Quantity Management (QMS) Designed for Company / Client verification of contractors measurement
Introduction Currently the Quantity Mgmt module contains two sub modules Contract Evaluation Measurement Verification Sutable for time and material contracts Price elements for man-hour norm and material unit rate (Compensation Codes) Quantity * Norms and Rates = Man-Hours, Labor Cost, Material Cost and Total Cost
Time and Material Contract Example Typical Compensation format in Norway
Evaluation Compare bidders Analyze norms and rates FEED MTO Compare bidders Analyze norms and rates Scenarios / Normalizing Identify «tactical priced norms and rates» Compensation Codes Scenarios Bidders Norms and Rates Compare Reports
Contract Evaluation (Demo) Compensation Codes & CBS Scenarios Bidders Compare Bids Norms and Rates Analyzer
Measurement Tool for Company’s verification of Contractor’s measurement and management of quantity update estimates that provides a continuous interpretation of Scope of Work into man-hours and cost through to final account. Deviations, cost changes and inconsistencies can be identified and managed at the earliest possible stage. The tool is divided in two main areas: Quantity Update – Estimates in line with Weight Reporting Quantity Measurement – A/IFC and As-built measurement
Quantity Update Project Duration 100% Scope Estimate IFC Quantities As-Built Quantities 100% Scope
Quantity Update Demo Estimate (Forecast) Scenarios Can be activated / deactivated in estimate Archive Estimate and MTO development Scenarios
Measurement Approaches 100% As-Built Verification (Heavy workload) Spot Check of As-Built Continuous verification -> Feedback to Contractor
Measurement data flow example Always use contractor’s measurement 100%, incl. errors and missing data. Contractor 100% transmissions, Incl. Errors, disagreements e.a Feedback Agreed measurement adjustments Company Disagreements Own measurement on the few items we definitive disagree on
Measurement Simplified Model Contractor a Contractor’s MTO 1 Quantity Update 2 b Compensation Codes 3 MTO 4 Estimate 5 Client
Measurement (Demo) MTO Information Library Reporting
What is there to check ? Reimbursable items (Not be measured) Tag or articles installed by vendors on equipment packages Compensation code Material Take Off (MTO) on document’s Article weight QtyMgmt Void item’s on documents and index Article length Doc MTO Art Clarifications Duplications in articles, documents or MTO (X) Item's that should be included in other articles with a general compensation code Tag or articles that should be measured in other phases (Hook-up) ATS-MC work paid both in measure and invoice