Overview of the TARGET Monolith Rough Vacuum

Slides:



Advertisements
Similar presentations
Oak Ridge SNS Experimental Facilities X /arb 1 SNS MPS Review Target-MPS Review WBS Ron Battle Target Controls, Target Systems Experimental.
Advertisements

ESS Cryogenic System Process Design Philipp Arnold Section Leader Cryogenics CEC – ICMC 2015 June 29, 2015.
The ESS vacuum team has overall responsibility for all technical vacuum systems used on the: Accelerator, Target and Neutron Scattering Instruments and.
Patrick Thornton, SNS/FPE June 9, 2008
Introduction and Charge to the Review of ESS Target building and Instrument Hall design requirements Roland Garoby November 2014, Lund
ESS Cryogenic Distribution System for the Elliptical Linac MBL/HBL - CDS requirements Preliminary Design Review Meeting, 20 May 2015, ESS, Lund, Sweden.
Hydrogen system R&D. R&D programme – general points Hydrogen absorber system incorporates 2 novel aspects Hydrogen storage using a hydride bed Hydrogen.
MICE CC Test Status Ruben Carcagno 11/06/13 1. Cooldown Coil Temperature (calculated average in each of 8 coil segments) SC Transition (voltages across.
Response to TAC8 and Annual Review Recommendations John Haines Head of Target Division April 2, 2014.
WP 12.3 Moderator & Reflector Systems D. Lyngh, M. Kickulies, J. Ringnér, J. Jurns, Y. Bessler (FZJ), M. Klaus (TUD), H. Quack (TUD) TAC12 Presenters:
Progress on Remote Handling Systems TAC 12 Magnus Göhran – WPM 15 th October 2015.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
Shrikant_Pattalwar TTC 2015 Dec 1, 2015 SLAC 1 Horizontal Tests in a Vertical Cryostat Shrikant Pattalwar STFC Daresbury Laboratory UK.
Risk Analysis P. Cennini AB-ATB on behalf of the n_TOF Team  Procedure  Documents in preparation  Conclusions Second n_TOF External Panel Review, CERN,
Installation of the T600 at Fermilab CSN2, September 22,
General overview of WU : Cryogenic Distribution for Elliptical Linac Jarosław Fydrych Cryodistribution Project Engineer Preliminary Design Review,
Details on the Accelerator Installation Plan E. Sargsyan & L. Lari 20 April 2016.
ESS Vacuum Systems TAC 6 November 2012 Peter Ladd Senior Vacuum Expert.
Thomas Jefferson National Accelerator Facility Page 1 Dana Arenius Cryogenics Control Account Manager 12 GeV Upgrade Project X Collaboration September.
Shrikant_Pattalwar ICEC 26, March 7-11, 2016, Delhi 1 Horizontal Tests in a Vertical Cryostat Shrikant Pattalwar STFC Daresbury Laboratory UK.
ESS Vacuum Standardization
Update on the ESS monolith design Rikard Linander Monolith and Handling Group ESS Target Division TAC 10, Lund, Nov 5,
Target Systems and Monolith Design Update Rikard Linander Group Leader Monolith and Handling April 2, 2014.
1 IPN Orsay / Division Accélérateurs The Spoke cryomodule Vacuum aspects P. DUTHIL on behalf of the IPNO team ESS Lund February 19 th 2013.
ESS Cryomodule Status Meeting – Introduction | | Christine Darve Introduction to Cryomodules for the ESS 2013 January, 9 th Christine Darve.
The ESS Target Station Eric Pitcher Head of Target Division February 19, 2016.
WP 12.3 Moderator & Reflector Systems D. Lyngh, M. Kickulies, J. Ringnér, J. Jurns, M. Andersson, M. Pucilowski, T. Hedlund, A. Olsson TAC11 Lund, 1 st.
ProtoDUNEs Interface documents (NP-02, NP-04) David Montanari (on behalf of Redouan A, Mark A, Johan B, Michel C, Joaquim C, Aurelien D, Kevin H) Apr 14,
Slides for TAC meeting Oct/2015 Marcelo juni Ferreira Vacuum section leader October,
Vishy Ravindranath LCLS-II 2 K Cold Box FDR March 9, 2017
News and Introduction from CERN June 15th, 2005
2K Cold Box FDR Introduction
Hydrogen System Update
Cryomodule test stand at ESS site
He Plant, LN2 Systems and Commissioing
Making Difficult Decisions in a Transparent Way –
Sub-system integration for the VBOX
Proximity Cryogenics P&IDs meeting
Cryoplant Installation Scope
Dana M. Arenius Jefferson Laboratory Cryogenics Dept Head
Leak Detection Tutorial Work
SPS cryogenic proximity equipment and SM18 validation
Hongyu Bai LCLS-II 2 K Cold Box FDR March 9, 2017
Spoke CDS PDR Closeout J. G. Weisend II June 10, 2016.
UK RFD Pre-Series cryomodule
Horizontal Tests in a Vertical Cryostat
Optimum cryomodule length at the ESS
ESS elliptical cryomodule
Target collaboratin Board Meeting
Operator Training Requirements
ESS Project Status Roland Garoby – Technical Director August 2018.
Jaroslaw Fydrych SHC Lead Engineer
Installation of Photon Beam Transport to FEH
ESS Freia Scope Setting ESS - Lund - 17/10/2016.
Cryomodule Assembly Plan
Daresbury ESS In-Kind Contributions
ISRC and LEBT Vacuum System Design
SNS PPU Helium Vessel Design and Assembly
IKON 15 Talal Osman & Iain Sutton
RSFs & categorisation 20 May, 2019.
APTM and GRID interface requirement PBIP and PBW
Czech in kind contribution – target technologies
CDS-EL IRR Closeout 28 March 2019 J.G. Weisend II, Chairman.
Michail Anastasopoulos Lead Detector – Design Engineer
Target Safety System Interfaces
Vacuum Control System for Monolith Vacuum
MRV system budget and scheduling Short overview installation
Vacuum System Design for the Target Monolith System
SNS PPU Cryomodule Design Overview
General Overview of WP 12 ESS Vacuum System
Presentation transcript:

Overview of the TARGET Monolith Rough Vacuum Dr. Marcelo juni Ferreira ESS Vacuum Section Leader European Spallation Source ERIC 28/05/2019

Outline Background of ESS monolith solution, Introduction to ESS Vacuum System, Vacuum Standardization Vacuum requirements: TARGET Monolith Rough Vacuum System specifications and interfaces,

ESS Monolith Vacuum System Brief history April/2014 First discussion with Target Div. about the He and Vacuum specifications, for big vessels and possibilities to run in He. Dec/2014 Considerations for the elimination of the Proton Beam Window, Feb/Mar 2015 Detailed discussions on the PBW elimination, Nov/2015 PDR for the Monolith vessel made clear: He and Vacuum solution present the same ”cleaning” requirements, what translate in following ”vacuum standards” for fabrication (welding, cleaning, leak rates…), PBW shall be persuade in any solution + He is possible solution as SNS, the monolith vessel shall follow pressure code. Dec/2015 to April/2017 Evolution of the vacuum and He solutions as possible. Details discussions for vacuum fabrication and design. April/2017 Final decision to persuade only vacuum solution. Fabrication following high vacuum standards, operation rough vacuum (a part discussion for Beam Instrumentation). Feb/2019 Formal responsibility transfer of the Monolith Rough Vacuum System to the ESS Vacuum Section. May/2019 Monolith Rough Vacuum CDR (alignment of scope for Vacuum Section responsibilities)

Introduction Target tank diameter 6 m x 9m Warm LINAC Cold LINAC Accelerator ≈ 600 m Neutron Instruments Neutron Instruments ≈ 120 m/each Total = 22 x 120 ≈ 2240 m The ESS organization charges the ESS Vacuum Section (VS) with the responsibility for all ESS vacuum systems including not only the Accelerator, but also Instruments, Neutron Beam Lines and the Target. The main task of the ESS VS is to support the in kind contributions on the vacuum system and the integrated vacuum design of the ESS complex.

Vacuum Standardization, an Integrated Approach Working closely with our partners across the project one of our primary goals was to promote the use of common vacuum equipment and standards. As a result a Vacuum Standardization meeting was held in February 2014 where equipment suitable for Standardization was agreed and reflected in the ESS Vacuum Handbook. An important element of this Standardization is the Procurement Policy applied for the procurement of all “major” vacuum equipment. This policy ask the partners to participate on a single Framework Agreement, The ESS Vacuum documents (handbooks, rules or interfaces documents) are the majors documents that covers the requirements for the accelerator, target and instruments and is applicable to all ESS IKC Partners . For the Monolith Vessel the document is the ESS-0057844 ESS Monolith Vessel Vacuum Rules.

Vacuum Requirements: Target 3D model for vacuum simulation Proton beam window Moderator and reflector plug Target wheel Neutron beam extraction Target drive housing Neutron beam window

Applicable regulations, codes and standards ✓ OK! ✓ OK! ✓ OK! Not usual requirement for vacuum system. Extra cost! ✓ OK! Not usual requirement for vacuum system. Extra cost!

Safety related requirement ✓ OK! Not usual requirement for vacuum system. Extra cost!

Performance requirements ✓ OK! Not usual requirement for vacuum system. Extra cost!

Performance requirements ✓ OK!

Performance requirements ✓ OK!

Performance requirements Extremely dependent of each component condition, venting process and leaks. ✓ OK!

Performance requirements Extremely dependent of each component condition and leaks. Upgrades are limited by mechanical constrains (pipe and flange conductance). Lessons learned from SNS. ✓ OK!

Requirements related to instrumentation, monitoring and controlance requirements ✓ OK!

Requirements related to instrumentation, monitoring and controlance requirements ✓ OK! ✓ OK!

Requirements related to instrumentation, monitoring and controlance requirements ✓ OK!

Requirements related to instrumentation, monitoring and controlance requirements ✓ OK! ESS Vacuum team has a calibration system on the VacLab. ✓ OK! It will require a specific system to sample the gas.

Constraints related to building interfaces and location within the target station ✓ OK! ✓ OK! Some discussion necessary, space required bigger than the original plan.

Constraints related to building interfaces and location within the target station ✓ OK!

Requirements on infra-structural ✓ OK! ✓ OK!

Requirement on vacuum pumps ✓ OK! Worst case scenario at maximum power.

Requirements on valves ✓ OK! ✓ OK! EPDM gaskets rated for 1 MGy.

Requirements on pressure measuring equipment ✓ OK! Vacuum instrumentation rated for UHV/baking full metal.

Requirements related to redundancy, separation and functional diversification ✓ OK! ✓ OK!

Material constraints ✓ OK!

Pressure/leak testing ✓ OK!

Installation logistics Extremely dependent on all/each component scheduling and limited by mechanical constrains (access to cranes and clean areas) ✓ OK!

System and components performance testing ✓ OK! Vacuum equipment are standardized and already approved. ✓ OK! All Vacuum components need to pass Acceptance test as on the ESS Monolith Vacuum Rules.

Missing interfaces ICD-R Monolith Rough Vacuum System and Proton beam Window. Define PBW total inflatable seal leak rate: 5 x 10-4 mbar.l/s The adding of this requirement has no impact on the Monolith Vacuum System solution! Requirement on water Create the interface for cooling water on the Turbo pumps for the MRV. Discussing started with some impact on the system available and pipe routing through the wall penetrations to the monolith room.

Target Vacuum requirements (major ideas as originally discussed) Moderator and Reflector Plug The vacuum levels for insulating vacuum of the moderator and reflector plug will be in the 10-2 to 10-3 Pa range, although lower levels will be required in the preparation of the hydrogen services lines to prevent the build up of condensable gases. Monolith The monolith will be required to operate in either a helium or vacuum environment. To operate in a high purity helium (ambient pressure) using a Proton Beam Window (PBW) environment pump and purge to 1 Pa range will be needed and leak rate (air or water from cooling system on the shield blocks) compatible com HV, In the vacuum mode a pressure in the 10-3 mbar range will be required for interfacing with the HEBT of the accelerator without PBW to limit the flow of gas from the monolith into the accelerator.

Thank you! Tack!