HL-LHC - WP15 modifications Coffrets Prise C4L8

Slides:



Advertisements
Similar presentations
Study report on the TDC2/TCC2 Cabling and Low Voltage activities Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting
Advertisements

Backwards Compatibility L4 – L2 W. Weterings LBCC - 14.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
IBL Vacuum Box in UX15 Short summary Andrzej Zmuda
Update on Q1 TAS REGION (18 to 22m), layouts. D. Brethoux, M. Lazzaroni, F. Sanchez Galan, WP8 meeting1.
Observations and next works from the recent tests of the insertion tools of Mini-Drawers at CERN Roméo Bonnefoy and François Vazeille Tilecal Operation.
Plasma Wakefield (AWAKE) Project Meeting 18 October 2012 Civil Engineering Feasibility Issues for the West Area EDMS : John Osborne GS-SE.
A. Perin, CERN, TE-CRG, 26 May Review of the cryogenic by-pass for the LHC DS collimators 26 May 2011 Modifications to the DFBs, DSLC and cryogenic.
HLTC 15 th April 2014 EDMS: Y. Muttoni EN-MEF-INT with the contribution of P. Fessia.
High Energy Dump LSS5 STI Cost Estimate A.PERILLO MARCONE & F.PASDELOUP 2015/04/16 With contribution of R.FOLCH & D.GRENIER.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
LHC Insertions Upgrade Working Group (LIUWG) Space available in tunnel Y. Muttoni.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
LIU – TCDI. INTEGRATION STATUS 1 ST APRIL 2015 Frédéric Galleazzi EN/MEF/INT Antoine Kosmicki EN/MEF/INT EDMS :
Test beam setup: status report 31/03/2009 M. Alfonsi (CERN)
May 26 th 2005 Development and Management of the Installation Drawings for the LHC Machine Samy Chemli, Jean-Pierre Corso, Yvon Muttoni TS-IC.
Technology Department LSS2 modifications Impact on the vacuum systems LTEX - 18/01/2011 Eric PAGE – TE-VSC.
12th HL-LHC Parameter and Layout Committee meeting.
February 14, Comprehensive Review B. Schmidt Outline: Status and overview of activities: –Platforms and staircases –Muon Filters and beam plugs.
 Based on 2+2 Roman Pot Stations on each side of ATLAS at ~ 240 m from the Interaction Point  Aim in Run 2 at measuring the total cross section and.
The integration of 420 m detectors into the LHC
TAS-Q1 Status & what if exercise Etude [HL-LHC] TAS-Q1.
Proposal for routing of ATLAS TAXS region HL-LHC WP8.
R ADIATION P ROTECTION ASPECTS LSS1 LHC f RE - INSTALLATION Cristina Adorisio (CERN - DGS/RP) LTEX Meeting – May 10 th, 2012.
ECR - PSB: New KSW magnet in 16L1 Luis Feliciano, 4 th February.
Proposal for rerouting of buried electrical networks and optical fibres at Point 1 LS2 Committee meeting S. Bertolasi on behalf on EN/EL WP17.2 HL-LHC.
Adriana Rossi BE/ABP on behalf of the collimation project (BE/ABP-EN/STI-TE/VSC-EN/ACE) Adriana Rossi BE/ABP on behalf of the collimation project (BE/ABP-EN/STI-TE/VSC-EN/ACE)
SPS movable table Joanna Swieszek, Kurt Artoos (EN-MME) 14/04/2016.
September 5, Burkhard Schmidt Integration and Installation Outline: Integration and Infrastructure issues -Suspended platforms -Cable chains -Beam.
Electrial Safety LS2 days November 2016 AP
Florian Buchsteiner (HEPHY Vienna)
SMR 21/09/2017 P. Fessia.
TCT BLM response from tertiary halo at 6.5 TeV
L. Gentini, A. Bertarelli, F. Carra
Update on the Critical Path of the PS Booster Schedule for the EYETS
Roadmap for triplet cryostats
Alignment of VSC components along LSS 1&5
MEMORANDUM Cabling and Electrical activities requests YETS 2017/2018
TAXS and TAXN ABSORBERS - OVERVIEW
TANB Integration – LS2 BLM Relocation Proposal C4R8 and C4L8
Equipment simplified model SMR UR safety
Installation of an Instrument on a CERN machine
Feasibility and implication of installation of the string test in SM18 with a slope M. Bajko WP16.
Preliminary Y-chamber specifications – First draft
Components for the Machine-Interface Regions
M. Alcaide Leon, Paolo Fessia
YETS & LS2 Reminder G. Girardot 20 juin 2017.
Region between TAXN and D2 in HL-LHC IR1/5: Implications on Collimator Design Alessandro Bertarelli, L. Gentini (EN/MME) On behalf of the LHC.
M. Alcaide Leon, Paolo Fessia
Progress with Experimental Vacuum Chambers
EN-STI activities in LHC during EYETS
B. 163 facility upgrade: work space options in B. 163 and B. 103 F
A very first look at siting issues
ATLAS ITk CO₂ Cooling pipe routing CO₂ Meeting, 28 June 2016
Extension SR1 WP3 Electrical installations
ATLAS ITk CO₂ Cooling pipe routing Common Mechanics meeting
The 11T cryo-assembly: summary of design and integration aspects
Proposal for the modification of building 151 in view of the LS2 PS main magnet and TT2 consolidaiton projects Dominique Bodart TE-MSC-MNC 29/09/2017.
TECHjOSH.COM TechJosh.com.
Impedance working group update
LST Module Installation
WP3 Meeting – December the 10th 2015 H. Prin
Ch. Boccard, M. Krupa, G. Schneider, R. Veness, M. Wendt
Triplet corrector layout and strength specifications
HL-LHCV1.4 (BI) R. De Maria WP13 meeting 3/9/2018.
LS3 Study & Readiness Meetings
Access Control for CERN Experimental Areas
BRAN: LS2-plans TREX M. Palm, E. Bravin, BE-BI-PM.
ECR on pole order of the HL-LHC IT circuit and resulting implications
HL-LHCV1.4 (BI) R. De Maria WP13 meeting 3/9/2018.
Presentation transcript:

HL-LHC - WP15 modifications Coffrets Prise C4L8 P. Santos Díaz, Y. Maurer, N. Latif, Thanks for the contribution of M. de la Aleja Cabana Reunion ICL Machines LHC - SPS CERN, 22th May 2019 EDMS: 2149413 v1.1

Outline Introduction Discussion Proposed solution Conclusions Pablo Santos Díaz EDMS: 2149413 v1.1

1. Introduction Pablo Santos Díaz EDMS: 2149413 v1.1

Location of the TANB installation in L8 The TANB will be installed between D2 and the TCTPH and in consequence, the BPMs will be displaced next to the Y-chamber. D2 Y-chamber TANB TCTPH TCTPV BPMs Electrical boxes concerned Pablo Santos Díaz EDMS: 2149413 v1.1

2. Discussion Pablo Santos Díaz EDMS: 2149413 v1.1

Present situation During the visit on 24/03/2019, it was noticed that there might not be enough space for the BPMs drilling plate integration. Space for the BPMs drilling plate Situation after 1st intervention. 24/04/2019 Pablo Santos Díaz EDMS: 2149413 v1.1

BPMs drilling template integration 55m+465mm=520mm are requested. Drilling template 230mm 55mm 465mm 546mm 278mm 87mm Pablo Santos Díaz EDMS: 2149413 v1.1

Integration check 55m+465mm=520mm are requested and ≈480mm available. Situation on 24/04/2019 Pablo Santos Díaz EDMS: 2149413 v1.1

3. Proposed solution Pablo Santos Díaz EDMS: 2149413 v1.1

Proposal for the new position of the electrical boxes [I] Displace the electrical boxes about 2.5m away toward the IP8. Pablo Santos Díaz EDMS: 2149413 v1.1

Proposal for the new position of the electrical boxes – integration model Any inconvenient from the plugs users? Pablo Santos Díaz EDMS: 2149413 v1.1

Proposed new telex routing Even closer to the main telex. Main telex Present routing Proposed routing Pablo Santos Díaz EDMS: 2149413 v1.1

Proposed new detailed position (top view) It provides enough space for installation. Telex on the floor 150mm 100mm Pablo Santos Díaz EDMS: 2149413 v1.1

3. Conclusions Pablo Santos Díaz EDMS: 2149413 v1.1

Conclusions Displacement of the electrical boxes is required for the BPMs drilling template integration. Proposal: displace them about 2.5m towards IP8 where there is clear space. Preliminary cost estimation: ≈500CHF. Pablo Santos Díaz EDMS: 2149413 v1.1

THANK YOU FOR YOUR ATTENTION!!!

Spare slides Pablo Santos Díaz EDMS: 2149413 v1.1

Present telex routing Situation after 1st intervention. 24/03/2019 Pablo Santos Díaz EDMS: 2149413 v1.1

Site visit on 12/03/2019 Left side of point 8. ACTION: coffret on left side to be installed together with the other two coffrets on the right side in a common new support. Connected cables can be shifted towards the IP to clear the space (cables position have to be 5cm away from the Y-chamber support for space allowance in case of vacuum support removal). Situation prior LS2 Pablo Santos Díaz EDMS: 2149413 v1.1