Mytholmroyd FAS Progress Update

Slides:



Advertisements
Similar presentations
Bewdley Flood Alleviation Scheme. Bewdley, November 2000.
Advertisements

NGfL CYMRU GCaD FLOOR COVERINGS.
THORNE GROUP Earthworks : Recycling : Reclamation : Demolition : Dismantling THORESBY LAKE PHASE 1 PRE-SUBSIDENCE WORKS Client: UK COALConsultant: Black.
Measurement for Civil Engineering works
Management of future floods at Cockermouth LO: To be able to explain how a specific riverine area has been managed.
Christchurch City Council footer text Flood Taskforce Flood risk in Sumner and Moncks Bay.
Huntly Flood Alleviation Scheme
Skyscraper Construction
Northumbrian Water Ouseburn Flooding - Brunton Park Meeting 17th January 2006.
Route 50 Widening Design/Build Project. 2  Virginia Department of Transportation  Shirley Contracting Company  Dewberry  Fairfax and Loudoun Counties.
Management of Surface Water in Severe Weather Conditions from the Highway GORDON HUNT COUNTY DRAINAGE ENGINEER for OXFORDSHIRE COUNTY COUNCIL.
Hargrave Street Pumpstation – Site Preparation July 2014.
Birr Public Realm Work achieved to date February
Chapter 34 Bridge Construction.
Village of Alden Stormwater Pictorial view. Here is a view of rainfall and notice how the water carry’s away from the center of the road to the sides.
John James Audubon Bridge Main Span Materials and Equipment Cement from Thailand Structural Steel from Japan Oscillator from Germany Wind tunnel analysis.
HOUSE BUSINESS COMMITTEE PRESENTATION BY GHRC ON CITY GATE PROJECT 13 th October, 2014.
Drainage Services Department Drainage Project Division Contract No. DC/2007/01 Contract Title: Drainage Improvement Works in Ki Lun Tsuen, Kwu Tung, Ma.
Foundations. Foundation supports weight of structure –Includes soil and rock under foundation –Building construction described by foundation type Slab.
Now is this a high risk job?. HIGH RISK JOBS – RED CODE WORKING WITH ASBESTOS, OR UNDERTAKING A JOB WHERE THERE IS A LIKELIHOOD THAT ASBESTOS IS PRESENT.
CONSTRUCTION.
Sanitary Engineering Lecture 16
Preliminary studies for Muon shield modification to accommodate LCLS II Alev Ibrahimov December, 2010 BSY.
John Osborne GS/SE March 2013
Superstructure Replacement Substructure Repair Rehabilitation of I-95 Bridges 11 Bridges Along I-95 Corridor
Prefabricated Timber Frame Construction
Manitoba Floodway Authority Manitoba Floodway Authority FLOODWAY EXPANSION GROUNDWATER ACTION RESPONSE PLAN 1. OVERVIEW GROUNDWATER IS A TOP PRIORITYGROUNDWATER.
The West London Free School Palingswick House Update.
Bridge Building Timelines Presented by The Richland County Engineers Office Thomas E. Beck, PE, PS 77 North Mulberry Street Mansfield, Ohio Jan.
Other Construction Projects
Introduction to a pit installation
1 MICE - INFRASTRUCTURE MICO meeting 7 th February 2008 Tim Hayler.
Building for Learning Project Photo Progress Report 3 October 2009 – November 2009 Project commencement 21 st September 2009.
Caythorpe Gas Storage Project Liaison Committee Meeting 28 th September 2009.
Chapter 33 Dam Construction. Objectives After reading the chapter and reviewing the materials presented the students will be able to: Give reasons why.
Joints for Diaphragm Walls
York floods November mm rain in 24 hours 3000 people evacuated, Army called in to help Ouse 4.8m above normal levels 80,000 sandbags used.
Town of East Greenbush Waste Water Treatment Plant Project Monthly Update – September 2014.
Typical Bridge Components
Wetland Restoration Planning considerations New Forest Consultative Panel – 3 Sept 2015.
Hayesbrook Community Pavilion. Aims St Stephen’s Church offers a variety of activities open to the whole community including Youth Clubs (Young & Old.
WBS Experiment Infrastructure: LArTF GPP Project Status Dixon Bogert Prepared for the MicroBooNE Collaboration Meeting 11/02/12.
Index Temporary Works: No.Subject 1Timber Trenches 2Timber Scaffolding.
Concrete Repair.
TOTAL BRIDGE REPLACEMENT OF M-13 OVER CHEBOYGANING CREEK
Introduction Bridges are inspected for three primary reasons
Prefabricated Timber Frame Construction
Temporary Works – P8 Project Practice.
Boscastle - the most frightening flood of the decade?
Potholes Supplemental Feed Route Project
B.V.Patel Institute of Technology-Diploma studies
US26: Cornelius Pass Rd -185th Ave
Safety Tip FQ18086 RHODE ISLAND AVENUE METRO STATION TRACK DECK AND PRE-CAST PANEL REHABILITATION Please use full fall Protection gear when using 6’ or.
Arch205 building construction foundation
Course Contents Culverts Bridges Buildings 20 November 2018.
Church of Uganda Kisiizi Hospital
Scheduling Project Assignment 3 Team A.
Presenter Tony Bosnich 2015
Pier Foundations Piers Suspended floor Ground beam Next slide.
Illinois Waterway 2020 Consolidated Closure
Contract 60X10 Informational Meeting Weber I-55
RISER PROJECT F bathroom.
Mytholmroyd Flood Alleviation Scheme
Construction Considerations
Kaituna River Re-diversion and Te Awa o Ngatoroirangi / Maketū Estuary Enhancement Project 7 November 2018 Community Meeting Murray Brock video.
Harbour Island Force Main Replacement
A133 IPSWICH ROAD SCHEME COMMUNICATION UPDATE ( )
A133 IPSWICH ROAD SCHEME COMMUNICATION UPDATE ( )
6th. Semester Schedule: 1st. Week
May 9, 2019.
Presentation transcript:

Mytholmroyd FAS Progress Update Slide 1: Mytholmroyd FAS Progress Update This picture and the next underpins the reason for undertaking the scheme. This is taken from Caldene Bridge showing the River Calder on Boxing Day 2015. This bridge is one of the main constrictions to flow in the village Calderdale Flood Partnership Board – 19th July 2019 Paul Swales FCRM Advisor

Overview Area I (Rochdale Canal works) Area L1 & L2 (Brearley and Luddendenfoot) – downstream mitigation Slide 2: Overview This scheme will reduce risk from River Calder, Cragg Brook, an ordinary watercourse, Rochdale Canal and surface water run-off The works involve channel widening (Area E and C), a new bridge and demolition of existing one, demolition of 10 properties (2 residential and 8 commercial), raised and/or strengthened flood walls, glass panelling, safety hand railing, a new footbridge (Area G), new surface water outfalls, canal works including a new overflow and property flood resilience

Area B – Greenhills Industrial Estate Slide 3: Area B – Greenhills Industrial Estate Planning permission has now been granted for Area B following objections from Network Rail Temporary scaffold is in place on left and right banks Commenced hand excavation works on left bank following the installation of a temporary fire escape Look ahead Excavate right bank and prepare concrete blinding for new walls Place pre-cast walls right bank Prepare concrete bases for downstream walls on left bank Commence removal of brickwork to corner of Lumalite building

Area C – St Michaels Church Slide 4: Area C – St Michaels Church Before

Area C – St Michaels Church Slide 5: Area C – St Michaels Church Spray concrete has been applied to the piles and stone cladding is nearing completion Removed existing wall at enterprise centre prior to re-build

Area C – St Michaels Church Slide 6: Area C – St Michaels Church Downstream of New Road bridge hard landscaping is all but complete – masonry and copings are complete, glass panels and flap valves installed and the majority of the area is open to the public

Area C – St Michaels Church Slide 7: Area C – St Michaels Church Look ahead Safety hand railing is being installed this week – left and right bank Hard landscaping to area of old toilet block has now commenced

Area C – St Michaels Church Slide 8: Area C – St Michaels Church Look ahead Hard landscaping to area of old toilet block has now commenced

Area C – d/s of St Michaels Church Slide 9: Area C – d/s of St Michaels Church Sheet piling and channel widening looking upstream – stone pitching will continue in the area Look ahead: works to start to rear of Burnley Road cottages, flood proofing properties up to flood defences level and installation of non-return valves

Area D – Cragg Brook/River Calder Confluence Slide 10: Area D – Cragg Brook/River Calder Confluence Before

Area D – Cragg Brook/River Calder Confluence Slide 11: Area D – Cragg Brook/River Calder Confluence This shows the new reinforced concrete wall with cladding where 18-22 New Road used to be. Temporary scaffold in place for raising floor levels of 14-16 New Road. Flood proofing works to rear of the Deli are progressing also. It is a slow job due to constrained access Final section of Streamside Fold has now commenced – 1 and 2 is underway. Rest of Streamside Fold is essentially complete, i.e. flood walls and copings. Garden reinstatement is ongoing Bridge End is complete including walls, masonry cladding and coping units. Glass panels are now installed.

Area E – Caldene Bridge Slide 12: Area E – Caldene Bridge Bridge deck steel reinforcement and mega trusses

Area E – Caldene Bridge Slide 13: Area E – Caldene Bridge Deck concrete pours completed. Strength for deck has been achieved so falsework stripping started. Mega trusses to be removed this week River Calder LB works upstream Caldene Bridge ongoing with precast unit install and masonry cladding to dry side progressing. Monday night closures have progressed with minimal incident. River Calder RB piling completed (excluding Calder Grove to Caldene Ave Bridge abutment) - three sections of capping beam concreted.

Area E – Caldene Bridge Slide 14: Area E – Caldene Bridge Crane in position on new bridge deck ready to remove falsework Continue to work with utility companies, CMBC and Fire Service with regards to diversion works. Temporary work in fire station forecourt starting next week – 8 weeks with diversion for traffic starting in mid-September

Area E – Caldene Bridge Slide 15: Area E – Caldene Bridge Mega Truss being removed

Area E – Caldene Bridge Slide 16: Area E – Caldene Bridge YW have installed 4 permanent diversion water mains through ducts in the deck. YW have completed the pipework and valve arrangements to two 100mm mains in Caldene Ave. YW have completed excavation for the twin 200 pipes to be extended into Caldene Ave. VBA removed temp works on Burnley Rd to facilitate YW pipeworks.

Area F – Upstream of Caldene Bridge Slide 17: Area F – Upstream of Caldene Bridge RB Caldene Ave gardens work nearing completion. Hard and soft reinstatements ongoing.   LB Access to the working area has started from 10 June just downstream of Whitehouses. This working area may serve Burnley Road wall works as well. Knotweed spraying completed and hardstanding established.

Area F – Upstream of Caldene Bridge Slide 18: Area F – Upstream of Caldene Bridge Pre-cast wall units in position on Burnley Road

Area H – White Lee Clough Culvert Slide 19: Area H – White Lee Clough Culvert New headwall and trashscreen at culvert inlet has been installed The culvert overflow now has planning permission so Mabel St access has started this week with track matting – construct outlet chamber A significant obstruction has been removed from within the culvert – re-design not required

Area I1 - Mayroyd Slide 20: Area I1 - Mayroyd New wall is nearing completion to prevent the River Calder entering the Rochdale Canal. Works to start on earth embankment

Area G – Cragg Brook Area I3 – Brearley Canal Overflow Area K – Scarr Bottom Cottages Area L1 – Brearley Area L2 – Luddenden Foot Slide 21: Other elements of the scheme Area G – this is complete – small piece of landscaping to finish Area I3 – we have been delayed on this due to Vodafone diversion works but this has now commenced. Towpath diversion is required so need to apply for this (4 weeks) – likely not to start until mid-August at the earliest Area K – planning submission is on hold due to design issues. Options have now re-visited and discussed with CMBC planners last week. They have confirmed their position and next steps are to meet with affected resident to discuss options Area L1 – planning is still on hold due to requiring Listed Building Consent – designers are working on a heritage statement to be submitted alongside the planning application Area L2 – planning has now been granted. We are awaiting cost from VBA for a walled option to rear of Tillotson Holme bungalows.

Questions?