Richard M. Boyce FAC Review – Accelerator Installation October 29-31, Installation – Accelerator Systems Installation Planning.
Advertisements

FAC review, 10/27 D. Schultz 1 e-Beams System Update Injector System Installation has started. Linac System Preparing for ’06 installation. Controls System.
FAC, 10/12/06 D. Schultz 1 e-Beams Systems Update Linac Injector Undulator Production MMF commissioning ARR David Schultz.
FAC, 4/20/06 D. Schultz 1 e-Beams System Update Linac System Preparing for downtime installation. Injector System Installation has started. Undulator System.
Paul Emma LCLS FAC April 16, Initial Experience with Injector Commissioning P. Emma, et al. Facilities Advisory Committee.
John N. Galayda LCLS FAC 20 April Linac Coherent Light Source Overview and Charge Facility Advisory Committee John.
Eric Bong LCLS FAC Injector-Linac October 27, 2005 Injector Design / Diagnostics / Gun & Linac RF Design E. Bong LCLS FAC.
FAC, 4/16/07 D. Schultz 1 e-Beams Systems Update People ARR Linac Installation Undulator Production MMF Operations David Schultz.
LCLS Linac System Management Linac Coherent Light Source Stanford Synchrotron Radiation Laboratory Stanford Linear Accelerator Center.
D. Schultz FAC 6/17/08 1 e-Beams Systems Update People Progress the last review LTU and Dump Installation Status Undulator.
Stephen Milton Undulator System 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.
Hamid Shoaee LCLS FAC Controls June 17, LCLS Control System Personnel Linac & BC2 Controls progress LTU, Dump Controls.
Eric Bong LCLS FAC Injector-Linac System October 27, 2005 Injector –Linac System Overview E. Bong LCLS FAC October 27, 2005.
Hamid Shoaee LCLS FAC Review – October Control System Overview Hamid Shoaee Controls System Manager Injector control system commissioning & Support.
Geoff Pile LCLS Und. System Fabrication FAC 29 th, 30 th & 31 st October 2007 LCLS Undulator System Fabrication Schedule FAC.
David H. Dowell Injector Physics/Diagnostics/Gun&L0 RF April 29-30, 2004 Injector Physics / Diagnostics / Gun & L0 Linac.
Hamid Shoaee Accelerator Readiness Dec. 2, ‘08 SLAC National Accelerator Laboratory Controls Department LCLS Maintenance.
FAC, 10/12/06 D. Schultz 1 Readiness for 2007 Startup Linac Injector Controls ARR David Schultz.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
Injector Accelerator Readiness Review, 10/31/06 Henrik Loos 1 Beam Losses During LCLS Injector Phase-1 Operation Scope of phase 1 operation Operating modes.
1 BROOKHAVEN SCIENCE ASSOCIATES Preparations for Linac Commissioning Ray Fliller, Associate Physicist 8 th ASAC meeting for NSLS-II Project May 10-11,
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
David Schultz Accelerator Readiness Dec. 2, ‘08 SLAC National Accelerator Laboratory 1 Undulator Complex Status LCLS Introduction.
LCLS Accelerator SLAC linac tunnel research yard Linac-0 L =6 m Linac-1 L  9 m  rf   25° Linac-2 L  330 m  rf   41° Linac-3 L  550 m  rf  0°
The Stripping Foil Test Stand in the Linac4 Transfer Line
Marjorie Widmeyer LCLS Injector Magnet Power March 30, LCLS Injector, Sector 21 and BC1 DC Magnet Power and Control.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
Maintain a single control room for all accelerator programs
Injector Performance Requirements Conventional Facilities Update
LCLS Injector: Introduction D. H
LCLS Linac Update Brief Overview L1 & BC1 Progress LTU & E-Dump Status Continuing Resolution Impact.
Injector –Linac Status & Schedule E. Bong LCLS FAC October 12, 2006
LCLS Gun Commissioning Status & Plans David H
LTU/Undulator Installation Status
LCLS Injector Commissioning Dates ( )
Advanced Research Electron Accelerator Laboratory
e-Beams Systems Update
Linac/BC1 Commissioning P
Electron Beam Systems ETC and Methodology
Injector / Linac Installation Current Status
LCLS Linac Overview E. Bong Lehman Review August 10, 2004
Linac (WBS 1.2.2) Vinod Bharadwaj April 23, 2002
LCLS Commissioning P. Emma, et al
INJECTOR (WBS 1.2.1) Jym Clendenin, SLAC April 23, 2002
LCLS Undulator System Status and Schedule
Electron Beam Systems Wrap-up
Maximum Credible Beam Event Paul Emma et al
LCLS Undulator System Production Management
LCLS Injector Commissioning P
2007 Downtime Controls Installation
LCLS Personnel Protection System and Beam Containment System
E-Beams Systems Manager
LTU/Undulator Installation Status
E. Michael Saleski PPS and BCS Systems Manager
LCLS Undulator System Status and Schedule
LCLS Injector System Overview D. H
Control System Overview Hamid Shoaee LCLS Control System Manager
Installation Status & Operational Readiness Process
P. Emma, for the LCLS Commissioning Team LCLS DOE Review May 14, 2009
Electron Beam Systems ETC and Methodology
Injector/Linac Design Status C. E
LCLS Undulator System Detailed Report
LCLS e- Beams System Overview
Vacuum Controls Stephen Schuh Tom Porter 25 October 2006
e-Beams Systems Update
LINAC System Engineering / Design Status C.E. Rago
LCLS Control System Personnel Linac & BC2 Controls progress
DOE Status Meeting of the LCLS Project
Injector/Linac RF Status
Control System Overview Hamid Shoaee LCLS Control System Manager
Presentation transcript:

LCLS e- Beams Systems Manager David Schultz LCLS e- Beams Systems Manager

2006 Installation In Linac Tunnel In Injector Vault 2006 Operations Readiness Undulator Production 2007 schedule Cost and Schedule Performance 6-Month Look-ahead

LCLS Diagnostics and Controls Physicist Joe Frisch Joining Paul Emma on the LCLS Physics and Commissioning Team Brings extensive experience with diagnostics, RFBPMs, bunch length monitors, timing systems, laser systems, …

Installation Schedule 6 MeV 135 MeV 250 MeV 4.30 GeV 13.6 GeV Linac-0 L =6 m Linac-X L =0.6 m rf gun L0-a,b Linac-1 L 9 m Linac-2 L 330 m Linac-3 L 550 m 25-1a 30-8c ...existing linac 21-3b 24-6d 21-1 b,c,d X undulator L =130 m BC2 L 22 m BC1 L 6 m ‘Wall region’ DL2 L =275 m Now through Dec. 2007 down SLAC linac tunnel research yard

LCLS Installation and Commissioning Time-Line Drive-Laser Commissioning LTU/und. Install Drive-Laser Installed Controls Checkout LTU/und. hall “ready” First Spont. Light A S O N D J F M A M J J A S O N D J F M A M J J 2006 2007 2008 Gun/Inj./BC1 Install (8/21 – 2/20) Gun/Inj./BC1 Commissioning Inj./Linac/BC2 Commissioning linac/BC2 Install LTU/und. Commissioning Oct. 19, 2006

2006 Installation Sector 21 Sector 20 Laser BLM BC1 LX L1 Ins/SAB Wall stopper BLM BC1 LX L1 Ins/SAB Wall

Installation Status in the Linac Tunnel Downtime installation work is underway Removal of accelerator structures went very well. Next few weeks - installing Wall region components L1 and LX accelerator regions BC1 supports BLM region installation begins 11/1 Insertion region installation begins 11/6 Cable connection and checkout begins 12/4

Linac Accelerator Section Removal Before After Making room for the Insertion, L-1 and L-X regions

The X-band accelerator section Klystron, modulator being power tested prior to installation.

Linac Tunnel Downtime Issues Late components, will not hold up commissioning: Vacuum chambers in insertion region. (Jan. 07) BC1 Instrument package. (Jan. 07) Toroids (in several locations) BLM 11 (BLM 12 will be in) Spool pieces are being fabricated to be installed temporarily. Completion of these parts is being aggressively pursued. Linac Access will be made available to install these components.

Injector Vault Installation Status Injector installation has taken second priority to Linac installation. Injector beamline: Accelerator structures, L0a ready, L0b in final bake RF Gun is in hot test 2nd gun (the spare) is in final cold-test. Final braze next. Complete in early Jan. Injector vault: Floor and cable plant installed Support stands are in the vault, Beamline installation underway except for the Gun-to-Linac table

The LCLS photocathode electron gun The new-design LCLS gun, with dual RF feeds. The dual RF feeds have been added to symmetrize the RF entering the gun, eliminating a source of beam emittance growth.

The LCLS Drive Laser Drive Laser installed and operating LSS is installed in laser room and approved. Temporal shaping is being worked on by Thales. Transport optics are being installed and tested.

Injector Vault Installation Issues Late: The GTL support stand will be here 11/16 Laser table install, optics commissioning follows. The Gun will be ready. GTL beamline is late, now in machining. Completion date is 2/8, we are pushing to advance this date and to stage delivery. This leads to a 2 month delay to e- commissioning. Laser commissioning, Controls checkout proceeds The 2007 commissioning goals will still be met. (next slide)

Gun-to-Linac area Laser table To L0a Spectrometer GTL Gun GTL table

Controls Installation Controls is preparing for January checkout. Magnet power supplies, vacuum controls, installed in racks and tested. Racks now installed in place. Linac cable plant phase 2 installation is underway. Network connection from S-20 is installed, ready. Wire scanner controls tested & calibrated, laser optics movers demo’d, OTR/YAG screen video capture ready, BPM/LLRF digitizer boards on order, … Coordination with hardware installation, Laser commissioning, and Controls checkout is being planned for January.

Controls - PPS The Personnel Protection System has been a concern. It is now in hand. Hardware installation is underway. The review process with the SLAC Radiation Safety Committee: Programmable Logic Controller design conditionally approved! The Committee wants to see the certification procedure. Beam loss and shielding designs approved. Beam Containment System approved 10/19.

Injector Accelerator Readiness Review Safety Assessment Document Draft LCLS SAD for Injector Commissioning under internal review. Operating procedures are being written with Accelerator Department Operations. Commissioning LCLS Commissioning Workshop October 9-11 Includes a Commissioning Readiness Review. Accelerator Readiness Review (ARR) LCLS ARR for Injector Commissioning scheduled for October 31st.

Undulator Systems Design Quadrupole Order placed, vendor designs, 1st article 2/07 Fixed Support/Mover Final Design Review - September 13/14 Go ahead given for production. Beam Finder Wire Final Design Review - September 20, 2006 Go ahead given for production of BFW, except wire card. RF Beam Position Monitor Design Review - October 4 Go ahead given for production of bodies. Vacuum Chamber Design Review - September 27/28 The development is behind schedule and near the Critical Path. The "4-weld" design is proceeding full steam. An alternate design effort has begun at SLAC, will not dilute the "4-weld" effort. Should the “4-weld” design run into problems the alternate design will be ready to be adopted.

2007 Installation Progress The design of L2, L3 and the second bunch compressor is well underway. The design of the LTU and beam dump areas are also moving. There are many common components with Inj/Linac, already designed. The Undulator installation schedule has been developed.

Cost and Schedule Performance Injector: SPI=0.95, CPI=0.89 We have been very cautious with the production of the RF Gun and the L0a and L0b Accelerating structures. This has led to schedule delay and cost increases in these areas. Linac: SPI=0.96, CPI=1.05 Design of Linac magnets, diagnostics and RF components have been very synergistic with Injector, leading to savings.

TEC Estimate to Complete Cost to Go at WBS Level 3 1.02 Injector System $M, Burdened, Escalated TEC Estimate to Complete Contingency % Contingency Total Estimated Cost (TEC) 1.96 33.2% 0.65 1.02.01 Injector System Management & Integration 0.25 25.3% 0.06 1.02.03 Injector Lasers 0.73 29.2% 0.21 1.02.04 Injector RF Subsystem 0.15 33.9% 0.05 1.02.05 Injector Magnets & Supports 0.04 32.7% 0.01 1.02.06 Injector Vacuum & Supports 57.4% 1.02.07 Injector Diagnostics 0.34 40.7% 0.14 1.02.17 Injector Installation & Alignment 0.38 34.8% 0.13 The Injector system is nearing completion. Remaining costs are component assembly, vacuum processing and installation.

TEC Estimate to Complete Cost to Go at WBS Level 3 1.03 Linac System $M, Burdened, Escalated TEC Estimate to Complete Contingency % Contingency Total Estimated Cost (TEC) 10.54 22.7% 2.39 1.03.01 System Management & Integration 2.14 23.0% 0.49 1.03.03 Linac Magnets & Supports 1.65 15.1% 0.25 1.03.04 Linac Vacuum Subsystem 2.02 22.4% 0.45 1.03.05 Linac Electron Diagnostics Summary 1.52 22.6% 0.34 1.03.06 Linac RF Subsystem 0.06 0.5% 0.00 1.03.07 Linac Installation & Alignment 3.15 27.1% 0.85 Much of Magnet design is existing, many are on order. There is little new RF hardware to fabricate for 2007 L1 and X-band are complete.

6 Month Look-Ahead Injector installation will be complete and Commissioning will be underway. A detailed schedule for the 2007 Linac downtime and, A detailed installation schedule for the LTU, Und., and Dump will be in hand. The production of components for the these areas will follow a schedule monitored weekly. 50% of Undulator magnets will be RFI. The Undulator Vacuum Chambers will be in production. The SAD will be under revision for the full LCLS, and an LCLS ARR will be scheduled.

Conclusion The downtime installation is underway. We got off to a good start. Not all parts are in hand. Injector installation will delay commissioning. The 2007 commissioning goals will still be met. The Undulator vacuum chamber is still in the design/prototype stage. Near the critical path. No show-stoppers but performance is not yet proven. Alternative design under consideration.