Change Order Number Five, Contract M03037P01, Professional Services, 2050 Facilities Plan – Ultimate Build Out, and Approve Changes in Total Project Cost.

Slides:



Advertisements
Similar presentations
RC Strategy Implementation. What we are asking for… Authorization to hire Black and Veatch to develop and issue the two RFPs associated with the RC Strategic.
Advertisements

For State Agencies. Contract Elements Scope of Work Routing & Contract Mgmt Negotiations Contract Information & Forms.
Conducting Collaborative Projects Part 4 OSP Awareness Feb 16, 2011 osp.syr.edu
Chapter 3: The Project Management Process Groups
Information Technology Project Management, Sixth Edition Note: See the text itself for full citations.
State of Oklahoma Information Services Division Contracts and Purchasing Unit 1.
Project Management Fundamentals Project Organization and Integration
Office of Project Management Metrics Report Presentation
Public Works Contracting Marsha Reilly Office of Program Research House of Representatives recommended.
Project Planning & Estimating – Are we there yet?
Information Technology Project Management, Sixth Edition Note: See the text itself for full citations.
Click on Next to continue Introductio n Inputs Tools and Techniques Outputs Next 12.2 Conduct Procurements: Introduction The process of obtaining seller.
Catherine C. Dunn, P.E., N.PE, P.PE Deputy Director Port Development Prt of New Orleans Catherine C. Dunn, P.E., D.NE, D.PE Director,
11-1 PROJECT CONTROL Project Control Defined Types of Control Systems Need for Balance in Control Systems Control of Creative Efforts Changes and Change.
FORUM Agenda 1. Fleet Vehicle Utilization Review -- Sam 2. Fleet On-line Reports -- Scott 3. Enterprise Rent-A-Car Contract Changes -- Sam 4. Already Replaced.
Copyright 2009  Describe the five project management (PM) process groups, the typical level of activity for each, and the interactions among them  Understand.
PUBLIC PURCHASING IN FLORIDA ROLES IN THE PURCHASING PROCESS (rev. 05/27/2008)
Catherine C. Dunn, P.E., N.PE, P.PE Deputy Director Port Development Prt of New Orleans Catherine C. Dunn, P.E., D.NE, D.PE Director,
Introducing Project Management Update December 2011.
1 Global Design Effort: Controls & LLRF Controls & LLRF Working Group: Tuesday Session (29 May 07) John Carwardine Kay Rehlich.
DHHS COE Meeting Agenda February 11, 2010 Welcome Introductions Contract Compliance Reporting Questions and Answers DHHS Open Windows Update.
Enterprise Approach to Environmental Management Tools April 2004 NAS Patuxent River Environmental Department Larry Donmoyer, Ph.D. Env. Compliance Division.
1 1 Effective Administration of Commercial Contracts Breakout Session # Session D06 Name: Holly Walker, CPCM Corporate Learning Solutions and Contract.
Construction Management At Risk Process
November 12, 2009 PM Process Improvement Plan: Employee Presentation.
The Project Management Process Groups
PRE-PROPOSAL CONFERENCE Welcome! American Air Power Museum 1230 New Highway, East Farmingdale, New York November 14, 2012 Management, Business Development.
OTE Building PMG Report March 2, 2012 Rhonda Merchut 1.
1 Professional Services Committee and DNS Work Group Charles Stripling Woody Hicks George McMahon May 18, 2011.
Information Technology Project Management, Seventh Edition Note: See the text itself for full citations.
PROJECT CONTROL Project Control Defined Types of Control Systems
Project Management for Treasury Professionals
Best Practices Consortium
The Port of New Orleans - As-Needed Consultant Selection Process for Professional Services June 9, 2016.
Award Set-Up and Advances
Business (Agency) Process Discovery and Documentation Workshop
Introduction Project Management.
Contract Basics For State Agencies.
Project Management Processes
12.2 Conduct Procurements The process of obtaining seller responses, selecting a seller and awarding the contract The team applies selection criteria.
PRE-PROPOSAL CONFERENCE
Chapter 3: The Project Management Process Groups: A Case Study
Achieving Strategic Goals while Supporting Operational Needs
Cost of Service Analysis & Rate Design
Chapter 3: The Project Management Process Groups: A Case Study
Developing and Issuing the RFP
Chapter 3: The Project Management Process Groups: A Case Study
Case Study: The Accounting Software Installation Project
Software Project Planning &
Chapter 3: The Project Management Process Groups: A Case Study
Post-Award Non-Financial Tasks
Chapter 12: Project Procurement Management
Two-Dam Independence Project Update
Outsourcing: Managing Interorganizational Relations
Legislative Budget Office (LBO) 2-Year Workplan
Project Management Processes
Introduction Project Management.
CANNABIS CONTROL COMMISSION
Variance Analysis Tool (VAT) Overview Session
Delta Water Supply Project
Southwest AWWA Conference 2018
CANNABIS CONTROL COMMISSION
Leveling the Negotiation Playing Field
Chapter 11 Project Control.
Change Order 4 Contract J06026C01 JIWRF Nonhazardous Site Lighting Upgrade Restore ED Original Delegated Authority Approve Changes to Total Contract.
Change Order 5, Contract S03003D01 Engineering Services for SSWRF Post-Secondary Capacity Improvements and Restore ED’s Original Delegated Authority.
Contracting & Coffee July 2019 nstxl.org.
Asset Management Plan Development and Implementation Support
Design and Engineering Services
Contract Award for the Colorado Street Bridge Suicide Mitigation Enhancements Project City Council May 20, 2019 Item # 7.
Presentation transcript:

Change Order Number Five, Contract M03037P01, Professional Services, 2050 Facilities Plan – Ultimate Build Out, and Approve Changes in Total Project Cost Commission Agenda Item # 10

2050 Facilities Plan Project Initiated 2014 Founded in Asset Management Milestone horizons: 2035, 2040, 2050 Four MMSD geographies: Conveyance/Storage systems Water Reclamation Facilities/Biosolids handling Watercourses Green Infrastructure

2050 Facilities Plan Project Innovative approach Develops customized tools Track risks Evaluate alternatives Prioritize investments

Change Order Number Five, 2050 Facilities Plan CONTRACT AMOUNT PERCENTAGE INCREASE OVER ORIGINAL CONTRACT AUTHORIZED BY   SWMBE Original $4,905,265 Commission 20.8% Change Order No. 1 $0 0.0% Executive Director N/A Change Order No. 2 $150,000 3.1% 33.4% Change Order No. 3 $1,325,158 27.0% 31.4% Change Order No. 4 Change Order No. 5 $1,653,191 33.7% Request of the Commission 17.5% Change Order Total $3,128,349 63.8% TOTAL $8,033,614 22.5% These are the 10 projects, but 11 contracts with budgets over $150,000 (ED Authority).

2050 Facilities Plan Project Change Past 5 Years: planning for facilities & asset management: Single, combined, efficient effort Focus primarily on AM Now: need critical answers: Major, long-term facilities investments Accelerated 2050 FP effort AM continue separately, focus on short-term WRF issues

2050 Facilities Plan Change Order 5 Primary Change Order tasks: Project management, collaboration, document writing Asset Management Plan, Chapters 1-4 Analyses: Conveyance/storage systems Water reclamation facilities/biosolids handling Watercourses Green infrastructure Public Involvement Nontraditional Amendment Approach: -Normally, when we identify extra tasks not in the original scope, the consultant costs them out and we either accept or negotiate the price -Here, knowing what we know several years into the game, we fully rescoped the project (adding in what we know is needed and removing AM post Ch 4), determined what the FP would cost to complete, and subtracted the amount of money that was still in the contract to arrive at the amendment. If Asked: Why significant changes to the scope? We didn’t know how involved the AM approach would become (FP’ing has never been done this way) At MMSD’s request per the RFP, we underestimated PM needs (large project, 2 dozen subs) We underestimated modeling needs We underestimated MMSD task leader and division director expectations Developed unexpected tools (BCEs, dashboards, $120K thing Other reasons for the sweeping changes? If Asked RE: costs to complete the work: Primary Amendment Tasks: Project Management, Collaboration ($489K) Asset Management Plan Ch 1-4 ($104K) Conveyance/Storage Systems ($563K) Water Reclamation Facilities/Biosolids Handling ($484K) Watercourses ($99K) Green Infrastructure ($106K) Energy ($24K) PI ($79K) Document Writing ($390K)

Project Cost/Schedule Cost requests: Contract amendment: $1,653,191 M03037 TPC: $1,653,191 Schedule change: Amended project completion date: December 2020 July Commission: Request to award AMP contract to Black & Veatch