Tuesday 6th April 8:00 Injection studies 16:00 RF studies

Slides:



Advertisements
Similar presentations
8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
Advertisements

LHC 23 June :07: Started injection cleaning with B1. 08:13: Fault on MKI B2. –MKI Beam 2 in P8 had a breakdown at 07:49 during the SoftStart process.
LHC 1 st August :34 Dump on TDI.B2 jaw position while filling –Checks and change TDI.B2 reference position by 0.1 mm outwards 09:40 Lost cryo in.
Nominal intensity bunches ● First ramp with nominal intensity bunches suffered from an instability appearing around 1.8 TeV. ● Nominal intensity bunches.
Tuesday 17 th April 04:00 Prepare second fill for v/d Meer scans. 06:22 Stable beams, v/d Meer scans for Alice and LHCb. 13:20 End v/d Meer scans.Dump.
Some ideas for/from the SPS LIU-SPS team. Scrubbing (only) for ecloud in SPS? aC coating remains baseline..... –but scrubbing has many potential advantages.
LHC Progress Thursday 29 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
09:25 Operator dump fill #2178, integrated lumi 107/108/18 nb-1. Trip of RQ4.R6 (fire heaters discharged) just after the beam dump but the QPS gave no.
LHC Injection Sequencing MD 16/23/2009 Injection sequencing / BCM R, Giachino, B. Goddard, (D. Jacquet), V. Kain, M. Meddahi, J. Wenninger.
Prepared by M. Jimenez AT Dept / Vacuum Group, ECloud’04 Future Needs and Future Directions Maximizing the LHC Performances J.M. Jimenez …when Nature persists.
Saturday 9 th April 10:24 Finally « 600 » bunches 14:30 Dump the 600 x :00 Loss maps Green light for 800 bunches 18:40 Fill for 800 bunches 20:48.
Injection and protection W.Bartmann, C.Bracco, B.Goddard, V.Kain, M.Meddahi, V.Mertens, A.Nord, J.Uythoven, J.Wenninger, OP, BI, CO, ABP, collimation,
Injection status W. Bartmann, C. Bracco, B. Goddard, V. Kain, A. Macpherson, M. Meddahi, S. Redaelli, J. Uythoven, J. Wenninger LIBD Meeting, 20 th Sept.
Benchmarking Headtail with e-cloud observations with LHC 25ns beam H. Bartosik, W. Höfle, G. Iadarola, Y. Papaphilippou, G. Rumolo.
Floating MD week 28 summary
Ralph Assmann, Giulia Papotti, Frank Zimmermann 25 August 2011
MD Planning Fri – Sat (26. – 27.8.)
Wednesday 8.9 External crossing angles:
Cryo Problem MD Planning Tue (1.11.) C B Day Time MD MP Tue 01:00
Beam dump at 03:00:
Machine Coordinators: G. Arduini, J. Wenninger
SPS extraction, transfer lines, injection
-9:00: Test IP transverse adjustment (CMS) and optics verification.
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Monday :00 Stable beams 9_6_6_6 13:40 Access.
Monday h00: Ramp 10 A/s (chromaticity, crossing angle non-closure, beta-beating): At 7m and 3.5m, put in one by one crossing angles, calculated.
Friday 07:00 Power glitch on the EDF network. Point 8 affected.
LHC Status Wed Morning 13-April R. Assmann, B. Holzer et al
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
Thursday morning – optics correction
LHC Morning Meeting - G. Arduini
Summary of week 44 Aims of week 44 J. Wenninger & J. Uythoven
Thursday 17th May 01:11 Fill #2633 dump in squeeze arc circulator load channel Ad1B 03:16 Fill #2644 Stable beams, lumi 5.2e33 cm-2s-1 04:38 Dumped by.
LHC commissioning Week 38
LHC Injection and Dump Protection
Summary of Week 16 G. Arduini, J. Wenninger
Lost at 12:05 to power converter (RTQX2.R1) problem
Note: squeeze in Atlas, CMS, LHCb and Alice on going
Mon 22/8 – Tue 23/8 00:07 stable beams #2040. Initial luminosities: 2.1x1033 cm-2s-1 18:00 Programmed dump. End of physics #2040. ~83 pb-1 in ~18 hours.
Scrubbing progress - 10/12/2012
Saturday 2/4/ :00-09:00 Problems with SPS:
Tuesday 9th November 10:02 Fill beams dumped
450 GeV Initial Commissioning with Pilot Beam - Beam Instrumentation
Wednesday 03/11 – The Plan Finish electron-cloud program:
Saturday 7th May Sat – Sun night
Tuesday morning 09:30 Beam dump, SIS dump due to lost connections with FCG FECs. Coincides with starting a development SIS server to test new interlocks.
Sunday/Monday & :30 Stable beams. Fill #1851.
Monday 24 October hours of 25ns MD
Tuesday 17/5 10: TeV - colliding. Start roman pot alignment ...
Thursday 04/11 - Morning Access until ~13:00 Pre-cycle Proton checks:
Wednesday 13th 9:30 Stable Beams… with 1 pilot and 2 nominals
Collective effects in the SPS and LHC (longitudinal plane)
Monday :00 – 15:00 : Stable beams 15:30 : Recover…
Tuesday 20 September 2011.
Fri :52 Stable beams fill #2536
Thursday 30th September De-bunching test
Wednesday 6th April Injection of 50 ns up to 108 bunches (3 x 36).
Wednesday h18: 228b fill lost just before start of ramp.
Thursday - setup 10:00 Starting pre-cycle. 11:30 Injection.
Injection Studies: 50 ns ABT/BTP.
Friday h55 Stable beams. Fill #1841. Lumi ~1.2e33.
Wednesday 14:30 Fill 2011 dumped.
Wednesday morning / afternoon
Monday 14th May 00:03UFO at BLMQI.06R8.B2E10_MQML. Beam dump Re-steering required for TI2 03:28 STABLE BEAMS # e11 ppb, 4.11e33 cm-2s-1 13:36.
Saturday 15th May One bunch 1 e11 per beam 09:57: start ramp
Tuesday
Thursday 10:00 Fill 1986 in stable beams.
Tuesday
Presentation transcript:

Tuesday 6th April 8:00 Injection studies 16:00 RF studies RF set-up 50 ns trains Injection of 50 ns trains, 36 bunches Scrubbing 16:00 RF studies 17:00 Collimation, loss maps at 450 GeV 23:00 Scrubbing with 50 ns trains 6/4/2011 LHC 8:30 meeting

Injection studies 50 ns trains Injection 50 ns up to 36 bunches operational. Very clean: maximum losses from uncaptured beam - 10 % of dump threshold, losses on TCDIs maximum 1% of dump threshold. Injection slot cleaning and abort gap cleaning always on. Injection slot cleaning, reduced the losses on the TDI by a factor 3. Correct scraping in SPS is essential. Emittance does not change with scraping: emittances always between 2.2 and 2.3 um. Scraping really only tails. Managed to inject cleanly bunch intensities up to 1.4e+11. Satellites after first batch of intermediate intensity, 12 bunches. Injection of batch 580 RF buckets after this first batch kicked out beam onto TDI and tripped ALICE BCM. For the moment should not inject beam too close to intermediate intensity batch. Investigating on booster/PS side. 6/4/2011 LHC 8:30 meeting

Satellites were confirmed by LDM. First 12 bunches 36 bunches Satellite < 1% of peak bunch intensity but get swept into experiment by the LHC injection kicker Adam Jeff 6/4/2011 LHC 8:30 meeting

LDM measurements Satellites are also seen with 25ns spacing between the bunches of the 12-bunch train up to 3% of main bunch, this is not seen between the bunches of the 36-bunch trains. 6/4/2011 LHC 8:30 meeting

Scrubbing while performing injection set-up Vacuum after 5th batch of 12 bunches, 50 ns 6/4/2011 LHC 8:30 meeting

Scrubbing with trains of 36 bunches 6/4/2011 LHC 8:30 meeting

Collimation checks at 450 GeV Loss of hierarchy not understood for B1 H Many, many loss maps at 450 GeV Series of loss maps on B1 with different conditions to try and reproduce the leakage observed in the last days: very high coupling (0.02) kicks with a single corrector in-phase and out-of-phase with the TCSG in 7. Conclusions: Coupling seems to have no effect As expected orbit has an effect above 0.5 -1.0 sigma excursions: OK Loss maps under normal conditions were ok 6/4/2011 LHC 8:30 meeting

Scrubbing with 50 ns trains of 36 bunches Finally scrubbed with 288 bunches, trains of 36 Started with e-cloud MD filling scheme(s) Needed to inject with 2 us spacing between trains Stopped in beam 2 because of a pressure rise in point 2 very close to the interlock limit after 3 injections. 6/4/2011 LHC 8:30 meeting

Bunch lengths – beams unstable vacuum rise, coherent motion and emittance growth have been observed with several batches of 50 ns beam. More analysis is needed, but we can already say that the behaviour is very similar to what we observed last year (horizontal instability that affects the last bunches of the batches and also seems to cause large emittance growth at the end of the batches). The perturbation appears to build up with the number of batches until the motion and emittance grows really strong. For some reason, bunches and batches that are injected after these seem less affected. 6/4/2011 LHC 8:30 meeting

Plan for Wednesday Injection studies Collimation verification ? Injection of 50 ns trains, 72 bunches ... Collimation verification ? Aim is to be able to increase the 300 bunch limit at 450 GeV Scrubbing with 50 ns beams – longer trains 6/4/2011 LHC 8:30 meeting