CHAPTER ONE: RESOURCE ALLOCATION AND SCHEDULING

Slides:



Advertisements
Similar presentations
Developing a Project Plan CHAPTER SIX Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
Advertisements

Developing a Project Plan CHAPTER SIX Student Version Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
Chapter 6: Developing a Project Plan
Where We Are Now Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved.
PRJ566 Project Planning and Management Lecture: Network Diagrams.
Project Management Project Management
ES=32 EF=34 LS=33 LF=35 ES=10 EF=16 LS=10 LF=16 ES=4+6=10 EF=10 LS=4
CSSE Sep.2008 Constructing and Analyzing the Project Network Diagram Chapter 6.
CSSE 372 Week 6 Day 2 Constructing and Analyzing the Project Network Diagram  PERT Chart PERT was invented for the Nautilus submarine project. Ok, maybe.
1 University of Wales Bachelor of Science (Industrial Engineering and Management) Year 3 Copyright © 2012 MDIS. All rights reserved.Section
Project Scheduling: Networks, Duration estimation, and Critical Path.
MGMT 483 Week 8 Scheduling.
5/4/20151 NETWORK SCHEDULING TECHNIQUES. 5/4/20152 Network Diagrams  PMI defines the scheduling process as: “the identification of the project objectives.
Construction Planning and Scheduling A G E NG 520 Schedule Computations Part #2 1. Definition and Computation of Total and Free Floats: Total Float : The.
Project Networks. A,4 B,3 C,4 D,6 E,3 H,6 F,5 G,4 I,2 St,0 Fin,0 Example Network - terminology C,t Activity Duration of Activity (ES, LS) Early Start.
Project Scheduling: Networks, Duration Estimation, and Critical Path
Time Management Ahmed Awad, Ph.D., PMP. Time Management It includes the processes required to ensure timely completion of the project. b Activity Definition.
Operations Management Contemporary Concepts and Cases Chapter Fourteen Project Planning and Scheduling Copyright © 2011 by The McGraw-Hill Companies,
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall o P.I.I.M.T o American University of Leadership Ahmed Hanane, MBA, Eng, CMA, Partner.
Where We Are Now. Where We Are Now Developing the Project Plan The Project Network A flow chart that graphically depicts the sequence, interdependencies,
The Critical Path – Precedence diagram method Luise Lorenz Christina Mohr.
Project Management Chapter 13 OPS 370. Projects Project Management Five Phases 1. Initiation 2. Planning 3. Execution 4. Control 5. Closure.
THE MANAGERIAL PROCESS Clifford F. Gray Eric W. Larson Developing a Project Plan Chapter 6.
1 7. R EPETITIVE C ONSTRUCTION Objective: To understand how production and production rates are affected by repetition of tasks, and to learn how to plan.
© Construction Management Association of America. Do Not Duplicate or Reproduce. Standards of Practice Course CPM Scheduling Lab.
Resource analysis Project management (lecture + seminar)
ENGM 631 Optimization Ch. 10: PERT/CPM. Great Pyriamid of Cheops (2,500 B.C.) 42,300,000 Stone Blocks 440 Stories 4Accuracy of 0.04 inch 413 acres level.
Dr. Hany Abd Elshakour 2/18/ :27 PM 1. Dr. Hany Abd Elshakour 2/18/ :27 PM 2 Time Planning and Control Activity on Arrow (Arrow Diagramming.
Project Planning & Scheduling What is a “project”? Objectives and tradeoffs Planning and Control in Projects Scheduling Methods Constant-Time Networks.
Network analysis Homework:
CE 366 PROJECT MANAGEMENT AND ECONOMICS Robert G. Batson, Ph.D., P.E. Professor of Construction Engineering The University of Alabama
Chapter 3 Project Management. Chapter 3 Project Management.
Project Management MGT 30725
Time Planning and Control Time-Scaled Network
Project Planning & Scheduling
PERT and CPM.
Time Planning and Control Activity on Node Network (AON)
Project Planning & Scheduling
Project Planning and Scheduling
Project scheduling Chapter 10 Copyright ©2016 Pearson Education, Inc.
Project Scheduling Chapter 14.
Projects: Critical Paths
Critical Path Method (CPM). Background & History Developed in the 1950s by the US Navy & Du Pont. Originally, the critical path method considered only.
Project Management CPM Method Tutorial-p2
Time Planning and Control Activity on Node Network (AON)
Developing a Project Plan
Project Scheduling: networks, duration estimation, and critical path
Time Planning and Control Time-Scaled Network
Project Scheduling Basics Activity on Node Precedence Diagrams
Software Project Management
Project Scheduling: Lagging, Crashing and Activity Networks
Basic Project Scheduling Line of Balance
Lecture 6: Time-Cost Trade-Offs
ENGINEERING MANAGEMENT (GE 404)
Time Planning and Control Activity on Node Network (AON)
Project management (seminar)
Software Project Management 4th Edition
Software Project Management 4th Edition
ELC 347 project management
Chapter 6 Activity Planning.
Lecture 5: Project Time Planning (Precedence Diagramming Technique)
LECTURE 3.
LINEAR BALANCE METHOD & MATRIX SCHEDULE
Chapter 6 Activity Planning.
Network analysis Homework:
ENGINEERING MANAGEMENT (GE 404)
University of Debrecen Mongolian University of Life Sciences
FACULTY OF ENGINEERING CONSTRUCTION AND BUILDING DEPARTMENT
Presentation transcript:

CHAPTER ONE: RESOURCE ALLOCATION AND SCHEDULING 1.7 Summary Diagrams Linear projects form an important part of construct ion projects. These projects contain repetitive construction works. Examples include long bridges and retaining walls, highways and pipelines. One method for preparing schedules for such projects is the summary diagram. This diagram can be constructed as follows: The repetitive work of one trade is represented by a single activity« The duration of this activity is the summation of the durations for individual activities within the trade. In order to maintain the logic of the network of such a project, relationships between the start of. each activity and the start of its successor and between the finish of each activity and the finish of its successor are introduced as follows: Start to start relationship = duration of individual predecessor Finish to finish relationship = duration of individual successor 1

CHAPTER ONE: RESOURCE ALLOCATION AND SCHEDULING The timings of each activity can be calculated as follows: ES of each activity = ES of its predecessor lag between them EF of each activity = EF of its predecessor + lag between them Or = ES of the activity + its duration (whichever is the longer) LF of each activity = LF of its successor - lag between them LS of each activity = LS of its successor - lag between them Or = LF of the activity - its duration (whichever is the shorter) 1. The early and late start timings of each activity represent timings of the first individual activity of each trade. On the other hand, the early and late finish timings of each activity represent timings of the last individual activity of the trade. Therefore, contract completion time equals finish time of the last activity in the summary diagram. 2

CHAPTER ONE: RESOURCE ALLOCATION AND SCHEDULING Example 1.6 The construction of a jetty is represented by three sequential activities: Pile driving, Pile cap and Deck construction. This sequence has to be repeated four times to finish the jetty. Table 1.10 gives durations of the activities for one part of the jetty. Construct the contract summary diagram using the precedence notation and compare it with the complete precedence diagram. 3

CHAPTER ONE: RESOURCE ALLOCATION AND SCHEDULING Solution The contract precedence diagram is shown in Figure 1.9 and the summary diagram is shown in Figure 1.10. 4

CHAPTER ONE: RESOURCE ALLOCATION AND SCHEDULING Figure 1.9: Summary Diagram for Example 1.6 5 Figure 1.10: Precedence Diagram for Example 1.6

CHAPTER ONE: RESOURCE ALLOCATION AND SCHEDULING From the summary diagram, it is obvious that the critical activities are: al1 sections of pile driving, then last sect ion of pile cap and then last sect ion of deck construct ion. The first sect ion of both pile cap and deck construction have a total float of three weeks each. The results of the summary diagram are compatible with the results of the precedence diagram on the assumption that durations of ail activities will not be changed. If the duration of one of the non-critical activities is changed, it wi11 be possible for the critical path to run through other activities and this will not be shown by the summary diagram.

CHAPTER ONE: RESOURCE ALLOCATION AND SCHEDULING 1.8 The Line of Balance CLOBD Method for Scheduling Repetitive Construction Works: The process of scheduling repetitive construction works aims at meeting a programmed rate of completed units and ensuring that a balanced mix of resources is kept fully employed. The LOB method achieves these objectives. The basis of the LOB technique is to find the required resources for each activity so that the following activities are not interfered with and the target completion rate can be achieved. Therefore, the difference between the LOB schedule and a networking technique is that the former is based on chosen set of resources to achieve a construction rate while the second is based on separating logic and resource allocation. The basic assumption of the technique is that each crew of labor should work at their natural rate. Figure 1.11 is used to compare between an activity LOB using one and two crews of labor. It is obvious that the inclination of the LOB will increase with the increase of the number of crews used.

CHAPTER ONE: RESOURCE ALLOCATION AND SCHEDULING 1.8.1Preparing an LOB Schedule The following steps demonstrate how an LOB schedule can be prepared for a contract: The man hours necessary, as well as the optimum crew size are estimated for each activity. This information may be obtained from field personnel who have many years of site experience or from previous records. Choose buffer times between the activities in order to absorb unforeseen events and errors. It can be assumed from knowledge of the likely variability of the preceding activity. Prepare a logic diagram for the activities of one of the many units to be constructed. Take into consideration the buffer times.

CHAPTER ONE: RESOURCE ALLOCATION AND SCHEDULING 1. Calculate the required target output in order to meet a given contract completion., date. Figure 1.12 demonstrates how this rate can be calculated.

CHAPTER ONE: RESOURCE ALLOCATION AND SCHEDULING Figure 1.11: An activity LOB (a) Using Single Crew (b) Using Two Crews

CHAPTER ONE: RESOURCE ALLOCATION AND SCHEDULING Figure 1.12: Determination of Target Rate of Build

CHAPTER ONE: RESOURCE ALLOCATION AND SCHEDULING For a contract with several activities, calculate the time required to complete all the activities in the first unit assuming all resources will be available, This time, should include buffer times between the activities. Then the target rate of build: r, is given by: r = 𝑁−1 (1.2) 𝑇𝑐− 𝑇𝐼 where N = no. of units to be constructed 𝑇𝐶 = chosen contract completion time.

CHAPTER ONE: RESOURCE ALLOCATION AND SCHEDULING The target rate of build should be expressed as a number of units per working period. The chosen working period must be used in al1 succeeding calculations, The number of crews necessary for the contract must be arranged in order that the rate of output is as close to the target rate of builds as possible. Assume the following notation: m= actual rate of output = slope of LOB. M= required man-hours per unit D= activity duration N= number of hours in a working period

CHAPTER ONE: RESOURCE ALLOCATION AND SCHEDULING 𝑆0 = optimum number of men/unit 𝑆𝑡 = theoretical gang size required to maintain r, 𝑆𝑎= actual gang size, a number which would be a multiple of𝑆0 if 𝑆𝑎 > 𝑆𝑇then m >r . ST = start time of activity in first unit which can be calculated from the Logic Diagram, and ST= start time of activity in the unit. Then we have : (1.3) (1.4) (1.5) (1.6) St= r .m/n M= r .sa / st D=M/(So.n) ST1 = ST1 + ( 1-1 ) / m, L ≤ N

CHAPTER ONE: RESOURCE ALLOCATION AND SCHEDULING Draw the LOB from the information obtained. The number of units to be constructed is plotted against time. Two parallelizes whose slope is equal to the actual rate of output, will denote the start and finish times respectively of each activity in al1 the units, from the first t: the last, the distance between the two 1ines represents the duration of the activity. Examine the schedule and assess possible alternatives to bring about a more balanced schedule.

CHAPTER ONE: RESOURCE ALLOCATION AND SCHEDULING Example 1.6 The construction of a long-reinforced concrete retaining wall involves the following three sequential activities: steel fixing, formwork erection and concreting. The wall is divided into 15 equal sections. The man hours required and the team size for each section are given in Table 1.11.

CHAPTER ONE: RESOURCE ALLOCATION AND SCHEDULING Data for example 1.6 Activity Man hours/section Team size/section Steel fixing (s) Formwork erection (F) Concreting (C) 576 1440 4 6 Prepare a 1ine of balance schedule for the contract using a target rate of builds of one section per week and each team working at their natural rate. Assume a minimum buffer time of three days between activities and six 8-hourdays per week. What is the overal1 duration of the contract and when will the first team of carpenters leave the site? 17

CHAPTER ONE: RESOURCE ALLOCATION AND SCHEDULING LOB Calculations for Example 1.6 Activity M 𝑆0 𝑆𝑡 𝑆𝑎 m D 𝑆𝑇𝑁 − 𝑆𝑇𝐼 Steel fixing Formwork Concreting 576 1440 4 6 12 30 1/6 18 84 18 Figure 1.14: LOB for Example 1.6

CHAPTER ONE: RESOURCE ALLOCATION AND SCHEDULING Solution Target rate of build; r = 1/6 sect i on per day The solution is given in Table 2.28 and Figures 2.29 and 2.30. The contract duration = 150 days. The first team of carpenters will leave the site on day 111. 19