Offshore Wind Transmission:

Slides:



Advertisements
Similar presentations
The Midwest ISO from a Transmission Owner Perspective.
Advertisements

August 1-2, 2013 Transmission Owner Perspectives: Transmission Siting and Order No Cost Allocation in the PJM Region Randall B. Palmer Senior Corporate.
Order 2000 and PJM: A Natural Match Craig Glazer Manager of Regulatory Affairs PJM Interconnection, LLC.
Federal Energy Regulatory Commission Large Generator Interconnection Order on Rehearing (Order No A) RM March 3, 2004.
1 RTWG Tariff update to the BOD, MOPC, SPC, and RSC January 4, 2005.
Transmission Independence and Investment Pricing Policy for Efficient Operation and Expansion of the Transmission Grid FERC Docket Nos. AD and.
FERC Federal Energy Regulatory C ommission May 30, 2002 Inter-RTO charges and RTO Membership decisions.
WELCOME Western Area Power Administration1. Where did the journey begin? Western Area Power Administration2.
Kansas Renewable Energy and Energy Efficiency Conference Wind 2007 RFP Update John Grimwade - Sr. Director Strategic Planning and Development September.
Regional Transmission Organizations: The Future of Transmission? Dave Edwards 4/17/2004.
DOE OFFICE OF INDIAN ENERGY Renewable Energy Project Development and Finance Framework: The 5 Step Process 1.
Federal Energy Regulatory Commission Proposed Rule on Small Generator Interconnection RM July 23, 2003.
Federal Energy Regulatory Commission Large Generator Interconnection Final Rule RM July 23, 2003.
Transmission Barriers to Wind Energy in the West Presented by: Pamela Jacklin Stoel Rives LLP POWER-GEN Renewable Energy & Fuels 2007 Conference Mandalay.
The Potential for Increased Cooperation on Offshore Wind among the Northeast States Warren Leon, Executive Director.
. Juan de Fuca Cable. Safe Harbor Statement Included in this document is certain information which is “forward looking information” as defined by the.
Despite Order No Planning Gaps for (Certain) Merchants OPSI Annual Meeting 2013.
1 Utility Ownership of Wind Power: Why it makes sense now American Wind Energy Association May 17, 2005 Eric Markell Senior Vice President Energy Resources.
1.  Offshore Siting Process / Guidelines – Macro View  Offshore Siting Example – VA  Offshore Development Example – VA Virginia Offshore Wind Technology.
Southwest Renewable Energy Transmission Conference May 21, 2010 Jeff Mechenbier Director Transmission & Distribution Planning and Contracts.
Powering Alberta AESO Annual General Meeting May 14, 2009 Reliable Power Reliable Markets Reliable People.
Joint Outreach Team Implementation Plan July 12, :30-11:30 a.m.
1 JULY 2010 PRELIMINARY TECHNICAL CONFERENCE REPORT – WORK IN PROGRESS Entergy Arkansas, Inc. Transition Plan Technical Conference #2 July 15, 2010.
OSC Meeting April 27, Transmission Cost Allocation Overview.
Sec. 5 RE-REGULATION- EPAct 1992 FERC Orders 888 and 889 (1996) EPAct 2005 In short these three laws move the power industry towards an increase in competition.
Phoenix Convention Center Phoenix, Arizona ANDREA L. KINCAID DLA Energy Track 5 Project FinanceSession 6 Renewables Through Private Financing.
1 Interconnection Update Jay Zimmerman Manager, Transmission Policy Entergy Transmission Planning Summit New Orleans, LA July 8, 2004.
Icfi.com © 2006 ICF International. All rights reserved. Wyoming Collector and Transmission System Project – Status Report Presented to: Wyoming Infrastructure.
Successful Restructuring: The Way Forward Mark Bennett Senior Manager of Policy Electric Power Supply Association Restructuring and the Wholesale Market.
MICHIGAN’S RETAIL ACCESS PROGRAMS Not the last Frontier A presentation to The National Energy Marketers Association.
Designing Energy Solutions without Borders National Association of Regulatory Utility Commissioners National Association of Regulatory Utility Commissioners.
1 NAUSCA Summer Meeting Boston June 30, 3009 David W. Hadley Vice President State Regulatory Relations Midwest ISO.
Order 1000 Implementation in PJM – Challenges and Opportunities Jodi L. Moskowitz Senior Director – Transmission Development & Strategy October 13, 2015.
Lauren Azar Senior Advisor to the Secretary U. S. Department of Energy May 31, 2013 – WI Public Utilities Institute 1 Transmission Planning – A National.
Bob Cupit Manager, Energy Facility Permitting Minnesota Public Utilities Commission.
ESI/SPP Seams Agreement Implementation Update Transmission Planning Summit August 11, 2010.
Creating a Successful Clean Energy Business The Project Development Puzzle Richard Harkrader Carolina Solar Energy CEO March 9th 2011 Conference on a Renewable.
C A L I F O R N I A E N E R G Y C O M M I S S I O N Integrated Energy Policy Report Workshop Landscape-Scale Environmental Evaluations for Energy Infrastructure.
Lessons Learned from Existing RTOs John Moore January WCEA Meeting January 7 th, 2016.
FERC Order 1000 and its Potential Implications for BCCPG Transmission Providers BCCPG Steering Committee Meeting 20 September 2011.
Generator Interconnection Studies & Agreements Charles Hendrix.
AES NewEnergy To The Institute For Regulatory Policy Studies May 18, 2000 By David L. Townley.
Kansas City Power & Light and KCP&L Greater Missouri Operations – Suggestions for Chapter 22 Revisions Missouri Public Service Commission Meeting Aug 31,
CARILEC. An Association of Electric Utilities CARILEC An Association of Electric Utilities The Caribbean Electric Utility Service Corporation (CARILEC)
Duke Energy Independent Entity Update
Regional Transmission Organizations
Location, Location, Location
Massachusetts Electric Restructuring Roundtable
DCC Cluster/Working Group Energy MTDS (GoT) priorities for the sector
Transmission: the Critical Link
Pseudo-tie business procedure
T.O. Highway/Byway Recommendations
Internet Interconnection
Reliability Assessment Committee Reliability Workshop Priorities
Transmission As Enabler
Malama Chileshe Energy Economist COMESA Secretariat
FERC NOI on Incentive Rates
New England Resource Adequacy
Kurt Adams EVP&CDO Restructuring Roundtable
Great Lakes Wind Collaborative: Who We Are and What We Do
Reliability Assessment Committee Reliability Workshop Priorities
Developing the power sector in Federal Nepal Main lessons from international experience Kathmandu, November 06, 2018.
Solar Energy Commercialization Session 11
Parks and Recreation Services
Supplemental Project Planning Process Under Order 890 Within PJM
Pseudo-tie business procedure
Offshore Wind Project Development:
Scaling up of Renewable Energy for Power Generation in the Western Balkan countries
DEVELOPMENT IMPACT FEES AB 1600 UPDATE
New England’s Response to FERC’s RTO Order No. 2000
Presentation transcript:

Offshore Wind Transmission: A Regulatory Update Author, MARK C. KALPIN Key considerations Regulatory Structures Cost Recovery Mechanism Open Access Requirements RTO Interconnection Process Coordination of Permitting and Construction Impact on Project Financing and Development Ability to Address Need for Short- and Long-Term Transmission System Upgrades GENERATOR LEAD LINE Current Model in State RFPs Bundled PPA Rates based on Delivery of Energy FERC Order 8071 5-Year Safe Harbor until Open Access Ability for “Voluntary Agreements”? Integrated Interconnection Process BOEM Lease / Easement with Coordinated SAP, COP and NEPA Review for Transmission Facilitates Project Development, but: Cost of Required Transmission Upgrades Falls on Project No Incentive to Address Long- Term Transmission Needs MERCHANT OWNERSHIP Cost-Based / Participant-Funded Rate Recovery FERC’s Chinook2 Four Factor Analysis and Final Policy Statement on the Allocation of Capacity3 prior to OATT Interconnection as an Independent Merchant: A New Wrinkle? Need for Separate BOEM ROW and GAP Complicates the Coordination of Permitting and Construction Complicates Project Development Who Bears the Financial Risk: Project or Merchant? Cost of Required Transmission Upgrades Still Falls on Project Still No Incentive to Address Long-Term System Needs TRANSCO OWNERSHIP RTO OATT & Cost Recovery Govern RTEP or Order 1000 Public Policy Project? Who Builds – Incumbent TSO or Merchant? Ability to Achieve Stakeholder Consensus? Substantial Coordination Risk: Technology, Design, Permitting, Construction, In-Service Dates Could Facilitate Project Development, but: Who Bears the Financial Risk? Can Sufficient Consensus be Achieved in Advance to Address Both Short- and Long-Term Transmission System Needs? CONTACT INFORMATION Mark C. Kalpin Partner, Holland & Knight LLP 617.305.2076 (o) | 617.835.7020 (m) mark.kalpin@hklaw.com www.hklaw.com/Mark-Kalpin/ References Open Access and Priority Rights on Interconnection Customer’s Interconnection Facilities, Order No. 807, 150 FERC ¶61,211 (2015), reh’g denied, 153 FERC ¶ 61,047 (2015) The four factors are: (1) justness and reasonableness of rates; (2) the potential for undue discrimination; (3) the potential for undue preference, including affiliate preference; and (4) regional reliability and operational efficiency requirements. Chinook Power Transmission, LLC, et al., 126 FERC ¶ 61,134, at P. 37 (2009). Allocation of Capacity on New Merchant Transmission Projects and New, Cost Based, Participant Fund Transmission Projects, 142 FERC ¶ 61,038 (2013) Transmission Planning and Cost Allocation by Transmission Owning and Operating Public Utilities, Order No. 1000, 76 FR 49842 (Aug. 11, 2011), FERC Stats. & Regs. ¶ 31,323 (2011), order on reh’g, Order No. 1000-A, 139 FERC ¶ 61,132 (2012), order on reh’g and clarification, Order No. 1000-B, 141 FERC ¶ 61,044 (2012)