Ward Park Restroom Timeline December 2016: $15,000 General Improvement Fund (GIF) Grant Approved June 2017: $15,000 Additional GIF Approved July 2017: Bid Opening $62,800 Low Bid (Key Builders) August 2017: Contract Signed 120 Days to Complete the Project once a Notice to Proceed has been issued
Ward Park Restroom Timeline September 2017: 9: $35,000 Additional GIF Approved 22: Pre-Construction Meeting Held at the Site City Contractor (Key Builders) Engineer (Schelle Architect) October 2017 3: Construction Started 120 Day Contract Estimated Completion Date: January 30, 2018
Ward Park Restroom Timeline November 2017 $35,000 GIF Resinded
October 3, 2017 Construction Begins
October 4, 2017
October 5, 2017
October 10, 2017
October 20, 2017
October 20, 2017
October 20, 2017
October 31, 2017
October 31, 2017
October 31, 2017
October 31, 2017
November 11, 2017
November 11, 2017
November 11, 2017
November 11, 2017
November 11, 2017
November 27, 2017
November 27, 2017
November 27, 2017
November 27, 2017
November 27, 2017
November 30, 2017
November 30, 2017
November 30, 2017
December 7, 2017
December 7, 2017
December 7, 2017
December 7, 2017
December 7, 2017