GLAST Large Area Telescope: I&T Test Readiness Review

Slides:



Advertisements
Similar presentations
GLAST LAT ProjectNovember 3, 2005 I&T Phase 0 IRR/TRR 1 GLAST Large Area Telescope: Integration and Test Phase 0 IRR/TRR November 3-4, 2005 Introduction.
Advertisements

GLAST LAT Project Managers F2F Integration and Test 1 GLAST Large Area Telescope: Face to Face Managers Meeting LAT Integration & Test April.
GLAST LAT ProjectNovember 18, 2004 I&T Two Tower IRR 1 GLAST Large Area Telescope: Integration and Test One and Two Tower Integration Readiness Review.
GLAST LAT Instrument GLAST Monthly Mission Review August 6, 2007 K. Fouts, SLAC 1 Monthly Mission Review Project Status Overview August 6, 2007 Ken Fouts.
GLAST LAT ProjectMonthly Status Meeting Jan 26, Project Status January 26, 2006 Gamma-ray Large Area Space Telescope Lowell A. Klaisner Project.
GLAST LAT ProjectOnline Peer Review – July 20, Integration and Test R. Claus 1 GLAST Large Area Telescope: I&T Integration Readiness Review.
GLAST LAT Project LAT System Engineering 1 Test Definition Planning Pat Hascall SLAC System Engineering Gamma-ray Large Area Space Telescope.
GLAST LAT ProjectNovember 04, 2005 Phase 0 TRR 1 GLAST Large Area Telescope: Integration and Test -Electrical Test- Phase 0 TRR Key Requirements Documents.
GLAST LAT ProjectOnline Roadmap Progress Report – April 22, 2004 R. Claus1 Online Roadmap to the July 2004 Freeze Progress report for April 22, 2004 (to.
GLAST LAT ProjectOnline Peer Review – July 21, Integration and Test J. Panetta 1 Gamma-ray Large Area Space Telescope GLAST Large Area Telescope:
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review Presentation 6 of 12 LAT Test Results 1 GLAST Large Area Telescope Pre-Environmental Test.
SVAC Instrument Analysis Meeting Aug 5, 2005 E. do Couto e Silva and Anders W. Borgland 1/7 SVAC 8 tower testing+ACD Anders and Eduardo.
GLAST LAT Project Technical/Cost/Schedule Review 03/31/ Integration and Test 1 GLAST Large Area Telescope: I & T Input to Monthly Technical/Cost/Schedule.
GLAST LAT Project4 April 2005 LAT System EngineeringLAT Test Planning Meeting GLAST LAT GLAST LAT System Engineering Gamma-ray Large Area Space Telescope.
GLAST LAT Project Technical/Cost/Schedule Review 09/01/ Integration and Test 1 GLAST Large Area Telescope: I & T Input to Monthly Technical/Cost/Schedule.
GLAST LAT ProjectNovember 3, 2005 I&T Phase 0 IRR/TRR 1 GLAST Large Area Telescope: Integration and Test Phase 0 IRR/TRR November 3-4, 2005 Introduction.
Trending ACD performance Parameters of interest Online tests (CPTs) TCI (charge injection) -> PHA TCI -> Veto mapping Timing PHA Pedestals Offline tests.
GLAST LAT Project Technical/Cost/Schedule Review 03/30/ Integration and Test 1 GLAST Large Area Telescope: I & T Input to Monthly Technical/Cost/Schedule.
GLAST LAT Project SE Test Planning meeting October 4, 2004 E. do Couto e Silva 1/13 SVAC Data Taking during LAT SLAC Oct 4, 2004 Eduardo.
GLAST LAT ProjectDOE/NASA Status Review, March 30 & 31, 2004 Integration and Test 1 Integration, Facilities, Configuration, and Test (IFCT) Flow Procedure.
GLAST LAT Project28 March 2005 LAT System EngineeringLAT Test Planning Meeting GLAST LAT GLAST LAT System Engineering Gamma-ray Large Area Space Telescope.
GLAST LAT Project November 18, 2004 I&T Two Tower IRR 1 GLAST Large Area Telescope: I&T Integration Readiness Review Integration, Facility, Configuration.
GLAST LAT ProjectLAT Planning Meeting July 17 th and 18 th Integration and Test 1 GLAST Large Area Telescope: I & T Input to LAT Planning Meeting.
GLAST LAT ProjectNovember 18, 2004 I&T Two Tower IRR 1 GLAST Large Area Telescope: Integration and Test One and Two Tower Integration Readiness Review.
GLAST LAT ProjectOnline Peer Review – July 21, Integration and Test L. Miller 1 GLAST Large Area Telescope: I&T Integration Readiness Review.
Sep/26/05Trigger test plan Trigger ACD/LAT Test Plan Eric Grove, Martin Kocian, Su Dong.
GLAST LAT Project Test Planning Meeting Dec 5, 2005 E. do Couto e Silva 1/5 Final Proposal for Phase 1 and 2 SVAC, E2E Tests (hereafter LAT 70X, 80X) Eduardo,
GLAST Large Area Telescope:
GLAST LAT Project4 April 2005 LAT System EngineeringLAT Test Planning Meeting GLAST LAT GLAST LAT System Engineering Gamma-ray Large Area Space Telescope.
GLAST LAT ProjectFace to Face Managers Meeting 04/14/ Integration and Test 1 GLAST Large Area Telescope: I & T Input to Face to Face Managers.
GLAST LAT Project LAT Instrument Analysis Workshop – Feb 27, 2006 Hiro Tajima, TKR Data Processing Overview 1 GLAST Large Area Telescope: TKR Data Processing.
GLAST LAT ProjectLAT Muons at NRL 28 Feb 2006 J. Eric Grove Naval Research Lab Washington DC LAT Muon Data Taking During Environmental Test at NRL J. Eric.
GLAST LAT Project LAT System Engineering 1 GLAST Large Area Telescope: LAT System Engineering Pat Hascall SLAC System Engineering Manager
GLAST LAT Project IA Workshop 4 July 14, 2005 E. do Couto e Silva 1/7 Introduction to the Instrument Analysis Workshop 4 Eduardo do Couto e Silva July.
GLAST LAT Project IFC Tour – Sep 5,2003 Larry Wai 1 GLAST Large Area Telescope: Integration and Facility Status Larry Wai SU-SLAC Integration and Facility.
GLAST LAT Project LAT Instrument Analysis Meeting– Aug 29, 2005 Hiro Tajima, TKR Updates at SLAC 1 GLAST Large Area Telescope: TKR Updates at SLAC Hiro.
GLAST LAT ProjectNovember 18, 2004 I&T Two Tower IRR 1 GLAST Large Area Telescope: Integration and Test Two Tower Integration Readiness Review SVAC Elliott.
GLAST LAT Project SE Test Planning Dec 7, 2004 E. do Couto e Silva 1/27 Trigger and SVAC Tests During LAT integration Su Dong, Eduardo do Couto e Silva.
GLAST Large Area Telescope:
GLAST Large Area Telescope:
GLAST Large Area Telescope:
Single-CAL Test and Calibration
GLAST Large Area Telescope:
GLAST Large Area Telescope:
GLAST Large Area Telescope
GLAST Large Area Telescope:
GLAST Large Area Telescope:
GLAST LAT System Engineering
GLAST Large Area Telescope:
GLAST Large Area Telescope: I&T Integration Kickoff Meeting
GLAST Large Area Telescope Instrument Science Operations Center
GLAST Large Area Telescope:
16:00 Meeting Fri. June 18 Mon. June 21 Tue. June 22 Wed. June 23
EPU load – same as SIU load except…
08:00 Meeting Fri. June 18 Mon. June 21 Tue. June 22 Wed. June 23
LAT Test Results GLAST Large Area Telescope LAT Pre-Shipment Review
GLAST Large Area Telescope:
Overview Goal Study GEM variables in SVAC ntuple
GLAST Large Area Telescope:
GLAST Large Area Telescope:
GLAST Large Area Telescope:
GLAST LAT System Engineering
Integration and Test Organization Chart
GLAST LAT System Engineering
GLAST Large Area Telescope: I&T Test Readiness Review
GLAST Large Area Telescope:
Introduction and Overview
Overview Cost to Complete
GLAST Large Area Telescope:
GLAST Large Area Telescope: Deputy for Systems Engineering
Presentation transcript:

GLAST Large Area Telescope: I&T Test Readiness Review Gamma-ray Large Area Space Telescope GLAST Large Area Telescope: I&T Test Readiness Review I&T Test History and Plans November 4, 2005 Larry Wai IFCT Manager SLAC

Tests Executed to Date “short tests” Receiving tests 10,12,14 bay tests NCR related tests STR tests Major test series Single bay tests 2-tower tests 4-tower tests 6-tower tests 8-tower tests 16-tower tests

LAT CPT – TKR History Module level CPTs executed through 6-tower tests Acquisition in parallel from all modules from 8-tower tests

LAT CPT – CAL History Module level CPTs executed through 6-tower tests Acquisition in parallel from all modules from 8-tower tests

LAT Operational Tests (pre-ACD) System configurations Timing (first 8 bays only) Trigger request alignment Trigger acknowledge optimization Trigger thresholds (first 8 bays only) Data Collection Calibration (first 8 bays only) Charge injection data Cosmic ray trigger data Efficiency (first 8 bays only) Muon Telescope End-to-end (first 2 bays only) Various rates, configs

Open Test NCRs Open test NCRs reviewed by I&T, systems, QA, ELX, TKR, CAL, ACD All agree – OK to install ACD More in Pat’s talk

16 Towers + ACD tests (pre-FSW) Pre-test review at 2pm, Tuesday Nov.8

16 Towers + ACD tests (LICOS/FSW) Pre-test review ~11/23 will cover: LATTE tests w/ LICOS-compatible CPT scripts LICOS/FSW tests EGSE Mobile computing rack (Linux) LATTE (backdoor) LICOS/FSW/SIU/VSC/associated EGSE