the PS East Hall Michael Moll, Maurice Glaser 10 March 2010 – IRRAD Working Group - some notes.
Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"
Radiation Tolerant Electronics New Policy? Ph. Farthouat, CERN.
LS1 : EL Upgrades & Consolidation Chamonix– February 8 th 2012 F. Duval on behalf of EN/EL The goal of LS1 is to implement everything needed for a safe.
Experimental equipment interacting with beam operation D. Macina TS/LEA Many thanks to my colleagues both from the experiments and the machine for their.
R2E Report M. Brugger for the R2E Study Group RadWG Meeting, August 20 th 2009.
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
Radiation Tolerant Electronics Expected changes Ph. Farthouat, CERN.
R2E Mitigation Project P5 Relocation Options - Discussion R2E Mitigation Project CMS Relocation Options Towards An R2E Baseline 1 M. Brugger for the R2E.
Samy Chemli – Configuration Management - S. Chemli EN-MEF – Contents Configuration Management Hardware Baseline Change Management.
CMS Proposal for a Maintenance & Operation agreement with EN/CV/DC for fluorocarbon detector cooling circuits v.2 P. Tropea For the CMS experiment.
K. Foraz & Perrot A. L., EN/MEF - R2E Project LMC 25th May 2011 Thanks to EN/EL, EN/HE, EN/MEF, equipment owners the LHC integration team & the R2E team.
Injection Energy Review D. Schulte. Introduction Will review the injection energy So could answer the following questions: Which injection energy can.
Hardware Commissioning  Preparation Documentation MTF Programme  Status The Review The commissioning activity in Resources  Outlook The new.
LHC-CC Validity Requirements & Tests LHC Crab Cavity Mini Workshop at CERN; 21. August Remarks on using the LHC as a test bed for R&D equipment.
R2E Availability October 15 th 2014 Experience from Past LHC and Injector Operation and scaling to the future G. Spiezia.
LHC Injectors Upgrade Project 1/12/2010 R. Garoby.
Radiation monitoring: what do we have and what do we need? M. Calviani, M. Brugger, P. Peronnard, J. Saraiva, G. Spiezia (EN/STI) R2E/Availability Workshop.
Upgrade PO M. Tyndel, MIWG Review plans p1 Nov 1 st, CERN Module integration Review – Decision process  Information will be gathered for each concept.
R2E Mitigation Project Status Report 2 nd R2E Committee Meeting R2E Project Report.
PS-EA Update RadWG August 23 rd 2012 Radiation 2 Electronics (R2E) LHC Activities RadWG August 23 rd 2012 PS East Area Update M. Brugger on behalf of the.
Conclusions on UPS powering test and procedure I. Romera Acknowledgements: V. Chareyre, M. Zerlauth 86 th MPP meeting –
Mixed field irradiation -- Who answered ?  In total 36 forms filled / 34 persons answered: 38% 62% CERN: mainly LHC related topics CERF: beside LHC topics.
Interface of FP420 to LHC FP420 meeting 28-Sep-2006.
R2E relocation & shielding LS1 preparation Anne Laure Perrot EN/MEF- LE Discussion with OP colleagues, 5 th July 2012.
Summary Session 5 Chamonix 2011, 24. – Session 5: “High Intensity: Present and Future” R. Assmann & S. Redaelli Thanks to Frank Z. for his notes…
R2E Workshop Preparations RadWG Meeting March 25 th.
LHCf collaboration meeting, Nagoya, January 2009A. L. Perrot LHC news A. L. Perrot CERN, EN/MEF-LE LHCf collaboration meeting, Catania, 6 th July 2009.
Personnel Safety Systems Stuart Birch Senior Engineer, Personnel Safety Systems November 6 th, 2014.
Collimation Aspects for Crab Cavities? R. Assmann, CERN Thanks to Daniel Wollmann for presenting this talk on my behalf (criticism and complaints please.
EXPERIMENTAL AREAS CONSOLIDATION EACONS part – early draft from comments.
Follow-Ups and Project Structure R2E Meeting September 8th Project / Study Group / RadWG R2E Mitigation Project:  Responsible of development and implementation.
R2E/Availability Workshop Report - RadWG October 22 nd 2014 R2E/Availability Workshop 2014 October th 2014 R2E/Availability Workshop RadWG - Brief.
LHC Injectors Upgrade Project 11/11/2010 R. Garoby.
Planning and strategy for HL-LHC R2E
LHC intervention scheduling with the Work Acceptance Tool
ITIL: Service Transition
Matters arising RADWG - 3 July 2009
News and Introduction from CERN June 15th, 2005
Irradiation test of Commercial (BASLER) digital cameras
S. Roesler (on behalf of DGS-RP)
Radiation monitoring and follow up during LHC commissioning
Equipment simplified model SMR UR safety
Installation of an Instrument on a CERN machine
CERN R&D plans and Infrastructures
Outline Introduction to LHC Power Converters Remaining Inventory Observed Availability New inventory – FGClite Cumulative & SEE Effects Maintenance.
Tile Upgrade Workshop (CERN- February and 9)
Quality Assurance applied to Accelerator Safety
Accelerator and Experiment Interface Session: LS2, LS3
Joint Meeting SPS Upgrade Study Group and SPS Task Force
the CERN Electrical network protection system
TI8/WIC Incident & UJ87/UA87 Radiation Levels & Analysis
CLIC Civil Engineering Update
Update on expected HL-LHC radiation levels
Engineering Processes
Collimator Control (SEUs & R2E Outlook)
Preliminary Analysis and foreseen actions EN-ICE&EN-STI
RADIATION induced failures in LHC 28th June 2011
R2E Follow-Ups and Project
Review of hardware commissioning
Radiation Working Group RADWG
Presentation transcript:

R. Losito – LHC Performance Workshop Chamonix 25-29 Jan 2010 Where are we with the Long-term plans and the CERN-wide radiation Policy R. Losito – LHC Performance Workshop Chamonix 25-29 Jan 2010

Acknowledgements Members of R2E Members of RADWG Members of PH-ESE, EN-STI, EN-MEF etc… A few other people, in particular M. Brugger, S. Weisz, A.-L. Perrot, G. Spiezia, D. Kramer, S. Roesler, R. Assmann, M. Lamont, Y. Thurel, J. Osborne, J. Serrano. R. Losito, EN-STI, LHC Performance Workshop, Chamonix 25-29 Jan 2010

Radiation Policy The principles The implementation for LHC R. Losito, EN-STI, LHC Performance Workshop, Chamonix 25-29 Jan 2010

PRINCIPLES Thought and proposed for LHC machine Sufficiently general to be usable for all underground or exposed areas Only the main principles of good practice in the policy. Detailed Application of the policy to be expressed in addenda specific to each big project/machine. Test procedures and reports to be adapted by system, installation, project, experiment etc… R. Losito, EN-STI, LHC Performance Workshop, Chamonix 25-29 Jan 2010

PRINCIPLES : 1) Environment First of all, the environment needs to be known. Every possibly critical area has to be simulated, a central repository for the project/installation need to be created : (e.g. R2E website for the LHC Machine). Need of at least: TID: Dose (Gray/year in silicon) NIEL: 1MeV eq. Neutron fluence SEU: >20 MeV fluence We need to specify a parameter for thermal neutrons Ratio Thermal/high energy + fluence? Spectra R. Losito, EN-STI, LHC Performance Workshop, Chamonix 25-29 Jan 2010

PRINCIPLES : 2) Selection of Components Designers shall have to select components compatible with the expected level of radiation. Test procedures and reports adapted to the fluence/dose Tests need to be performed for every new batch. While a central database may be established, this is not felt fundamental by users: it quickly gets obsolete… A central procurement of rad-tolerant components might be more useful. Working groups to approve selection of the components (RADWG? ). Unrealistic, too much workload for the available manpower. Can only be done for main systems and components. R. Losito, EN-STI, LHC Performance Workshop, Chamonix 25-29 Jan 2010

PRINCIPLES : 3) Design Reviews Classification of equipment: responsibility of project/experiment Personnel safety Machine/experiment protection Critical for operation/ downtime “monitoring” Equipment critical for personnel safety and machine/experiment protection should not be installed underground if possible If not, they have to undergo a strict procedure of design review and test to ensure a minimum risk of failure. Systems responsible for relevant beam downtime should undergo design reviews as well. Monitoring: only on request of its owner R. Losito, EN-STI, LHC Performance Workshop, Chamonix 25-29 Jan 2010

PRINCIPLES : 4) System Test Final systems need to be tested in a reference environment similar to the final one CNGS for LHC machine (nTOF? HiRadMat?) RP does not consider CNGS a long term facility… For machine equipment, tests inside and outside CERN shall be coordinated through the RADWG Test reports: impossible to provide a general template: groups must produce written technical reports for each test. Groups must present their results in RADWG and, if requested, in yearly Radiation workshops organised (for machine) by RADWG. R. Losito, EN-STI, LHC Performance Workshop, Chamonix 25-29 Jan 2010

PRINCIPLES : 5) Quality Assurance Equipment groups shall have to provide in the MTF values of sensitivity to the parameters set out in the Environment part: TID, NIEL, SEU, Thermal Neutrons. Equipment Groups shall be responsible to set operational procedures with OP to ensure the risk is minimised e.g. access controls underground switched off before sending beam e.g. Preferential use of given collimators… Control Needs dedicated qualified personnel, both centrally and in each (main) group, to verify that the numbers correspond to what simulated. OP in charge to implement operational procedures R. Losito, EN-STI, LHC Performance Workshop, Chamonix 25-29 Jan 2010

Implementation : LHC Machine For LHC Machine, the LMC will supervise and give priorities. R2E will coordinate technical work at different level and give coherence between simulations, design, test, machine integration. RADWG will support equipment groups for design (component selection, design reviews) and radiation test Equipment owners are responsible for implementation and quality assurance. Point owners (or persons to be identified) shall be informed of installed equipment and in charge of organising control. Ensure that OP is aware of special procedures suggested for a given equipment R. Losito, EN-STI, LHC Performance Workshop, Chamonix 25-29 Jan 2010

Conclusions on Radiation Policy The policy implies work It will remain just a document without manpower It implies manpower available, both in equipment groups and for working groups R. Losito, EN-STI, LHC Performance Workshop, Chamonix 25-29 Jan 2010

Consolidation Program LHC Tunnel Service galleries R. Losito, EN-STI, LHC Performance Workshop, Chamonix 25-29 Jan 2010

Can we quantify the risk? Options for LHC operational scenarios (and imperfections) bring uncertainty on radiation levels The real uncertainty comes from the equipment sensitivity: Even if we knew it now, it would change in the future with repairs, updates, upgrades etc.. Sensitivity to low energy neutrons cannot be excluded So the answer is NO, but the risk is there. First SEE during transfer line commissioning. R. Losito, EN-STI, LHC Performance Workshop, Chamonix 25-29 Jan 2010

Our assumption We assume SEU are caused only by High Energy hadrons We assume the risk is acceptable for fluencies ≤ 107 hadrons / cm2 / year R. Losito, EN-STI, LHC Performance Workshop, Chamonix 25-29 Jan 2010

LHC Tunnel Main systems at risk tested in CNGS: then QPS - ok Cryo – under way….ok BLM – ok BPM – ok then Power Converters: as discussed by Yves (ok) FIP: only real concern. R. Losito, EN-STI, LHC Performance Workshop, Chamonix 25-29 Jan 2010

P2 – P3 – P4 – P6 Good news!!!! Nothing to do P4: assuming no catastrophic beam-gas interaction happens P6: assuming filling of ducts successful (intensity up to now not sufficient to verify!) R. Losito, EN-STI, LHC Performance Workshop, Chamonix 25-29 Jan 2010

Cost: ~5÷10 MCHF ? The wooden option ~20 FTE ? We touch wood and hope it will be ok!! To help, we add some shielding here and there, relocate some equipment as possible. We gain maybe 1 year, 2 or 3 in some areas Includes full relocation in P8 Cost: ~5÷10 MCHF ? ~20 FTE ? R. Losito, EN-STI, LHC Performance Workshop, Chamonix 25-29 Jan 2010

A further step: RRs in P7 Redesign 120A and 600A converters to either be rad-tolerant Implies additional specialised manpower Solution can be deployed anywhere else or distance tolerant Only valid for P7 and few additional places Implies complete re-integration of TZ76 Or use Super Conducting Links COST: ~10÷15 MCHF? ~20 FTEs? R. Losito, EN-STI, LHC Performance Workshop, Chamonix 25-29 Jan 2010

Cost: ~50÷60 MCHF RRs in P1 and P5 Re-design of power converters not a credible option (4-6 kAmps not present in P7) 4 new shafts (as presented yesterday by Sylvain) Relocation: services infrastructure, PC and further electronics Cost: ~50÷60 MCHF R. Losito, EN-STI, LHC Performance Workshop, Chamonix 25-29 Jan 2010

RR’s + shafts Point 1 & 5 New Shaft ∅5m Existing LHC tunnel John Osborne GS-SEM New Shaft ∅5m Existing LHC tunnel Existing RR New Access ∅3m Existing LHC tunnel New cavern ∅7m John Osborne GS-SEM

UJ 14/16/56 Full solution for relocation only credible for P1, at the price of taking all the space reserved for the LHC upgrade. For P5 no full solution: Either we use PM56 (or UP/USC): integration study to confirm Or we need further civil engineering works in P5: new UAs? See Sylvain’s talk tomorrow. Relocation cost: 5÷15 MCHF? R. Losito, EN-STI, LHC Performance Workshop, Chamonix 25-29 Jan 2010

Conclusions (1/5) In a nominal year at 7 TeV per beam we will have several areas with fluencies ≥ 109 hadrons / cm2 / year How can we reduce the risk? ….(beware: numbers following mostly my guess) R. Losito, EN-STI, LHC Performance Workshop, Chamonix 25-29 Jan 2010

Conclusions (2/5) To ensure everywhere ≤ 108 hadrons / cm2 / year and move all the electronics supposed to be sensitive to that level (apart from power converters). Material [MCHF] MANPOWER [FTEs] decision Ready Early shielding/relocation 5÷10 20 Now 2011 Relocation UJs (no new civil engineering) 15 30 2010 2013 R. Losito, EN-STI, LHC Performance Workshop, Chamonix 25-29 Jan 2010

Conclusions (3/5) Redesign power converters to be compatible with 108 hadrons / cm2 / year Material [MCHF] MANPOWER [FTEs] decision Ready Redesign 120/600 Amps 5÷10 15÷25 May 2010 2014 R. Losito, EN-STI, LHC Performance Workshop, Chamonix 25-29 Jan 2010

Conclusions (4/5) Solve problem of 4-6 kAmp in RRs Material [MCHF] MANPOWER [FTEs] decision Ready New Shafts and relocation 50÷60 40 June 2010 2014÷2015 R. Losito, EN-STI, LHC Performance Workshop, Chamonix 25-29 Jan 2010

Conclusions (5/5) If we want a safe solution in P1 and P5, and invest in an infrastructure ready for further challenges (LHC upgrade, crab cavities etc…) Material [MCHF] MANPOWER [FTEs] decision Ready 4 New UAs 50÷100 MCHF ? 60? 2011? 2015 R. Losito, EN-STI, LHC Performance Workshop, Chamonix 25-29 Jan 2010

Summary Beware, these numbers are only my guess!! Material [MCHF] MANPOWER [FTEs] decision Ready Early shielding/relocation 5÷10 20 Now 2011 Redesign 120/600 Amps 10 15÷20 May 2010 2014 New Shafts and relocation 50÷60 40 June 2010 2014÷2015 Relocation UJs (no new civil engineering) 15 30 2010 2013 4 New UAs 100 MCHF ? 60? 2011? 2015 R. Losito, EN-STI, LHC Performance Workshop, Chamonix 25-29 Jan 2010

Conclusions Numbers are enormous, and we cannot wait too long. Decisions have to be taken BEFORE the risk can be quantified. A workshop will be organised after Easter (mid April) to consolidate the information Equipment groups shall come with their numbers. Safety groups and LHC upgrade shall have to be part of the decision. It is necessary to invest substantial manpower in 2010 for integration studies (in the widest sense!). The different options have to be studied with sufficiently high priority in the integration team. We should also consolidate CNGS or design/invest in a new long term facility R. Losito, EN-STI, LHC Performance Workshop, Chamonix 25-29 Jan 2010

Addendum… Start to invest on the future… Set-up joint working group with PH-ESE for common development of FPGA or microprocesors (ex: generic field-bus, or acquisition module for temperature, pressure, low precision voltage measurement etc…) Would need money and resources as well R. Losito, EN-STI, LHC Performance Workshop, Chamonix 25-29 Jan 2010

SPARE SLIDE R. Losito, EN-STI, LHC Performance Workshop, Chamonix 25-29 Jan 2010

Summary Of Areas – See Direct Link