Question 1: Contingency for “extra” year

Slides:



Advertisements
Similar presentations
2006 TEA Conference Terry Berends, PE Assistant State Design Engineer Washington State Department of Transportation Risk Based Estimating Tools at WSDOT.
Advertisements

Cost, Schedule & Funding Closeout Jan Joint DOE/NSF CD2/3a Review 1 DOE/NSF Review of the Dark Energy Survey (DES) Project SC 6/7 Cost, Schedule.
GLAST LAT ProjectSubsystem Managers Face to Face, November 17, GLAST Large Area Telescope: Darren Marsh Stanford Linear Accelerator Center Performance.
Risk Management CS 414, Software Engineering I Mark Ardis, Rose-Hulman Institute January 28, 2003.
Major Management & Systems Engineering Ideas for Reducing Costs Peter Wizinowich NGAO Team Meeting September 11-12, 2008.
Developing a result-oriented Operational Plan Training
NEDM Construction Project Cost & Schedule Philosophy Vince Cianciolo, ORNL Physics Division Internal Cost & Schedule Review 02/11/2005.
David M. Lee Forward Vertex Detector Cost, Schedule, and Management Plan Participating Institutions Organizational plan Cost Basis R&D Costs.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Baseline Jim Yeck NSLS-II Deputy Project Director NSLS-II PAC Meeting November 20, 2007.
LSST Camera CD-3 Review Brookhaven National Laboratory, Brookhaven, NY LSST Safety Council Camera Review Bremerton, WA 2015 LSST Camera Environment,
Chapter 15: Risk Management
John Peoples for the DES Collaboration BIRP Review August 12, 2004 Tucson1 DES Management  Survey Organization  Survey Deliverables  Proposed funding.
Managing Risk The Science and Art of IT Risk Assessment for Project Managers Presented at the FCW Events Government PM Summit November 2004 Michael Lisagor.
OFFICE OF SCIENCE 2.3 Infrastructure and Installation Sims, Edwards 1.Does the conceptual design and planned implementation satisfy the performance specifications.
1 US Cost & Schedule Summary W. R. Edwards US Project Manager CD-2/3a Review January 8, 2008 BNL.
TOF Preliminary Design and Safety Review Project Management Controls R. L. Brown.
 To provide a realistic accurate idea of the cost  Provide information about building or not.
Module 4: Effect of Agile on the DoD Program Office TLO: Given a DoD program involved in software development using Agile philosophy methodologies, the.
UK Project Plan Roy Preece STFC RAL RLSR 26 th October 2015.
1 OBSERVATORY CONTROL SYSTEM (OCS) FRANCISCO DELGADO OCS CAM.
LSST Commissioning Overview and Data Plan Charles (Chuck) Claver Beth Willman LSST System Scientist LSST Deputy Director SAC Meeting.
LSST Commissioning Status Update & Overview Charles (Chuck) Claver LSST System Scientist SAC Meeting March 5, 2017.
Large Synoptic Survey Telescope
ComCam Hardware and Interfaces James Howard ComCam CAM LSST 2017 Project & Community Workshop 2017 Aug 15.
Jim Fast Pacific Northwest National Laboratory
Agenda ComCam planning and scheduling (James & Jacques) CCS & CCS-TCS Interface (Tony) Software to use ComCam Software to get data out of ComCam (Mike)
Telescope Assembly, Integration and Verification (AIV) WBS 04C. 14 J
Page Headline Beam Commissioning Adam Bartnik.
Status of the MICE Construction Project
Project Management W. J. Foyt
WBS 1.03 Readout Systems Scope, Cost and Schedule
ComCam Hardware and Interfaces James Howard ComCam CAM LSST 2017 Project & Community Workshop 2017 Aug 15.
LSST Commissioning Overview and Data Plan Charles (Chuck) Claver Beth Willman LSST System Scientist LSST Deputy Director SAC Meeting.
East Hall under construction
Work Breakdown Structures (WBS)
LSST Commissioning: FY18 Planning
LSST Commissioning Kevin Reil LSST Commissioning Camera Rep
OSG Computer Security Plans
Chuck F Claver LSST System Scientist & Commissioning Lead
Phase 2 Tollgate Review Discussion Template
Risk Register I want to plan a project
PMIS Initiating a Project Application of Project Management Processes Project Charter Stakeholder Analysis and Stakeholder Register 2. Planning.
Project Organization Chart Roles & Responsibilities Matrix
Phase 2 Tollgate Review Discussion Template
Phase 1 Tollgate Review Discussion Template
Ocean Observatories Initiative
DOE: Transition from MIE to Early Operations Kevin Reil LSST Camera Commissioning Lead LSST Commissioning Plan Review January 24-26, 2017.
Preparations for a Lehman Review
Management Breakout: DOE Budget Summary Vincent Riot LSST Camera Interim Project Manager LSST Commissioning Plan Review January 24-26, 2017.
Management Breakout: MREFC Budget Summary Victor L
LSST Control Software Integration Francisco Delgado OCS Software Manager LSST Commissioning Plan Review January 24-26, 2017.
Software & Hardware for Wavefront Estimation Pipeline Development Te-Wei Tsai Software Engineer Joint Technical Meeting March 6, 2017.
Click to add title Planning for LSST Verification George Angeli LSST All Hands Meeting Tucson August 15, 2016.
Phase 2 Tollgate Review Discussion Template
Recommendations for using this ‘framework’ template
Overview of Science Verification Plan Keith Bechtol and Zeljko Ivezic LSST Commissioning Plan Review January 24-26, 2017.
Animal Welfare EU Strategy
Handout 1: Manage personal performance
The emphasis of Construction Management and Preconstruction Services in the AEC industry Preconstruction Services Construction Management.
CBGD: Nguyễn Thanh Tùng
Handout 1: Manage personal performance
Cost Estimating Best Practices
Software Testing Lifecycle Practice
Linac Coherent Light Source (LCLS)
Department Of Energy Review Linac Coherent Light Source Project
Assumptions INFS 4810.
CSS Consequential Programme Change Assurance March, 2019
Key Issues and Today’s Goals
Commissioning Data – Who and Why?
FASER LS2 work coordination meeting
Presentation transcript:

Template Response to Questions Steve Kahn LSST Commissioning Plan Review January 24-26, 2017

Question 1: Contingency for “extra” year Lien on contingency for the additional year depends on the cause and when we learn about the delay. The most likely cause for the needing time in the extra year is delays in the delivery of the LSSTCam and/or the Telescope. Early awareness of the delay can be mitigated to some extent by compressing the time with ComCam. A delay in the start of Commissioning, would have a small impact on the use of DOE-Commissioning contingency. An extension of Commissioning beyond what is planned would have the highest impact on the draw of contingency. “Marching army” cost for DOE labor is ~$3M per year, covering fully the extra year would draw ~$3.1M of contingency out of the $3.8 estimated.

Question 2: Early Ramp of DOE Commissioning The scope in FY17 and FY18 can be broken down into two main items Preparation for a “CD-2 like” review. Basis of estimate and detailed planning requires currently unfunded engineering support on the DOE We cannot support a CD-2 like review without this support. FY17 impact can be removed by delaying next review well into FY18 Early commissioning of CCS, DAQ, OCS, TCS and DM control systems is a risk mitigation to prevent future delays This is can be delayed or stretched into later years causing higher risks later in commissioning

WBS 06.02.01 Commissioning Management, Core Commissioning Team, Science Verification Team 24 FTEs + some contracted sabbatical support Expect ~half of these to carry forward into the same roles in operations [e.g. Observatory Operations scientists, CCS/DAQ software engineers]. Expect many of the rest to carry forward into related roles [e.g. SDQA, community support, long-term survey monitoring].