WCR ROAD COMMITTEE REPORT – Skip Porter Band sawing material for Rock Grizzly Rock Grizzly construction layout
WCR ROAD COMMITTEE REPORT - SKIP PORTER Positioning frame for welding Rotating Grizzly for welding
WCR ROAD COMMITTEE REPORT – SKIP PORTER Welding sucker rod grid to grizzly frame work Scissor lift used for safety while welding
WCR ROAD COMMITTEE REPORT – SKIP PORTER Rock Grizzly during priming and painting Rock Grizzly finished loaded on the trailer
WCR ROAD COMMITTEE REPORT – SKIP PORTER ROCK GRIZZLY PROJECT #1054 BUDGET $7500 COMPLETED FOR A TOTAL EXPENSE OF $3625.44 QUOTE FOR A NEW ROCK GRIZZLY WITH THIS HEAVY DUTY DESIG WOULD HAVE COST APPROX $11,000.00