Cryogenic upgrade of B165 CRG Status Meeting 16th may 2019

Slides:



Advertisements
Similar presentations
Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE CM24 at RAL June 1, 2009.
Advertisements

Fcal upgrade for sLHC: Cryogenics modifications – TE-CRG/ C.Fabre 1 ATLAS FCal Upgrade for sLHC: Modifications to the Calorimeter Cryogenic.
Internal review of superconductors and magnet laboratories 2nd part: Infrastructure/Laboratories Cryogenics Klaus Barth (CERN), Vladislav Benda (CERN)
Workshop Chamonix XIV Shortcuts during installation and commissioning: risk and benefit H. Gruehagen, G. Riddone on behalf of the AT/ACR group 18 January.
April 19, 2006A.Klebaner Cryogenics for ILC TA Current Status Plans and issues.
January 4, 2007 Project Overview RHIC II Project Internal Cost Review Roberto Than Cryogenics Systems January 4, 2007.
Process Definition of the Operation Modes for Super-FRS Magnet Testing CSCY - CrYogenic department in Common System, GSI, Darmstadt Y. Xiang, F. Wamers.
SM18 cryogenics infrastructure upgrade L. Serio TE-CRG.
Central He distribution service upgrade status and dedicated He distribution for AD K. Barth on behalf of TE/CRG ADUC and ELENA Meeting Wednesday, September.
AT-ACR B. VULLIERMECSOC Meeting 29 September Cryogenics for LHC Test Benches Safety Aspects Overview of the Test Station Overview of the Operation.
MAGNET#1MAGNET#2MAGNET#3 SATELLITE VB#1 SATELLITE VB#2 SATELLITE VB#3 PRECOOLER#1PRECOOLER#2 DISTRIBUTION VALVE BOX DVB CP#1CP#3CP#2 BUFFER DEWAR LHe 5m.
TAC2 Alpi consolidation in Cryogenics and Cryomodules.
HIE ISOLDE commissioning of the cryogenic control system installation at CERN. LNL-INFN 22/07/2015 Dr. Marco Pezzetti (CERN )
A. Perin, TE/CRG, Page 2 CERN-GSI FAIR Project integration/coordination meeting 5 14 th October 2015 A. Perin, H. Derking, L. Stewart, M. Chesi,
L. Tavian, TE/CRG, LSC Page 2 February 21 th, 2014 LS1 Committee (LSC) L. Tavian TE-CRG.
Internal review of superconductors and magnet laboratories 2nd part: SM 18 & b.163: current status, weak points, possible improvement Cryogenics Vladislav.
ESS | Helium Distribution | | Torsten Koettig Linac – Helium distribution 1.
S A Griffiths CM42 June 2015 Electrical & Control.
H. Hayano(KEK), B. Petersen(DESY), T. Peterson(FNAL),
Vishy Ravindranath LCLS-II 2 K Cold Box FDR March 9, 2017
Neutrino Platform Proximity Cryogenics 68th EHN1 Cryogenics Integration TE-CRG
ILC Cryogenics: Study of Emergency Action and Recovery - in progress -
How Does HNOSS Operate? Rocío Santiago Kern 20th May 2016.
Cryoplant Installation Cost and Schedule Installation PDR
Teleconf ACS – FREIA 28th March 2017
Study and Development of Large Cryogenic Systems in China
Dana Arenius LCLS-II 4.5K Cold Box Director’s Review November 16, 2016
2K Cold Box FDR Introduction
Magnet cryogenic system update.
Existing Prototype Test Facility (PTF) and planned Series Test Facility Schroeder, Claus Cryo-Review Darmstadt
Status, Schedule and EVM for the test facility project
He Plant, LN2 Systems and Commissioing
Spoke section of the ESS linac: - Status of prototypes and CDS-SL
SM18 RF M7 Bunker Project Status 14th July 2017
Crab cavities Cryogenics progress for the SPS
FRIB Cryogenic Support
IT-4189 Supply and installation of a cryogenic distribution system
Cryoplant Installation Scope
N. Hasan1, P. Knudsen2 and V. Ganni2
Dana M. Arenius Jefferson Laboratory Cryogenics Dept Head
SPS cryogenic proximity equipment and SM18 validation
David Montanari / Johan Bremer Jun 11, 2015 Rev. 1
Teleconference ACS – FREIA 17th October 2017
Hongyu Bai LCLS-II 2 K Cold Box FDR March 9, 2017
Preparation of the activities for the LHC Long Shutdown 2
Keeping LHC cold during LS periods Preliminary proposal
Teleconference ACS – FREIA 31st October 2017
Activities of the ME section during LS2 ( )
YETS 2017 TE-CRG-OP overview of tasks to perform during the first month _GF YETS2017_CRG-OP.
Status of the cryogenic system for B180
The HIE—ISOLDE Cryogenic System, its Infrastructure and Considerations for Phase 3 O. Pirotte (TE/CRG)
Cryo stop of P8 on 1st of November
DAYS OF THE WEEK.
Payroll Processing pay period end for HR Professionals
Teleconference ACS – FREIA 20th February 2018
Pressure Piping Analysis
ESR 2 Presented to Joint Hall A/C Summer Meeting
Overarching Commissioning Plan
Got Gas? A Planned Oxygen Shutdown
CryoPlant Commissioning
Monday, FEBRUARY 12, Day 115 Welcome back! I hope you had a great weekend! For today, you will return to your old groups. Please quietly distribute.
Monday, FEBRUARY 5, Day 110 Welcome back! I hope you had a great weekend! Please enter quietly, distribute job cards and then fill in your agenda.
CTF Users’ Perspective
Contact
Monday, April 30th PD Day! No school for students.
Teleconference ACS – FREIA 19th June 2017
ESS Spoke cryomodule testing: cryogenic experience
ESR2 Process Cycle Design
ESR2 Process Cycle Design
Cryogenic upgrade of B163, B165 & B253 Status Meeting 19th December 2018
Presentation transcript:

Cryogenic upgrade of B165 CRG Status Meeting 16th may 2019

Status of Mechanical Work Cryogenic Distribution System (CDS): Installation and connection of main components complete; Final delivery this Friday (SV’s, Flexible lines and N2 phase separator) Remaining mechanical work: Connection of LN2 line to Cryolab (During N2 Shutdown, 22nd May); Installation of connections to B165-CB and B165-FS (20th May); TL1 supports (ongoing, no impact on process).

Status of Mechanical Work 20,000 l Dewar: Repair and testing completed by 1st May; Transport and re-installation behind B165 took place last week; Dewar Adaptor: Installation took place last week; Final warm connections underway.

Status of Mechanical Work GMP CDS: Installed. GMP GHe Buffers: GMP Compressor (GMP-CP): Installation on Friday. GMP Purge: Modifications requested by ML outstanding, planned for next week. GMP Cold box: Installation of B165-FS return line and 3 way valve finished this week; Modifications to purge collector postponed. Warm Piping: (planned completion next week) Connection of GMP-CP and GMP Purge; GHe lines to LHe Dewar and trailer; Finalization of warm piping to B165-CB.

LN2 System - Next steps LN2 Level valve and phase separator Shut down planned for Wednesday and Thursday next week (TBC by ML). Effect on client: Cryolab will be affected for two days, during construction of the TL connection and the pressure test; Other clients will be affected for Half a day, during connection of the LN2 Dewar. Valve commissioning will be undertaken before pressure test; Pressure test will be undertaken on Wednesday evening (TBC with HSE); Operation from Thursday evening; Level valve and phase separator: Installation after operation of LN2 system is underway. Before the commissioning of LHe system. LHe Dewar LN2 Dewar B159 B243 To Trailer Dewar CDS LN2 CDS LHe CryoLab

LHe System - Next steps CDS: Final warm connections completed by Wednesday next week; Flexible lines to B165-CB and B165-FS will be tested for fit next Monday. They will be installed after the pressure test. LHe Dewar To B159 To LN2 Dewar Cold Box Filling Station To Trailer Dewar CDS LN2 B165 To B163 CDS LHe To B243

LHe System - Next steps GMP Compressor: Final warm connections completed on Wednesday next week; GMP Purge: Final warm connections to the LHe system will be completed by Wednesday next week; Some piping additions may be required after the pressure test, however this shall not affect commissioning. GMP Cold Box: Installation of the new CV and 3 way valve from the B165-FS will be completed before Wednesday next week. Pressure Test: Given the status of the mechanical works we aim to undertake a pressure test of the LHe system on Thursday or Friday next week. Re-connection to Gazometer: After the pressure test, the LHe system can be re connected to the gasometer. This will effect B163 and B243 for half a day and is planned for 27th May.

B165: Project Status - Planning = Electrical connection required To meet SD planning commissioning must be achieved in 2 weeks Operation to advise: 1/ Do they need to use the LHe atmospheric heater? 2/ Do they need to retain a connection to the compressor LP? Potential delay of 4 days (1 week), supply with 10,000l transfer Original Shut Down period