System Planning and Expansion November 10, 2016 System Planning and Expansion
Principles and Best Practices Uniform, walkable station density providing comparable service in urban core and bedroom communities Strong partnership and coordination between City agencies, operator, and community members to select sites Empower stakeholders and lay the foundation for public support Operator input ensures a functionally viable system Strategy for roll out incorporating a manageable supply chain, staffing plan, equipment and other resources
Citi Bike: system launch and expansions Phase Stations Docks 2013 - 2014 336 11,599 2015 140 4,557 2016 139 3,872 2017 141 3,571 Total 756 23,599 2013 2014 2015 2016 2017
Network planning: system density in NYC
Network planning: system density in NYC
Network planning: system density in NYC
Expansion site selection: Identify available space
Expansion site selection: identify available space
Expansion site selection: community feedback
Expansion site selection: operational criteria
Expansion site selection: draft and final plans
Expansion planning: station siting and design guidelines 1. Site selection criteria clearances and functionality 2. How to conduct a site survey 3. Utilities and other surrounding objects When to use street treatments Striping, delineators, granite blocks 4. Dimensions to be shown distance to point of beginning distance between station and street treatments
Expansion planning: overlapping dependencies
Staffing and equipment: year round ops vs expansion ops
Staffing and equipment: year round ops vs expansion ops 7 60 2 8 1 2 3 6
Staffing and equipment: expansion ops
Station installation https://youtu.be/g1s90DgSL6Y https://vimeo.com/179916936