15/12/2009 Vacuum interlock in sector 78 understood  out-gassing of a Penning gauge ignited as a result of ionization or dust arcing In conclusion: NO.

Slides:



Advertisements
Similar presentations
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Advertisements

Highlights of the ATS MD part I (injection and ramp) … An 8h video game party carefully organized by Jorg et al. 1S. Fartoukh, LSWG 24/05/2011.
Report Friday Very efficient last 24h!.
The ATS MD part III (Achromatic Telescopic Squeezing scheme) Participants: Any (active) volunteers Goal: 1)MD1 (S. Fartoukh & R. Assmann  10h): “Pre-squeeze’’
LHC progress with beam & plans. Of note since last time Transverse damper Beta beating in the ramp Collimation set-up at 450 GeV & validation LBDS – systematic.
● 08:30 Loaded by mistake squeeze function to 2 m  Dumped beams ● 10:30-13:00 Test of new algorithm for long. Emittance blow-up to minimize oscillations.
ION COMMISSIONING REVISITED 1 Thanks to: John Jowett, Walter Venturini. Matteo Solfaroli.
:00: Prepared new fill B1: Q X =0.293, Q Y =0.269; lifetime = 25h ✔ B2: Q X =0.297, Q Y =0.267; lifetime = 5h ✗ Strong 50Hz and 100hz lines.
Friday to Saturday 02:00: Machine closed. 09:00: Cryogenics all OK. Preparing pre-cycle. 10:00: Pre-cycle started. 11:30: Pre-cycle finished. 14:00: Beam.
R. Assmann - LHCCWG Two Beam Operation R.W. Aßmann LHCCWG Acknowledgements to W. Herr, V. Previtali, A. Butterworth, P. Baudrenghien, J. Uythoven,
LHC Progress Friday 30 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
MD Wed – Sat DayTimeMD Wed06:00UPS repair, ATS optics checks w/o beam 12:00Cycle, test ATS optics w/o beam 16: TeV: BPM offset determination for.
LHC progress Sunday 3rd May 2015 Coordination: Mike Lamont, Wolfgang Hofle.
Saturday 11.9 ● From Friday – Minimum required crossing angle is 100  rad in 2010 – Plenty of aperture at triplets: > 13  (n1 > 10) – Can stay with 170.
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
Tue 23/8 – Wed 24/8 09:00 Start 90 m optics run – Preparation and verification of the collimation functions – Re-generation of functions for Transverse.
Wednesday
Ralph Assmann, Giulia Papotti, Frank Zimmermann 25 August 2011
MD Planning Fri – Sat (26. – 27.8.)
Wednesday 8.9 External crossing angles:
Day :00-11:30: Optics at 3.5 TeV Optics re-measured with AC-dipole. Excellent reproducibility. Small emittance increase from AC-dipole. Collapsed.
-9:00: Test IP transverse adjustment (CMS) and optics verification.
Summary of week 7 Hardware Commissioning:
LHC Status Wed Morning 13-April R. Assmann, B. Holzer et al
Status of LHC Operations
Saturday 09:40 Stable beams #1369 (56 bunch scheme)
Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
LHC Morning Meeting - G. Arduini
Thursday morning – optics correction
Summary of Week 11: 14 – 21 March
Alice solenoid – orbit distortion
Summary of Week 16 G. Arduini, J. Wenninger
Mon 22/8 – Tue 23/8 00:07 stable beams #2040. Initial luminosities: 2.1x1033 cm-2s-1 18:00 Programmed dump. End of physics #2040. ~83 pb-1 in ~18 hours.
Saturday 2/4/ :00-09:00 Problems with SPS:
Friday Morning 3:44 – 15:04 stable beams Fill (dumped by operator)
Tuesday 20 March 2012.
Week 35 – Technical Stop and Restart
04-05/08/2010 End of physics at ~11:00 after 18.5 hours ~120 nb-1.
Planning at 5 o’clock meeting Friday
Yesterday Power back around lunchtime Access until 12:30
Monday 08:30 – 11:00 Access for: LBDS beam 2 problems: TSU unit changed RQTD.A67B1: controller for the current lead heater changed RQS.A67B1 power converter.
Friday 16/3 08:30 – 10:15 Access for QPS and EPC (BI in point 4)
Wednesday 09 March …:09:00: beta* measurement (1.5 m) by K-modulation and with AC-dipole excitation. 1/17/2019 LHC 8:30 meeting.
BI cont. *** Summary Matching Monitor test *** We only had ~15minutes of inject and dump, but managed to see a profile with ~9e9 p (!)
Saturday 7th May Sat – Sun night
Friday 23rd March 08:00 Access
Summary Thursday h21: Stable beams fill #1303.
Planning for the week MO M P
Summary of week 19 Machine Coordinators: G. Arduini, M. Lamont Main aim: Luminosity production.
Aims for the week Recover from technical stop and precycle at 10A/s
Wednesday 10:00 test of the un-squeeze to 90 m at 4 TeV.
Rocky last 24 hours Losses Q6.R5 Orbit SIS TCDQ OK! Power converters
Tuesday morning 08:30-09:00 Squeeze with probe.
Monday 8th December Morning used for RF work (IP z, injection), damper noise checks. Stable beams period with LHCb spectrometer OFF – lost beam after.
07/08/2010 Fill #1264 dump at 02:14:38.
MD Planning Fri – Sat (1. – 2.7.)
Thursday 22 September 2011.
Summary for LPC (March 7th, Ralph Assmann)
Saturday :42 stable beams fill 3541
Sat 18/3 - Ramp to 4 TeV Again glitch on the safe beam flag for beam 2. Cause identified: noise on BCT2B giving values above the safe beam limit (2.4×1010.
Wednesday 23/2 Thanks CRYO!!!.
Wednesday h18: 228b fill lost just before start of ramp.
Monday 26th September 7:30 Beam dump, QSP on RQX.R1, lost cryo in ITR1, 91 pb-1. Cryo recovery, needed about 1.5 h. Setting of TI2 collimators to 5 sigma.
LHC Morning Meeting - G. Arduini
Another Immortal Fill….
Monday 27th August & night
31/3/2010 Difficult day… but at the end stable beams.
Wednesday :35 : Beam lost because of trip of RCBXH3.L1
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

15/12/2009 Vacuum interlock in sector 78 understood  out-gassing of a Penning gauge ignited as a result of ionization or dust arcing In conclusion: NO LEAK, just a problem of vacuum instrumentation, VSC following up the issue Re-injected beam at ~08:30 TOTEM test from 08:30 to 10:30

15/12/2009 10:30 -15:00 Abort gap cleaning tests Cleaning of a selected bunch observed Attempted gap cleaning on un-bunched beam Some controls issues on abort gap monitors

15/12/2009 15:00-19:00 Orbit feedback Checked by using small orbit bumps trimmed via LSA and that were removed by the feedback Still some work to be done before putting in operation

15/12/2009 Ramp with tune feedback very smooth: feedback takes care of the decay at the end of the ramp

15/12/2009 Orbit at high energy requiring corrections

15-16/12/2009 21:40 Beam dump due to triplet orbit corrector induced by a “wild” trim of the orbit feedback (thought to be disabled) 00:00 Ready for injection 01:00 1.18 TeV Vertical blow-up in beam 2 visible

16/12/2009 Beta beating measurements for un-squeezed optics at 1.18 TeV for Beam 2: similar to what observed for beam 1. Optics within specs.

16/12/2009 02:30 Squeeze in IR5 to b*=9m. After squeeze step 1: IP5 beta's H:8.48+- 0.2m (9.00) V:9.7+-0.4 (9.0)

16/12/2009 02:50 Squeeze in IR5 to b*=7m. After squeeze step 2: IP5 beta's H:6.8+- 0.3m (7.00) V:7.5+-0.5 (7.0) Hands-off from ~03:30 to 04:30 after rough separation tuning in IP1

16/12/2009 Additional optics measurements until 05:30 (e.g. Dispersion for beam 1 with b*=7m) Then energy extraction test in Sector 12 bends for measurements on the energy extraction switches (QPS team) 06:00-08:00 Machine pre-cycled

16/12/2009 08:00-10:00 Injection studies 10:00-12:00 ATLAS aperture 12:00-16:00 Lifetime studies 16:00-17:00 BLM-nQPS test 17:00-18:00 Intrusion test 18:00 End of Run