Weekly Status Report Week of 11-03-07 Team Indigo S. MacNaughton, C. Downs, D, DeMeo This Week Project Plan due 11-10 by C. Downs Ready Project Status Report by 11-9 S. MacNaughton System Engineering Diagram R2 by 11-9 by D. DeMeo Website Updated and Digital Drop Box created by D.DeMeo and S. Mac www.ece.tufts.edu/~ddemeo01 http://drop.io/dcsindigo Password: design Meet with Project Advisor 11-14 – all Re: Current source and parasitic capacitance Prototype by January Next Week Further Howland Current Source and Capacitance research by C. Downs by 11-16 Part list for current source by 11-16 by C. Downs Order chip(AD8302) by D. DeMeo by 11-16 Project Proposal R3 if necessary by S. MacNaughton by 11-16 Long Term Research Sensing Coils by 11-30, Design Coils by approx. 12-20 Finish Specifications on Chip Set so able to Order Sample Parts by 11-30