Where We Are Now. Where We Are Now Rationale for Reducing Project Duration Time Is Money: Cost-Time Tradeoffs Reducing the time of a critical activity.

Slides:



Advertisements
Similar presentations
Project Management 6e..
Advertisements

Project Management for Maximum Effectiveness
Chapter 9: Reducing Project Duration
Reducing Project Duration
SCHEDULE COMPRESSION In real practice – how would you compress your Schedule?
Reducing Project Duration: Project Crashing
Reducing Project Duration
■ Project duration can be reduced by assigning more resources to project activities. ■ However, doing this increases project cost. ■ Decision is based.
Time-Cost Trade-Off (Time Reduction = Time Compression = Time Shortening) 4/17/ :55 AM.
OPSM 639, C. Akkan Resource Planning Resources affect the schedule, cost and performance of a project. Resources are –Individual people, departments/teams,
OPER 576 Project Management Reducing Project Duration or Project Crashing Greg Magnan, Ph.D. May 20, 2004.
Quiz#1 Chapter 5: Estimating Project Times and Cost
Software Project Management Task Estimating and Scheduling
Time/Cost Trade-off Analysis
Chapter 9: Reducing Project Duration
Time-Cost Trade-Off (Time Reduction = Time Compression) (Time Shortening) Time-Cost Trade-Off (Time Reduction = Time Compression) (Time Shortening)
Scheduling Resources and Cost
Human Resources n How do we compete with everybody else who needs resources? n Where do we find people when we can’t hire new employees? n What does time.
Exercise 3 Group 8 Kristin Eik and Tanya Drangevåg Sangolt.
Reducing Project Duration CHAPTER NINE Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
Reducing Project Duration CHAPTER NINE Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
Prepared by Scott M. Shafer, Updated by William E. Matthews and Thomas G. Roberts, William Patterson University Copyright 2007 John Wiley & Sons, Inc.5-1.
1 Finishing Projects Fast James R. Burns Professor of Operations Management and Information Technology Texas Tech University.
 Delay in project implementation invariably results in cost- overrun.  Delayed project implementation means delay in getting return on investments made.
TOPIC-6- TIME-COST TRADE OFF
3/18/ :47 AM 1 Time-Cost Trade-Off (Time Reduction = Time Compression = Time Shortening)
Develop Schedule is the Process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule.
1 Finishing Projects Fast James R. Burns Professor of Operations Management and Information Technology Texas Tech University.
Develop Schedule is the Process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule.
University Of Palestine Faculty Of Applied Engineering & Urban Planning Civil Engineering Department PROJECT MANAGEMENT Scheduling Resources and Costs.
Scheduling Resources and Costs
Estimating Project Times and Costs
Project Management 6e..
Reducing Project Duration
CE 366 PROJECT MANAGEMENT AND ECONOMICS Robert G. Batson, Ph.D., P.E. Professor of Construction Engineering The University of Alabama
Project Management Chapter 8.
Project Management.
Project Management Chapter Topics
Project Management Operations -- Prof. Juran.
Estimating Project Times and Costs
Chapter 4: Project Management
Project Planning & Scheduling
P.I.I.M.T American University of Leadership
Project Management -- Scheduling Resources and Costs
Project Management -- Reducing Project Duration
Where We Are Now. Where We Are Now Estimating Projects Estimating Types of Estimates The process of forecasting or approximating the time and cost.
Reducing Project Duration
Engineering Project Management
Project Planning & Scheduling
Project scheduling Chapter 10 Copyright ©2016 Pearson Education, Inc.
UNIT II Scheduling Procedures & Techniques CRITICAL PATH ANALYSIS
Estimating Project Times and Costs
Estimating Project Times and Costs
Chapter 8 Scheduling Resources.
ENGINEERING MANAGEMENT (GE 404)
In this tutorial you will:
Project Management Operations -- Prof. Juran.
Lecture 6: Time-Cost Trade-Offs
Finishing Projects Fast
Manajemen Industri Teknologi informasi
Reducing Project Duration
Finishing Projects Fast
Where We Are Now. Where We Are Now The Resource Problem Resources and Priorities Project network times are a schedule until resources have been assigned.
Estimating Projects Estimating Types of Estimates
Estimating Project Times and Costs
Finishing Projects Fast
Where We Are Now. Where We Are Now Rationale for Reducing Project Duration Time Is Money: Cost-Time Tradeoffs Reducing the time of a critical activity.
Where We Are Now. Where We Are Now Rationale for Reducing Project Duration Time Is Money: Cost-Time Tradeoffs Reducing the time of a critical activity.
Presentation transcript:

Where We Are Now

Rationale for Reducing Project Duration Time Is Money: Cost-Time Tradeoffs Reducing the time of a critical activity usually incurs additional direct costs. Cost-time solutions focus on reducing (crashing) activities on the critical path to shorten overall duration of the project. Reasons for imposed project duration dates: Time-to-market pressures Unforeseen delays Incentive contracts (bonuses for early completion) Imposed deadlines and contract commitments Overhead and public goodwill costs Pressure to move resources to other projects

Options for Accelerating Project Completion Resources Not Constrained Adding resources Outsourcing project work Scheduling overtime Establishing a core project team Do it twice—fast and then correctly Resources Constrained Fast-tracking Critical-chain Reducing project scope Compromise quality

Explanation of Project Costs Project Indirect Costs Costs that cannot be associated with any particular work package or project activity. Supervision, administration, consultants, and interest Costs that vary (increase) with time. Reducing project time directly reduces indirect costs. Project Direct Costs Normal costs that can be assigned directly to a specific work package or project activity. Labor, materials, equipment, and subcontractors Crashing activities increases direct costs.

Reducing Project Duration to Reduce Project Cost Identifying direct costs to reduce project time Gather information about direct and indirect costs of specific project durations. Search critical activities for lowest direct-cost activities to shorten project duration. Compute total costs for specific durations and compare to benefits of reducing project time.

Project Cost–Duration Graph FIGURE 9.1

Constructing a Project Cost–Duration Graph Find total direct costs for selected project durations. Find total indirect costs for selected project durations. Sum direct and indirect costs for these selected project durations. Compare additional cost alternatives for benefits.

Constructing a Project Cost–Duration Graph Determining Activities to Shorten Shorten the activities with the smallest increase in cost per unit of time. Assumptions: The cost relationship is linear. Normal time assumes low-cost, efficient methods to complete the activity. Crash time represents a limit—the greatest time reduction possible under realistic conditions. Slope represents a constant cost per unit of time. All accelerations must occur within the normal and crash times.

Activity Graph FIGURE 9.2

Cost–Duration Trade-off Example FIGURE 9.3

Cost–Duration Trade-off Example (cont’d) FIGURE 9.3 (cont’d)

Cost–Duration Trade-off Example (cont’d) FIGURE 9.4

Cost–Duration Trade-off Example (cont’d) FIGURE 9.4 (cont’d)

Summary Costs by Duration FIGURE 9.5

Project Cost–Duration Graph FIGURE 9.6

Practical Considerations Using the Project Cost–Duration Graph Crash Times Linearity Assumption Choice of Activities to Crash Revisited Time Reduction Decisions and Sensitivity

What if Cost, Not Time Is the Issue? Commonly Used Options for Cutting Costs Reduce project scope Have owner take on more responsibility Outsourcing project activities or even the entire project Brainstorming cost savings options

Key Terms Crashing Crash point Crash time Direct costs Fast-tracking Indirect costs Outsourcing Project cost–duration graph

Project Priority Matrix: Whitbread Project FIGURE 9.6