CMGC Overview SLAC Site Plan Systems Description Construction Schedule

Slides:



Advertisements
Similar presentations
David Saenz Space Conversion to June 17, Space Conversion to Offices Scope Schedule Budget.
Advertisements

Alternative Project Delivery
1 BROOKHAVEN SCIENCE ASSOCIATES Procurement Dave Paveglio, Contract Administrator NSLS-II PAC Meeting May 25, 2007.
1 BROOKHAVEN SCIENCE ASSOCIATES National Synchrotron Light Source II Procurement Methodology David Dale NLSL II Procurement Manager.
David Saenz FAC CF April 20, 06 Meeting of the LCLS Facilities Advisory Committee LCLS Conventional Facilities D. Saenz.
David Saenz CM/GC April 8, 2005 CM/GC Overview CM/GC Plan & Status Systems Description Cost Estimate Construction Schedule.
Jess Albino Session 5 Conventional November 11, Facility Advisory Committee LINAC Coherent Light Source Project.
David Saenz FAC CF April 07, 2005 Conventional Facilities Overview SLAC Site Plan Systems Description Construction Schedule.
David Saenz Facility Advisory October 30, 2007 CONVENTIONAL FACILITES MANAGEMENT.
David Saenz Far Experimental Hall - June 17, Far Experimental Hall - Hutches Scope Budget Schedule.
Mark Reichanadter LCLS FAC April 20-21, 2006 Meeting of the LCLS Facilities Advisory Committee LCLS Project Management M.
Jess Albino FAC CF April 16, 2007 Meeting of the LCLS Facilities Advisory Committee LCLS Conventional Facilities Jess.
1 Jess Albino 1 Conventional Facilities Status FAC Review – Breakout Session CONVENTIONAL FACILITIES STATUS Jess Albino – Associate.
David Saenz FAC CF Oct 12-13, 2004 Conventional Facilities Overview SLAC Site Plan Systems Description Construction Schedule.
Jess Albino Facility Advisory October 29, 2007 FACILITY ADVISORY COMMITTEE PLENARY CONVENTIONAL FACILITIES UPDATE October.
David Saenz CF Oct 30, CF MEP Commissioning.
Bob Law FAC Oct 24, Sector 20 Project Overview Sector 20 Site Plan Description Organizational Chart Schedule Cost.
David McGiven FAC: Construction April 2006 Facility Advisory Committee (FAC) Construction Procurement David.
1 BROOKHAVEN SCIENCE ASSOCIATES LOB - Ring Building Construction Coordination Michael P. Bromfield Construction Engineer NSLS-II Conventional Facilities.
1 BROOKHAVEN SCIENCE ASSOCIATES Procurement David J. Paveglio Contracts Administrator Laboratory Office Buildings CFAC Review - November 9-10, 2009.
David Saenz FAC Review CF Design, Cost and Schedule Oct 27, 2005 CF Overview & Status Design Status CMGC Status Latest.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS – II CFAC Review Conventional Facilities Method of Accomplishment Marty Fallier Director for Conventional Facilities.
Additional Commercial Contract Types FAR Case Summary of Comments from October 19, 2004 Public Meeting Appropriate Use Terms and Conditions Payment.
David Saenz Readiness for Oct 12, 2006 # Meeting of the LCLS Facilities Advisory Committee LCLS Conventional Facilities.
Pre-Construction Activities to include: - Provide effective overlap period and oversight of effort - Estimates during - CPM Schedule - Identify lead-time.
Mark Reichanadter LCLS October 9-11, 2007 LCLS BCR Overview and EIR LOIs Project Progress / Status Revised Project Baseline.
David Saenz EIR Review Oct 9-11, Conventional Facilities (CF) WBS 1.9 ETC and Methodology David Saenz CF Systems Manager.
Request for Information & Capability Statements Richland Acquisitions Post-FY 2018 November 17-19, 2015.
CONDUCTING BUSINESS WITH THE TOWN OF MIAMI LAKES Construction Services October 28, 2013.
IAS Pre-proposal Conference December 10, 2012 Pre-proposal Conference December 10, 2012 San Antonio bldg 1 & 4 Renovation san antonio, tx Project no: San.
1 BROOKHAVEN SCIENCE ASSOCIATES Conventional Facilities Schedule Steve Sawch Asst. Director, Construction Management CF Advisory Committee Review of the.
Solicitation VA69D-16-R-0583 Rehab Renovation Pre-Proposal Conference June 22, :00am CDT NCO 12 Great Lakes Acquisition Center.
USAID Afghanistan Engineering Support Program (ESP) Pre-Bid Meeting July 14, 2015.
CBETA Project ALD’s Cost and Schedule Review February 6, 2017
LCLS-II ES&H Requirements: Subcontractors
Construction Oversight
CM at Risk v. Design-Bid-Build
Meeting of the LCLS Facilities Advisory Committee
Experimental Facilities Planning
CF Organization & Schedule
Meeting of the LCLS Facilities Advisory Committee
Far Experimental Hall Hutches Civil Construction
Far Experimental Hall Hutches Civil Construction
CONVENTIONAL FACILITIES STATUS
Electron Beam Systems ETC and Methodology
Thomas Fornek Project Manager July 15, 2009
John N. Galayda – Director, LCLS Construction May 13, 2009
CONVENTIONAL FACILITIES LCLS Office Space
Department Of Energy Review LINAC Coherent Light Source Project
X-Ray Endstations Update
Conventional Facilities (WBS 1
Details supporting the increase
CONVENTIONAL FACILITIES LCLS Office Space Procurement
DOE Review of the LCLS Project
Far Experimental Hall - Hutches
Project Management Issues John N. Galayda, SLAC April 24, 2002
Project Status Review May 13-15, 2008.
Conventional Facilities WBS 1.9
Integrated Safety and Environmental Management
Conventional Facilities Status
CONVENTIONAL FACILITIES
DOE Review of the LCLS Project
Installation Status & Operational Readiness Process
Department Of Energy Review Linac Coherent Light Source Project
Conventional Facilities
Phase 1 Statement of Work Preconstruction “Plan The Work”
DOE Mini-Review of the LCLS Project
CF Scope, Management & Organization
X-Ray Endstation Systems (XES) 2006 Schedule
LCLS Conventional Facilities David Saenz Systems Manager
Presentation transcript:

CMGC Overview SLAC Site Plan Systems Description Construction Schedule Cost Estimate ES&H CMGC SOW Summary

SLAC Site Plan SLAC Main Gate Pep Ring Road Bldg #081 - MMF Sector 25 Sector 20 Upstream LCLS General Work Boundary Research Yard

LCLS Site Plan Spear Future Office Space Pep Ring Road SLC Legend Baseline Future LCLS Site Plan Spear Future Office Space Pep Ring Road SLC Office Complex Undulator Hall Research Yard Survey Tower NEH Beam Transport Hall SLC Tunnel Beam Dump Front End Enclosure Future Beam Lines X-Ray Transport Pep Tunnel

LCLS CF Systems Description Includes a composition of renovations to existing SLAC infrastructure and new facilities for CMGC Research Yard Modifications Beam Transport Hall Undulator Hall Electron Beam Dump Front End Enclosure Near Experimental Hall X-Ray Transport & Diagnostics Tunnel Far Experimental Hall Central Lab Office Complex

New Facilities Beam Transport Hall – 227m long above grade facility to transport the electron beam through the existing RSY Undulator Hall – 175m long underground tunnel housing undulators and ancillary equipment Central Lab Office Complex – office facility to house ~ 300 LCLS researchers, engineers, technicians, administrative staff and visiting experimentalists Far Experimental Hall – underground cavern/tunnels to house 3 experimental hutches, prep and shop space Electron Beam Dump – 40m long underground facility used to separate the electron and x-ray beams Front End Enclosure – 30m long underground facility to house various diagnostic equipment in support of the photon beam Near Experimental Hall – underground facility whose primary function is to house 3 experimental hutches, prep and shops X-Ray Transport & Diagnostics Tunnel – 250m long underground tunnel used to transport photon beams from NEH to FEH

Below Grade Plan FEE Beam Dump Near Hall/CLOC Beam Transport Hall (at grade) Undulator Hall XRTDT Far Hall FG ~ 360’ FG ~ 320’ FG ~ 280’ FG ~ 245’

LCLS CF Construction Schedule LEGEND TI Design TII Design Preconstruction Construction Major construction phase FY 06 at 30 months duration Beneficial Occupancy dates are key to technical system interfaces Site-work at NEH is key! Increased duration of CM/GC procurement phase DOE SO approval for CM/GC SOW – (in progress)

WBS 1.09 TEC (BCWS x FY) $76.7M Construction Start Mar 06 LLP – S20, MMF, CMGC Phase 1

ES & H Risks Construction Safety – Is not a priority, but a VALUE! (priorities change from time to time, values remain consistent over time) All construction activities shall comply with Federal and State environmental, safety, health and building codes Subcontractor activities In-house activities LCLS will approve GC construction safety program prior to any start of construction activities Unique considerations to normal day-to-day construction projects at SLAC Tunnel construction Excavations Subsurface construction Weak ground conditions Naturally occurring asbestos Elevated work Heavy equipment Congested work areas (RSY)

CM/GC Plan SOW for CM/GC (LLP) has been developed and continues to have the highest priority in the CF group as largest stand-alone procurement in the LCLS project Reviewed by SLAC DOE SO Final comments updated and sent to proof reader for final corrections Once approved by SLAC DOE SO, plan will be submitted to DOE HQ for approval (Chicago → DC) With blanket approval, there will not be a need to return for multiple approvals for bid packages

CM/GC Plan – cont’d Advanced Procurement Plan (APP) approved Advertisement placed in construction periodical – ENR Magazine Jan/Feb Advanced Procurement Plan (APP) approved Meeting planned milestones are crucial!

CM/GC Plan – cont’d CM/GC services will be solicited with an award based on a best-value firm fixed price contract Phase 1 – preconstruction services Phase 2 – construction services of underground and major excavation effort, and construction services of above ground buildings Anticipating CM/GC award for Sept 05 CM/GC qualifications – partial list Technical competence Similar previous experience Successful history using second and third tier subcontractors Financial strength

CM/GC Plan – cont’d Outstanding safety record Experience Modification Rate (EMR) <.81 EMR 1.0 indicates that a company submits injury claims that are considered average among their industry group EMR > 1.0 indicated that the company files more claims than other similar companies EMR<0.81 indicates that the company had filed fewer claims than other similar companies Injury frequency and severity rates Safety Program evaluation and evaluations of the key personnel OSHA citation history References from previous projects Evaluation of the contractors’ integration of safety into their work practices LCLS has decided to place all contractors working on projects to have an EMR of <.81, go no-go

Summary SOW completed and is currently being reviewed (with RFP package) in collaboration with SLAC DOE SO, SLAC and LCLS project team Comments incorporated Complete CMGC package (RFP, SOW, T&C’s, etc) under review by technical writer DOE approval milestones are critical! CM services (interim phase) scheduled to commence in collaboration with 30% design review Cost validation Schedule review Constructability review Value Engineering

End of Presentation