MQXF-11T Integrated Schedule

Slides:



Advertisements
Similar presentations
Series 2: Project Management Understanding and Using 6 Basic Tools 9/2013 From the CIHS Video Series Ten Minutes at a Time.
Advertisements

Basic Overview of Project Management and Life Cycle ACES Presentation T. Gregory Guzik January 21, 2003.
Technology Applications Texas Essential Knowledge and Skills Desktop Publishing Project-Based Learning &
NCSX Vacuum Vessel Overview Paul Goranson WBS 12 Manager Vacuum Vessel Manufacturing Study Kickoff meeting April 29, 2003.
Non-welded Window Option Edgar L. Black IIT August 15,2003.
1S. Virostek - LBNL Spectrometer Solenoid Fabrication Update S. Virostek and M. Green are visiting vendor today for progress update Vendor expects to complete.
Series 2: Project Management Understanding and Using 6 Basic Tools 9/2013 From the CIHS Video Series “Ten Minutes at a Time”
Managing Projects
11 T Dipole informal coil and assembly readiness review Long coil and fabrication tooling development status and plans September 22 nd, 2013 – F. Savary.
F. Toral CLIC Workshop CIEMAT contribution to CLIC Experimental Verification F. Toral on behalf of Accelerator Technology Group, CIEMAT.
Lecture 3 Scheduling CSCI – 3350 Software Engineering II Fall 2014 Bill Pine.
Rev. 0 CONFIDENTIAL Mod.19 02/00 Rev.2 Mobile Terminals S.p.A. Trieste Author: M.Fragiacomo, D.Protti, M.Torelli 31 Project Idea Feasibility.
Thoughts about the MQXF development plan P. Fessia Thanks to discussions within the MDT section (P. Ferracin, J. C. Perez, E. Todesco, P. Ferracin), L.
Presenter Date Page Project manager The PROGRAM The Company Name 03/21/01 STOPLIGHT METRICS Stoplight Charts provide a means of communicating the status.
11 T Dipole Informal Coil and Assembly Readiness Review CERN September 2013 Review committee: Herman Ten Kate CERN (Chair) Fred Nobrega FNAL Davide.
The Way Forward Carol S. Carson AEG Meeting March 19-23, 2007.
Timeline and Milestones. The first step to any plan is thinking about a timeline. You want to know what needs to get done and when, to ensure that you.
F. Savary Question 1 A. Magnet design criteria for the prototype and production magnet to be tested before the installation into the tunnel.
Project Setup and Execution For PMPlan Enterprise Presented by AlNik Solutions Copyright ©
LMQXFA Cold Mass Assembly Antonios Vouris Fermilab February 3, 2016.
Instrumentation of the Controls Configuration Directory Service J. Luis González Arias BE3528 Software Developer for the Accelerator Controls Configuration.
11 T Dipole Project Cold mass integration status & plan F. Savary / TE-MSC-LMF.
11 T Dipole Project CERN Status M. Karppinen 11 T Management meeting 1 July 2013.
1 Project Management Software management is distinct and often more difficult from other engineering managements mainly because: – Software product is.
MQXF Short model and prototype plans P. Ferracin, G. Ambrosio HL-LHC/LARP International Review of the MQXF Design December 10-12, 2014 CERN.
MQXF Workshop on Structure, Alignment, and Electrical QA – Feb 2-4, 2016 Requirements and feedback form LARP structure review Ruben Carcagno February 2,
Last week first slide: Planning “Best Guess” Short Plan “best guess” – collared coils 102/104 “dry test" next week – Mirror MBHSM101 : collared coils 105/101.
MICE Coupling Coil Update Allan DeMello Lawrence Berkeley National Laboratory Illinois Institute of Technology June 17, 2013 June 17, 2013.
Shrikant_Pattalwar ICEC 26, March 7-11, 2016, Delhi 1 Horizontal Tests in a Vertical Cryostat Shrikant Pattalwar STFC Daresbury Laboratory UK.
LARP CM15, SLAC, 11/3/2010GianLuca SabbiSummary of MS Parallel Sessions Summary of Magnet Systems Parallel Sessions GianLuca Sabbi LARP Collaboration Meeting.
MICE Coupling Coil Vacuum Vessel Fabrication Update Allan DeMello Lawrence Berkeley National Laboratory Coupling Coil Working Group January 28, 2014 January.
Logo area Cold Mass Design, Assembly Plans & QC by US HL-LHC-AUP Antonios Vouris MQXF International Review – CERN, June 7 th – 10 th, 2016.
Tests on production cryomodules Bob Kephart Sept 30, 2006.
September 5, Burkhard Schmidt Integration and Installation Outline: Integration and Infrastructure issues -Suspended platforms -Cable chains -Beam.
Closing Session Report
WEEK 4 Introduction to Project Management 1. Communication Plan Objectives Objective is to determine: ◦ Who needs to know what? ◦ How will they be told?
What a load of Rubbish - Overview Of Project
Introduction to Project Management
11 T Dipole Integration & Plans M. Karppinen
CSP 25th November 2010 Technical agreement number 3: overview
FCC Cryo-magnet Logistics
Feasibility and implication of installation of the string test in SM18 with a slope M. Bajko WP16.
MQXF Goals & Plans G. Ambrosio MQXF Conductor Review
MQXF Planning Paolo Fessia, Frederic Savary, Ezio Todesco, Lucio Rossi - CERN Mike Anerella, Peter Wanderer - BNL Giorgio Ambrosio, Mark Kaducak - FNAL.
Project Management and Information Security
Spectrometer Solenoid Fabrication Status and Schedule
10/month is the present production rate 2 FTE + sporadic contributions
University of Delaware
PReSS – Iterative Assessment Review
Paolo Ferracin, Giorgio Ambrosio
Large aperture IR Quadrupole (MQXF) development plan
MQXF updates P. Ferracin October 9th, 2014.
Project Scheduling: networks, duration estimation, and critical path
[Project Name] STEERING COMMITTEE UPDATE [Date]
Progress Report TF Sequence Listing in XML
Key Dates-Odd Days April 26th-Lottery April 28th-Draft & Work Day
Time Management.
STOPLIGHT METRICS.
LDZ System Charges – Structure Methodology 26 July 2010
4. 2. Revision of the Regulation
Critical Path Method Farrokh Alemi, Ph.D.
Setting up a project file
Comments on SIEC by the Expert Group on International Economic and Social Classifications UNSD.
SPS Planning meeting for LS2 #19 Vacuum sectors & Magnet campaign situation Antonio Grande EN-ACE 06-Mar-2019.
Critical Path Simulation
SPS Planning meeting for LS2 #18 Vacuum sectors situation
SPS Planning meeting for LS2 #16 Vacuum sectors situation
Luxembourg Workshop on Space and Satellite Communication Law,
SNS PPU Cryomodule Space Frame
SPS Planning meeting for LS2 #25 Vacuum sectors status
Presentation transcript:

MQXF-11T Integrated Schedule A. Grande MQXF CERN Technical Meeting 8th May 2019 CERN

Index Structure of the planning Planning overview Series production of the 11T Models, both MQXF and 11T MQXFBT Prototype Summary table Next steps Antonio GRANDE

Structure of the planning The objective is to merge the previous plannings to have a clear overview of the tasks related with the production and the testing of the different magnets: Series production of the 11T Models, both MQXF and 11T MQXFBT prototype Resources will be taken into account while planning to avoid over-allocation of them  This can impact significantly the planning ! DRAFT Antonio GRANDE

Planning overview – Series production of 11T The 11T production planning is being simplified to a “resource level” For the first study of the MQXFBT prototype’s cold mass, the simplified planning of F. Savary has been taken into account and Cold mass assembly activities have been split into 7 steps DRAFT Antonio GRANDE

Planning overview – Models DRAFT Typical production sequence Typical assembly sequence Typical testing sequence In yellow: testing duration depends on tests performed (to be verified) In green: sequence verified in meetings Antonio GRANDE

Planning overview – MQXFBT Prototype The welding press would be the bottleneck A slot of ~4w is necessary An extra week would be needed to align the cradle for 11T magnets  Delay? ! a DRAFT F. Savary’s planning has been slightly modified to apply the usual duration of a typical Cold Mass Assembly (need verification) In orange: steps in welding press Antonio GRANDE

MQXF Prototype Cold mass Summary table Summary table Magnet Proccess Start date Finish date Comments SP107 Fabrication 29-11-18 31-05-19 Depends on 180s activities starting Cold Testing (SM18) 03-06-19 01-07-19   SP108 24-01-20 01-04-20  Depends on material availability 04-05-20 DP201 12-06-19 19-09-19 17-10-19 MQXFS6 30-04-19 26-06-19 02-07-19 29-07-19 MQXF Prototype Cold mass 20-05-19 25-11-19 (7-10-19) Option b SP109 MQXFS4 Antonio GRANDE

Next steps Simplification of the 11T series production planning. The minimum level should be the “resource level” Meetings to verify the duration and starting of all the activities Introduce all the resources in every task Antonio GRANDE

Thank you