LCLS Instrument MIE Project: Staffing, Schedule

Slides:



Advertisements
Similar presentations
Tom Fornek LUSI June 17, LUSI UPDATE – June, 2008.
Advertisements

Stefan Moeller XES FAC Review – April 16, 2006 X-Ray Endstation Systems (XES) Status Stefan Moeller.
John N. Galayda LCLS Facility Advisory November 11, LCLS Update November 11, 2008 Construction Status LCLS Instruments.
John Arthur X-ray November 11, 2008 SLAC National Accelerator Laboratory 1 X-ray Overview LCLS Directorate structure.
Richard M. Bionta XTOD October 12, 2004 UCRL-PRES-XXXXX X Ray Transport, Optics, and Diagnostics, Overview Facility Advisory Committee.
John N. Galayda LCLS FAC 20 April Linac Coherent Light Source Overview and Charge Facility Advisory Committee John.
John Arthur LCLS September 26, 2005 John Arthur SLAC LCLS Construction and Science.
J. B. Hastings LUSI Overview LCLS FAC March 20, 2007 LUSI Overview J. B. Hastings January 2007 Lehman Review Response to Lehman Review.
J. B. Hastings LCLS User October 12-13, 2004 LCLS User Program J. Hastings SLAC/SSRL.
Diffraction studies of stimulated dynamics (pump-probe) Coherent-scattering studies of nanoscale fluctuations Atomic, molecular and optical science High.
John Arthur Photon Systems April 16, LCLS Photon Systems Status Technical status and accomplishments Response to.
John Arthur Photon October 29, Photon Systems Update FAC recommendations Current status New plan for Photon Systems.
John Arthur Photon October 27, Photon Systems Overview John Arthur SLAC.
LCLS Transition to Science DOE Status Review of the LUSI MIE Project NEH status and XFD operations Hal Tompkins, John Arthur LCLS Experimental Facilities.
John Arthur Photon April 20, 2006 Photon Systems Update John Arthur SLAC Photon Systems Manager.
1 T. Fornek 1 LUSI CXI FIDR June 3, 2009 Thomas Fornek Project Manager June 3, 2009 LUSI Coherent X-Ray Imaging Instrument Final.
John Arthur PIXEL Project April 7, 2005 Status of the Proposed PIXEL Project John Arthur SSRL/SLAC Photon Instrumentation.
1 T. Fornek 1 LUSI XCS FIDR June 17, 2009 Thomas Fornek Project Manager June 17, 2009 LUSI X-Ray Correlation Spectroscopy Instrument.
John Arthur X-ray April 20, 2006 X-Ray Beamline and Experiment Layout John Arthur LCLS Photon Systems Manager.
John Arthur Photon October 12, Photon Systems Update John Arthur SLAC 1.
Stefan Moeller XES Plan for FAC Review - April 20, 2006 X-Ray Endstation Systems (XES) Status and Plan for FY06 Stefan Moeller.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Baseline Jim Yeck NSLS-II Deputy Project Director NSLS-II PAC Meeting November 20, 2007.
Keith O. Hodgson SSRL Director Brief Update on the Linac Coherent Light Source - LCLS February 26, 2002 Basic Energy Sciences Advisory Committee Undulator.
W.J. Foyt LUSI DOE Review July 23, 2007 Project Management 1 Project Management W. J. Foyt Project Scope Timeline Cost Estimate.
7/26/2006 Wyatt Merritt 1 DECam CD1 Documentation DOE Critical Decision Process Documentation Requirements.
DOE Stanford Site Office Office of Science U.S. Department of Energy 1 U.S. Department of Energy’s Office of Science Office of Science Review of the LCLS.
SCT Project Management Issues
LCLS User Access Policy
Project Management W. J. Foyt
X-ray Correlation Spectroscopy (WBS 1.4) Aymeric Robert
LUSI Coordination with LCLS
Experimental Facilities Planning
X-ray Pump-Probe (WBS 1.2) David Fritz
Preparations for a Lehman Review
LCLS Ultrafast Science Instruments
X-ray Pump-Probe Instrument
1 Zoe Van Hoover 1 User Safety: Commissioning and Early Experiments NEH ARR User Safety: LCLS NEH Commissioning and Early Experiments.
LUSI X-ray Pump-Probe Instrument WBS 1.2
Linac Ops Budget Review LCLS Overview / Org Structure / Legacies
Linac Ops Budget Structure & Approach WBS 1 – LCLS Mgmt & Admin
LINAC OPS Budget Review
LCLS History and Science Overview Keith Hodgson, SSRL Director April 23, 2002 LCLS DOE Review, April 23, 2002 Keith Hodgson, SSRL.
X-ray Pump-Probe Instrument
Thomas Fornek Project Manager July 15, 2009
X-Ray Endstation Design & Management/Commissioning
X-Ray Transport, Optics, and Diagnostics WBS Alan J
X-ray Pump-Probe Instrument
X-Ray Endstations Update
Tom Fornek Project Manager April 20-22, 2009
Details supporting the increase
LUSI MANAGEMENT OVERVIEW
DOE Review of the LCLS Project
Project Management Issues John N. Galayda, SLAC April 24, 2002
Synchrotron Science and User Program at SSRL A Brief Overview for the Context of LCLS Presented to the DOE Review of the LCLS Project Keith O. Hodgson,
Endstation Systems, Installation Costs and Schedule J. Hastings
EVMS Status and Overview
Experimental Program and Endstations System (WBS ) J
John Arthur – LCLS Experimental Operations
NEH - Status Stefan Moeller.
The Transition to User Operations
PIXEL Project Status John Arthur Photon Instrumentation for
X-ray Correlation Spectroscopy Instrument
Linac Coherent Light Source Project Update
Linac Coherent Light Source Transition to Operations 11 July 2007
Preliminary Project Execution Plan
X-Ray Endstation Design & Management/Commissioning
LUSI Status and Early Science
X-Ray Endstation Systems (XES) 2006 Schedule
LCLS Photon Systems Overview
Presentation transcript:

LCLS Instrument MIE Project: Staffing, Schedule John Arthur SLAC Photon Instrumentation for X-ray Experiments

What is the Instrument MIE project How will the project be organized

Instruments Ultrafast x-ray studies of laser-induced transient states of matter Nano-particle and single-biomolecule (non-periodic) imaging Nanoscale equilibrium dynamics in condensed matter Soft x-ray imaging and dynamics

Detector Development LCLS experiments need new detector technology Dual development strategy for fast 2-d detectors Several technologies look promising, no clear leader LCLS will pursue one strategy MIE will try a different technology Both prototypes should be ready by 2009

LCLS Detector Advisory Committee Held first meeting Feb 28 - March 1, 2005 Reviewed proposals for 2-d detector development Based on their review, MIE has decided to collaborate with BNL on 2-d detector R&D, leading to at least one prototype detector in 2008-9 LDAC will continue to review MIE and LCLS detector R&D LCLS will hire a detector scientist to manage the efforts

Instrument MIE Phased Approach First LCLS light may come in mid-2008 Budget will not support building 4 instruments by 2008 Phased approach 2 instruments in phase 1 sufficient functionality by mid-2008 to begin experiments phase 1 instruments can support early work in all four areas complete phase 1 while phase 2 is ramping up remaining instruments in phase 2 begin phase 2 after 2008 complete all work in 2012

An LCLS instrument costs $12-15M Controls (including laser timing)+Computers Slits Flight path Valves/windows/pumps KB focusing system (1 µm and sub-µm options) X-ray pulse split+delay with table Crystal monochromator with table Diffractometer with table Optical table for laser Laser PPS Laser system (10 mJ Ti:sapphire plus OPA) Laser diagnostics X-ray diagnostics 2d detector Typical LCLS “instrument” + PEOPLE

LCLS in 2008-9 possible layout NEH Soft X-ray Station AMO Physics (funded by LCLS) Hard X-ray Imaging Station Coherent imaging (MIE) Hard X-ray Diffraction Station Pump-probe dynamics (MIE) Nanoscale dynamics (MIE) FEH

LCLS in 2012 NEH Soft X-ray Station AMO Physics Magnetism, surfaces Hard X-ray Imaging Station Coherent imaging Hard X-ray Diffraction Station Pump-probe dynamics Hard X-ray Diffraction Station Nano-dynamics of solids Hard X-ray Station Extreme states of matter (assumes funding found) FEH

SSRL Asst. Dir for LCLS Science Keith Hodgson SSRL Director Instrument MIE organization LCLS Science Teams Jerry Hastings SSRL Asst. Dir for LCLS Science John Arthur Project Director TBD Project Chief Engineer Budget ES&H PMCS Database Purchasing Administration Inst #1 Instrument Scientist Engineering & Development 4-5 Engineers 2-3 Designers Inst #2 Instrument Scientist Inst #3 Instrument Scientist Inst #4 Instrument Scientist

Role of the LCLS Science Teams Teams are responsible for preparing physics specs for MIE instruments Teams have designated leaders Quarterly meetings at SLAC with leaders Start weekly teleconferences soon Yearly general meeting (Oct) Web site is up

Draft WBS to level 3 4 instruments OPC

Draft WBS Instrument partial, to level 5 Major project function (design, fab) Instrument subsection (lasers, detectors) Major component (monochromator)

Proposed funding profile $millions Good possibility of funding in 2006 Total = $50M-$60M

Project Staffing Now: 2 people Next 6 months: 11 more people Proj. Director (J. Arthur), Proj. Chief Scientist (J. Hastings) Next 6 months: 11 more people 3 Inst. Scientists (hard x-ray instruments) Admin (Chief Engineer, ES&H, Budget, PMCS) Engineering (2 Inst. Physicists, Designer, Control Eng.) By end of FY06: 6 more Admin (Administrator, Database/Web Manager, QA Manager) Engineering (second Designer, Programmer) Some of the Admin people are matrixed with other SLAC groups

SSRL Asst. Dir for LCLS Science Keith Hodgson SSRL Director Instrument MIE organization in Dec-05 LCLS Science Teams Jerry Hastings SSRL Asst. Dir for LCLS Science John Arthur Project Director TBD Project Chief Engineer Budget ES&H PMCS Database Purchasing Administration Inst #1 Instrument Scientist Engineering & Development 2 Engineers 1 Designer Inst #2 Instrument Scientist Inst #3 Instrument Scientist Inst #4 Instrument Scientist

SSRL Asst. Dir for LCLS Science Keith Hodgson SSRL Director Instrument MIE organization in Oct-06 LCLS Science Teams Jerry Hastings SSRL Asst. Dir for LCLS Science John Arthur Project Director TBD Project Chief Engineer Budget ES&H PMCS Database Purchasing Administration Inst #1 Instrument Scientist Engineering & Development 3 Engineers 1 Programmer 2 Designers Inst #2 Instrument Scientist Inst #3 Instrument Scientist Inst #4 Instrument Scientist Hire in 2009

Proposed Project Milestones CD0 (Statement of mission need, begin project) Q3 2005 CD1 (Completion of conceptual design) Q3 2006 CD2a (Baseline costs of Phase 1) Q1 2007 CD3a (Begin construction of Phase 1) Q3 2007 CD4a (Finish Phase 1) before 2012 CD2b 2009 CD3b 2010 CD4b (Finish Phase 2) Q4 2012 Detector development program will be included in Phase 1

Summary The funding profile constraints on the instrument MIE project, along with the LCLS schedule, indicate that a phased approach is needed Two instruments in Phase 1, two in Phase 2 Detector development program in Phase 1 Funding for this project is lean through FY06 Overall funding through FY12 is adequate if profile is maintained Rapid increase of staff in FY06, proximity to SSRL and other SLAC groups will help Strong support from the Science Teams will be needed, good communication is a priority Expect CD0 very soon, ready to start on CDR