Big Stone II Study Update

Slides:



Advertisements
Similar presentations
AN INTRODUCTION TO THE MIDWEST ISO By Bill Malcolm Manager-State Regulatory Affairs Pierre, South Dakota June 9, 2006.
Advertisements

MI CNF T/D Page 1 T/D Group Update to CNF Overview of Transmission Transfer Studies Results of CNF T/D Studies – Lower Michigan Group Status Thomas Vitez.
Big Stone II Study Update SPG Meeting October 19, 2006.
March 26, 2014 Transmission Coordination and Planning Committee 2014 Q1 Stakeholder Meeting.
Power Grid Reinforcement Fall Presentation Team 9b: – Jon Brown – Kyle Reininger – Alan Myers – Karl Homburg – Dan Sinnott.
NTTG Economic Study and Biennial Study Update NTTG Economic Study and Biennial Study Update NTTG Study Cycle.
Arrowhead  Weston Transmission Line Project Dave Van House Minnesota Power.
Twin Cities Minnesota Zone Meeting Xcel Energy October 27, 2004 St. Paul, MN.
Buffalo Ridge Incremental Generation Outlet (BRIGO) Transmission Study Presentation to National Wind Coordinating Committee June 22, 2005 W Grivna, PE.
Houston Region Import Capacity Project August 27, 2013 Regional Planning Group Meeting.
WECC PCC Meeting Salt Lake City, UT March 26, 2014.
System Voltage Planning Brian Moss PD / Transmission Planning Transmission Planning Overview October 30, 2007.
WECC PCC Meeting Salt Lake City, UT July 16, 2014.
Andy Meyers ISAS Chair ISAS Report WECC Operating Committees March 2015 Salt Lake City, UT.
1 Green River Utah Area Transmission and Distribution System – January 16, 2009.
New Richmond Load Serving Study Northern MAPP Subregional Planning Group August 16, 2006 Daniel Kline.
George Bartlett Director, Transmission Operations Economic Transmission Projects Entergy Transmission Planning Summit New Orleans, LA July 8, 2004.
Potential Transmission Construction Scheduling In Southern Minnesota--- Fall Spring 2006 Xcel Energy has posted Significant Transmission construction.
ICT Strategic Transmission Plan (ISTEP) Review and Status Update Entergy Transmission Summit July 29, 2008 Astor Crown Plaza New Orleans, Louisiana Douglas.
Report on the NCTPC 2006 Collaborative Transmission Plan Mark Byrd, Manager – Transmission Planning Progress Energy Carolinas, Inc January 25, 2007.
NERC Congestion Management Congestion Management Option 3 Vendor Meeting Julie Pierce – NERC IDCWG Chair.
2006 Reliability Study Scope Name Date. DRAFT 2 Purpose of Study Assess the PEC and Duke transmission systems’ reliability Develop a single reliability.
0 CapX /1/2015 CapX 2020 Transmission Plan: Ensuring Reliable Electricity.
Peak RCCo Performance Metrics Draft –November 2013.
1 Transmission Advisory Group Meeting January 25, 2007 Raleigh, NC.
1 Transmission Line Projects in Maryland – an Overview Sandra S. Patty PPRP - Manager, Transmission Projects PPRAC Meeting Country Inn & Suites, Annapolis,
2015 Summer Shoulder-Peak Near-Term Assessment of Transmission System Performance ~ Board of Directors Meeting September 30, 2010 Presented by Jeff Mitchell.
Page 1© 2009 Quanta Technology LLCPage 1 November 2007 BGE January 4, 2008 Strategic Midwest Area Renewable Transmission (SMART) Study October 06, 2009.
SM April Peak Week Operations Review Presentation to ISO Business Issues Committee May 22, 2002.
MISO Northwest Exploratory Study Presented to National Wind Coordinating Committee Participants in study – MISO, Various utilities in Minnesota, North.
Entergy AFC Stakeholder Meeting February 16, 2005 Houston, TX.
CMWG Update WMS September 2015 Meeting. CRR Balancing Account Fund Discussion The CRR Balancing Account fund appears to be working as expected The cap.
Big Stone II – Delivery Study Phase 6 and Supplemental #2 For Northern MAPP SPG Meeting 4/3/07 Elk River Richard Dahl Missouri River Energy Services.
SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX.
SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting June 20 th, 2008 Austin, TX.
Joint BPS and ESS/ITS ATC/AFC Subcommittee Update November 2007 – January 2008 February 5, 2008.
ESI Alternate Economic Study Process E-RSC Meeting October 21, 2010.
Coordinated Planning Concept (For Discussion Only) revised 11/30/04 07/01/04.
Update on the North Carolina Transmission Planning Collaborative January 30, 2007 For the North Carolina Utilities Commission and the North Carolina Public.
2006 Reliability Study James Manning Bryan Guy May 12, 2006.
June 11, 2010 RPG Meeting Houston Import Study Update Jeff Billo.
2006 Preliminary Reliability Study Results Bryan Guy September 7, 2006.
BPA Pacific DC Intertie (PDCI) Upgrade Project WECC Path Rating Process PDCI 3220 MW North to South Phase 1 Kick-off Meeting October 23, :00-4:00.
Congestion Management Work Group 2008 Overview CMWG Marguerite Wagner, Reliant Energy Inc.
DRAFT – FOR DISCUSSION PURPOSES ONLY © 2013 New York Independent System Operator, Inc. All Rights Reserved. EIPC Roll-Up Powerflow Model Zach Smith Director,
October 15, 2012 PV & Storage Workshop ERCOT’s Interconnection Process John Adams Principal Engineer.
1 NPCC – A-2 Dr. Mayer Sasson Transmission Planning Consolidated Edison of New York June 1, 2006 Presented to the NYSRC-RRS.
TEP RMR Workshop Presentation1 Workshop on ACC RMR study submitted with 2004 ten year plan Tucson Electric Power January 15, 2004 Ed Beck Supervisor Transmission.
Reliability Must Run Workshop RMR Study Process May 24, 2016.
Minnesota Renewable Energy Integration and Transmission
Freeport Area Master Plan Project -
CSC DETERMINATION PROCESS
Transmission Planning in ERCOT- Overview
2016 RTP Update November, 2016 RPG Meeting.
Status of the Planning Working Group’s (PWG) Efforts
Troy Anderson ERCOT Program Management Office November 6, 2008
Western Electricity Coordinating Council
I-5 Corridor Reinforcement Project
MRES Resource Operations in SPP
DEC System Voltage Planning - June 2018
UK Link Technology Refresh
Agenda Provide a recap of primary northern route alternatives for the MPRP Describe basis for selected route N5 Overview of analyses performed Description.
2019 Attachment O customer meeting
2017 Attachment O Customer Meeting
345 kV Bailey-Jones Creek Project Anticipated Project Schedule
Palo Verde-COI RAS Retirement
Palo Verde-COI RAS Retirement
Excelsior Energy’s Mesaba Energy Project
NERC Congestion Management
345 kV Bailey-Jones Creek Project Anticipated Project Schedule
Presentation transcript:

Big Stone II Study Update SPG Meeting October 19, 2006

Presentation Overview Summary of September 18 MAPP DRS Mtg. Interconnection Study Delivery Service Study Phase 5 Summer Off-peak Analysis Model Assumptions Results Upcoming Schedule

Recap of Sept. 18 DRS Mtg. Interconnection Study Presentation given to MAPP DRS Discussion led to conditional approval of the IC study with 4 follow-up items: Verify ND Load Levels in Stability Models Arrowhead-Weston 345 kV Stability Sensitivity Resolution of local stability issues Update DRS once transmission option selected by the MN PUC

Recap of Sept. 18 DRS Mtg. Delivery Service Study Presentation given to MAPP DRS Discussion led to identification of 4 follow-up items before DRS will take action on study. Finish Phase 5 analysis (Summer off-peak study) Prior outage analysis of Phase 3 models Deeper explanation of flowgate analysis Identify fixes for delivery related issues (revise motion)

Phase 5 – Summer off-peak High Simultaneous transfer case Phase 5 only for DRS review. Submitted to the DRS on Sept 29th for review at the November 2nd meeting Not part of MISO submittals

Technical Scope This phase is steady state only Base case is 2006 summer off-peak case from the NMORWG package with: MHEX South = 2175 MW NDEX = 1950 is base case – raised with Big Stone II MWSI = 1480 MW prior to Arrowhead – Weston in service. Maintained at such level prior to Arrowhead – Weston throughout study. Since this case has maxed out interfaces, the model does not reflect existing firm commitments. Baseloads within NDEX @ URGE Load within NDEX approx @ 70% NMORWG TITLE: URG-S7006AA.UZVV424.SAV

Powerflow model additions Added some new topology: Split Rock – Nobles Co. – Lakefield 345 kV Lakefield – Fox Lake 161 kV #2 Arrowhead – Stone Lake – Gardner Park 345 kV Series Compensation of Lakefield – Wilmarth 345 kV Upgrades associated with Council Bluffs 4 and Nebraska City 2 Other miscellaneous model changes in addition to this

Study BSP II output sunk to generation similar to that of Phase 3 and 4 of the Delivery Study One scenario for each of the two interconnection alternatives studied.

Results Thermal overloads observed, and impacted above 2% DF: Big Stone – Blair 230 kV. Loaded between normal and emergency rating Granite Falls 230/115 kV xmfrs Aurora – Brookings 115 kV Arlington – Watertown 115 kV Brookings – Watertown 115 kV McLeod 230/115 kV xfmr Granite Falls – Morris 230 kV Morris 230/115 kV xfmr Watertown 345/230 kV xfmr Johnson Jct. – Ortonville 115 kV Grant County – Hoot Lake 115 kV

Results - continued Part of this study is to identify if TTC of interfaces would be reduced because of this project. Note that the model is not reflective of firm commitments. Two of the thermal issues seen is part of the current NDEX interface definition: Big Stone – Blair 230 kV Morris – Granite Falls 230 kV No new steady state voltage concerns observed. Discussion on what the constraints that will have to be mitigated will be held at the DRS meeting.

Upcoming Schedule November 2 DRS Mtg. December 7 DRS Mtg. Discuss Phase 5 Analysis December 7 DRS Mtg. Discuss Remaining Follow-Up Items December 31 Draft IA MISO Approval of IC Study January 2007 Begin Phase 6 Analysis Sensitivity to EHV line and other regional transmission projects