Lafayette New Terminal Program Update February 13, 2019
Terminal Program Update FAA On site FAA Resident Inspector Currently managing grants LA DOTD Terminal Program Update
Terminal Program Update LA FP&C Received Cooperative Agreement for FP&C contribution to QTA Coordinating with FP&C to confirm bid process and eligible items for terminal contribution 2019 Capital Outlay Application submitted Applying for $7 million towards terminal construction to be available next Fall EDA Grant Application Revised EDA grant application submitted. Awaiting date for Decision Committee TSA OTA Application Submitted Grant Application, Waiting on Feedback Terminal Program Update
Terminal Program Update Airlines Working with Airlines to discuss leasable space and an agreement to buildout space in New Terminal QTA \ Ready Return Continued to meet with Rental Car Companies, moving forward on QTA Lease Rates Working with FP&C on approvals for NTP Concessions
Terminal Program Update Enabling Demo Demolition - Complete AOA fencing and gates – Complete Fill Material and Asphalt – Complete Seeding/Sod – Complete Substantially Complete Reviewing completion paperwork and waiting on 45-day lien-free period Final Acceptance - upcoming Terminal Program Update
Terminal Program Update Rental Car Quick Turn Around Facility Timeline: Oct. 2018: Commission Approved Updated CFC Nov. 2018: Construction Bids Due Dec. 2018: Approved Bids Jan. 2019: FP&C Construction Concurrence Feb. 2019: Award Contract Apr. 2019: NTP Feb. 2020: Construction Complete Terminal Program Update
Terminal Program Update GMP 1: Approved 9/25/18, Notice to Proceed 11/12/18 Terminal Program Update Description Est. Start Sub. Comp. Project 1 - RTR Cable Relocation Nov. 2018 Mar. 2019 Project 2 – RTR Facility Jun. 2019 Project 3 – Terminal Foundations Jan. 2019 Jul. 2019 Project 5 – Enabling Parking GMP 2: Approved 1/15/19, Notice to Proceed 1/15/19 Description Est. Start Sub. Comp. Terminal Structural Steel, Elev. and Escalators Jan. 2019 Nov. 2019 GMP 3: Terminal Building Shell, MEP and Finishes 100% Design to complete in Feb. 2019 Bidding in Feb./ Mar. 2019 Approval by LAC May 2019
GMP1 – Project 1 New Terminal Construction Update Project 1 – RTR Cable Relocation Manholes 1 through 4 set and backfilled. Cable wire pulled, spliced, and the FAA will cutover to the new RTR cable this week GMP1 – Project 1
GMP 1 – Project 2 RTR Facility New Terminal Construction Update Project 2 – RTR Facility Slab pour - complete Duct banks for the RTR cable from the building to tower – ongoing GMP 1 – Project 2 RTR Facility
GMP 1 – Project 2 RTR Facility New Terminal Construction Update Project 2 – RTR Facility CMU installation – ongoing Truss/framing installation – upcoming GMP 1 – Project 2 RTR Facility
GMP 1 – Project 5 Enabling Parking New Terminal Construction Update Project 5 – Enabling Parking Storm drainage installation – complete Underground electrical rough in – complete Economy lot – site grading and compaction – ongoing Short-term parking lot re-striping – ongoing GMP 1 – Project 5 Enabling Parking