SNS PPU Helium Vessel Design and Assembly

Slides:



Advertisements
Similar presentations
3 rd Harmonic He Vessel Welding Helium Vessel-to-Cavity No June 2008.
Advertisements

Vacuum Vessel Production Readiness Review
Pressure Systems 10CFR851 - The Way to Go but, Some Tough Issues W. Oren Manager of Engineering and Technical Services Division Pressure Systems 10CFR851.
Gas Transmission Pipelines
Material choice Ofelia Capatina OC, Material choices Discuss material choices for – Helium tank – Flanges, joints, bellow OC,
Spectrometer Solenoid Design and Procurement Review Steve Virostek Mike Green Mike Zisman Lawrence Berkeley National Lab MICE Collaboration Meeting October.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Lab MICE CM26 at Riverside California March 26, 2010.
"Welder Certification" The purpose of this presentation is to introduce you to the various aspects of welder certification. This is not intended to cover.
NIOWAVE Requirements for Manufacturing Readiness: (Beamtube Assembly only) Due 1 month before start of manufacturing for CERN approval.
First Article Inspection
Cryomodule Concept for the ODU RF Dipole Crab Cavity Tom Nicol* - Fermilab December 10, 2013 * With lots of help from HyeKyoung, Tom J, Shrikant, Ofelia,
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Laboratory MAP Winter Collaboration Meeting at JLab, Virginia February 28, 2011.
SFOBB East Span Seismic Safety Project Steve Margaris, Specifications Engineer, Caltrans.
RFQ Fabrication Plan, Schedule and QC PXIE RFQ Fabrication Readiness Review LBNL – June 26, 2013 Steve Virostek - Engineering Division Lawrence Berkeley.
Status of Activities at CERN
Americas Cavity Specification C.M. Ginsburg (Fermilab) On behalf of the Fermilab cavity crew October 20, 2010.
56 MHz SRF Cavity and Helium vessel Design
Main features of PETS tank J. Calero, D. Carrillo, J.L. Gutiérrez, E. Rodríguez, F. Toral CERN, 17/10/2007 (I will review the present status of the PETS.
LMQXFA Cold Mass Assembly Antonios Vouris Fermilab February 3, 2016.
HiLumi-LHC/LARP Crab Cavity System External Review – May Work partly supported by the EU FP7 HiLumi LHC grant agreement No and by the.
MICE RFCC Module Update Steve Virostek Allan DeMello Lawrence Berkeley National Laboratory MICE CM27 at RAL, UK July 8, 2010.
JLAB Pressure Systems Considerations Ed Daly. Outline Introduction Federal Law - 10CFR851 Compliance JLAB Pressure Systems Program –Complies with 10CFR851,
LCLS-II Prototype Cryomodule Vacuum Vessel and HGRP Tom Peterson 4 December 2014 Design Review.
"Welder Certification" Weldertraining.org The purpose of this presentation is to introduce you to the various aspects of welder certification. This is.
CM2 Helium Circuit Vacuum Leak & Repair Tug Arkan, 6/18/
7th SRF Materials Workshop FRIB SRF Cavities 7/16/12 Chris Compton.
LCLS-II Prototype Vacuum Vessel (VV) and Helium Gas Return Pipe (HGRP) FDR Planned Quality Control Effort (QC) Ken Premo 12/04/14.
S. Barbanotti - DESY Requirements Conformance for SRF Cryomodules Workshop 16/10/2014 – ESS, Lund XFEL cryostat main components: Quality Assurance and.
Development of Cryo-Module Test Stand (CMTS) for Fermi Lab (R.L.Suthar, Head,CDM, BARC) Cryo-Module Test stand (CMTS) is a very sophisticated equipment.
Logo area Cold Mass Design, Assembly Plans & QC by US HL-LHC-AUP Antonios Vouris MQXF International Review – CERN, June 7 th – 10 th, 2016.
Cryomodule Interconnect Installation Issues A Comparison of XFEL to LCLSII Karen Fant 7/29/2015.
Cryomodule Safety Approvals Jay Theilacker LCLS-II Production Cryomodule Final Design Review May 12-14, 2015.
JLAB Cryomodule Assembly Facilities Visit Report Tug Arkan, Yuriy Orlov March 26, 2012.
650MHz Cavity, Helium Vessel, and Tuner Status at Fermilab Chuck Grimm IIFC POC 650MHz Cavities Fermilab (Avinash Puntambekar RRCAT)
Prototype Cryomodule FDR Ken Premo 21 – 22 January 2015 High Power Coupler Design.
LCLS-II 3 rd Harmonic Dressed Cavity Design Review Chuck Grimm November 20, 2015.
S A Griffiths CM42 June 2015 Electrical & Control.
Crab Cavity Technical Coordination meeting:
CERN – Zanon discussions
Ed Daly for W. Robby Hicks
Ti/SS transitions A.Basti INFN-PISA*
Crab – RFD prototype: Production Status Update
1.3-GHz Cavity Vacuum Furnace at IB4
Overview of Mechanical Design
Fredrik Fors Mechanical Engineering, JLab 09/29/2016
Hongyu Bai LCLS-II 2 K Cold Box FDR March 9, 2017
2K CB FDR Overview:  Agenda, Charge, Review Process
SC1R Cold Box PDR Mechanical Design
First Article Inspection
SNS PPU Cryomodule Instrumentation
Cryomodule Assembly Plan
Undulator System Components Status Dean Walters
SNS PPU Helium Vessel Design and Assembly
SNS PPU Cryomodule Thermal Shield
SNS PPU Cryomodule Vacuum Vessel
SNS PPU Cryomodule Space Frame
SNS PPU Cryomodule Magnetic Shields
SNS PPU Cryomodule Shipping Plans
Work Unit AIK 11.2 CDR of the CDS-SL Mechanics
SNS Coupler Shipping Plans
SNS PPU Cryomodule Instrumentation
SNS PPU Cryomodule Space Frame
SNS PPU Cryomodule Thermal Shield & MLI
SNS-PPU upgrades the existing accelerator structure
SNS PPU CRYOMODULE FDR Magnetic Shields Gary Cheng June 10, 2019.
SC1R Cold Box PDR Assembly Sequence
QCM and C50-12 Status Update
SNS PPU Cryomodule Design Overview
SNS PPU CRYOMODULE PDR Cleanroom Assembly Katherine Wilson
JLAB CHL 2K COLD BOX REPLACEMENT
Presentation transcript:

SNS PPU Helium Vessel Design and Assembly SNS PPU CRYOMODULE FDR SNS PPU Helium Vessel Design and Assembly Katherine Wilson June 10, 2019

Outline Technical Requirements Design Overview Engineering Interface with Other Designs Current status and updates since PDR SOW & Procurement Plan Plans to Finish

Pressure Systems Requirements Pressure boundary defined by SNS is vacuum vessel; however, JLab requires “Every reasonable effort shall be made to design and construct pressure vessels in full compliance with the Code [or]…to the greatest extent that is reasonably possible.” Design requirements developed by Gary Cheng and agreed to by SNS specify the design pressure as 5 atm/75 psia internal @ 2K, 2.2 atm/33 psia internal and 45 psia external @ 300K 10CFR851 provides a limited exemption to BPVC When national consensus codes are not applicable (because of pressure range, vessel geometry, use of special materials, etc.), contractors must implement measures to provide equivalent protection

Other Design Requirements Temperature range: 2-300 K Shipping loads 4 g vertical 5 g longitudinal/axial/beam axis 1.5 g transverse Tuner requirement: 490 kHz/2.0 mm and 29,000 cycles Grade 2 titanium (bellows grade 1 titanium) Similar CTE to niobium Requires Ti-to-SS transitions

Bellows Stroke: ± 0.31 in Pressure: 75 psi internal/45 psi external Infinite fatigue life Active length 1.25 in Operating temp: 2-300 K Cold shocked / leak checked Wall thickness, number of convolutions to be set by manufacturer BPVC calculations Internal pressure test to 75 psi on qualification part (by manufacturer)

Explosion Bonded Joints Transition Gr 2 Ti to 316L SS Updated design! Based on R&D by national labs and used in similar applications Thicker at the explosion joint for more bonding area Longer for less heat during welding Change in location of plate cut-outs to reduce leaks Proven design and vendor Will be thermal shocked and leak checked by vendor Extras to be procured for weld process development

Helium Vessel Procurement Procured as three separate components (probe end head assembly with backing strap, FPC end head assembly with backing strap, shell) Subcontractor to procure explosion-bonded joints as directed source and QC Subcontractor to procure bellows and QC (pressure test on qualification part) Backing straps will be supplied unattached and tacked in place at JLab for ease of assembly QC at vendor: Cold shock & leak check RT of all pressure-boundary welds Visual inspection of welds by certified inspector CMTFs, tracking of materials, serial numbers Assembled to cavity at Jefferson Lab

Heads Nitronic rod attachments Bellows Explosion-bonded joints Backing straps Stiffener

Shell Shell trimmed to fit cavity at JLab prior to welding Cavity spider attachments x3 BPVC-compliant seam weld Heater mount

Pressure Vessel Assembly Heads and shell welded to each other and cavity at JLab Heads and shell welded with BPVC-compliant double bevel butt welds with backing straps Non-BPVC-compliant fillet weld between head and cavity qualified by calculations and experience Head welded to cavity at bellows

Nitronic Rod Attachment Locations Welds were confirmed to have a comfortable factor of safety for nitronic rod pre-loads Shipping loads were analyzed in detail during original SNS and this analysis was not repeated

Assembly Plan Process development required to avoid detuning the cavity Legacy helium vessel components available from SNS will be used for practice First few cavities will be tested bare and dressed to confirm process Cavity will be measured and shell trimmed to fit Cavity, two heads, shell will be welded. Small amount of adjustability is available. Welding procedures will be developed and tooling verified before production

Assembly Procedure JLab plans to adapt horizontal set-up and welding Each head assembly will arrive welded together (dished head, inlet & outlet pipes, stiffener). Cavity support blocks that attach to spider are welded inside HV to match cavity dimensions Two options: Pre-weld FPC end head to shell – reduces detuning of cavity due to weld shrinkage Weld both heads to shell at the same time – reduces the number of weld set-ups Cavity is installed horizontally into shell/FPC end head assy Instrumentation is attached and wiring is fed out “Spider” is attached FPC end dish welded to cavity NbTi Probe end dish installed and welded to shell and cavity Details of procedures being developed

Procurement Strategy Helium vessels needed before cavities, summer 2020 Lead time ~ 30 weeks Weld process will be developed on qualification parts in parallel Build to print Bellows and explosion-bonded joints purchased by HV vendor Explosion-bonded joints to be a directed source CMTRs and traceability requested Certified welders and inspectors Vendor to perform QC (cold shock, leak check, etc)

Current Status Drawings are 90% complete; need to be finalized SOW is complete and signed Procurement plan has been discussed with JLab procurement department No-fund purchase req allows procurement to solicit budgetary quotes for schedule efficiency On track for procurement to support project schedule

BACKUP SLIDES

Applicable Codes and Specifications Requirements “SNS PPU Cryomodule Pressure & Vacuum Systems” Power Point slides, by Gary Cheng, 6 Nov 2018 JLab EHSQ manual 6151 “Pressure and Vacuum Systems Safety Program” 10CFR851, DoE “Worker Safety and Health Program” Reference Spallation Neutron Source Statement of Work PPU Cryomodule 104110000-SW0008-R00 Helium Vessel w/o Liquid Level Probes and Helium Vessel with Liquid Level Probes, 104110102-M8U-8200-A008 and –A009

Pressure Systems Requirements Pressure boundary defined by SNS is vacuum vessel; however, JLab requires “Every reasonable effort shall be made to design and construct pressure vessels in full compliance with the Code [or]…to the greatest extent that is reasonably possible.” Design requirements developed by Gary Cheng and agreed to by SNS specify the design pressure as 5 atm/75 psia internal @ 2K, 2.2 atm/33 psia internal and 45 psia external @ 300K 10CFR851 provides a limited exemption to BPVC When national consensus codes are not applicable (because of pressure range, vessel geometry, use of special materials, etc.), contractors must implement measures to provide equivalent protection…. Measures must include the following: Design drawings, sketches, and calculations…. Qualified personnel must be used to perform examinations and inspections of materials, in-process fabrications, nondestructive tests, and acceptance test. Documentation, traceability, and accountability must be maintained for each unique pressure vessel or system…

Design Helium vessel consists of shell and torispherical heads Anticipate that HV will arrive from vendor in 3 pieces: backing straps already tacked to heads, explosion-bonded joints attached, bellows attached to one head Shell will be trimmed to fit Instrumentation covered in instrumentation talk (M. Wiseman)

Welds Shell-to-head weld modified to add backing straps per welders’ request; allows for better purging Shell-to-head weld is now code- compliant double bevel butt joint Head-to-bellows welds verified Head-to-cavity weld increased size; design unchanged

Helium Vessel Stiffener Original design: fillet welds between head and shell; stiffener was welded to the sliding ring Modified design: fillet welds changed to double bevel butt welds for BPVC compliance; stiffener completely within head Original SNS Design Current PPU Design Modified SNS Design