DORENA SEED COOLER Presentation of Updates/Discussion of Draft Findings US FOREST SERVICE 6/21/2012 Angela M Snyder – Project Lead Howard Cotner - R6DT Architect Steve Sichau – R6DT Electrical Engineer Jack Yousey, Gene Johnson – Solarc Inc. John Langley – R6DT Group Leader
AGENDA Opening remarks Our Role General Overview - Site Plan Scheme Information gathering Refining the scope of project Provide viable alternatives to consider for development project and funding strategies General Overview - Site Plan Scheme Overview of the ‘Base Alternative’ Overview of the ‘Build-Out Alternative’ *’Additional Items’ (not in current scope but discussed)
SITE PLAN SCHEME KEY ITEMS: Proposed New Refrigeration Building New Dorena Admin Office New POV and GOV Parking Engine Bay Storage Warehouse Space not Shown
BASE ALTERNATIVE KEY ITEMS: Remove and replace seed freezer number 1 with a new seed freezer. Heating system
BUILD OUT ALTERNATIVE KEY ITEMS: New refrigeration building with root cutting area New stratification cooler in location of seed freezer number 1 Heating system in existing building
DELIVERABLES Feasibility Report Base Alternative – Mid-July (Costs) Build-out Alternative – Late August Does not include RD and RC consolidation Does not include the “Additional”
Questions?