SPS 2, 3, 4 and 6 during W23-26 2019 D.MCFARLANE EN-ACE-OSS 12/06/2019.

Slides:



Advertisements
Similar presentations
Study report on the TDC2/TCC2 Cabling and Low Voltage activities Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting
Advertisements

Backwards Compatibility L4 – L2 W. Weterings LBCC - 14.
HiRadMat : report from WG2&3 – WANF dismantling January 15, 2010S. Evrard 1 Worksite: activities achieved or in progress WANF cleaning: status Proposal.
LHC Hardware Commissioning Review May 2005 T.Pettersson - EDMS: TS Department Utilities Safety Access SU - a plea for co-ordination of co-activities.
LS1 Injectors K. Foraz on behalf of N. Gilbert, S. Mataguez, D. Hay & D. McFarlane LSC 24 th May /05/2013LSC – EN-MEF-OSS1.
Claudio Bortolin. 1 st June: PT100 electrical connection failure (Temp Chiller water In&Out) 1) it required an access to the cavern to be fixed 2) access.
 A brief history of time  In the years BC.  My years at CERN  Current position  What is a Technical Coordinator?  The different type of intervention.
Injectors & LHC report K. Foraz on behalf of OSS members 14/06/2013LSC - K. Foraz1.
NA YETS: schedule week by week S. Evrard.
Paolo Guglielmini - TS / CV LHCb Install Meeting - 12/10/2005 LHCb - Install Meeting 12/10/05 TS/CV/DC Installations STATUS Ongoing works 1.chilled / mixed.
LHC-YETS Coordination meeting #9 24 th November, 2015.
Long shutdown 1 LHC Machine Status Report K. Foraz June 12 th, 2013.
Injectors & LHC report K. Foraz on behalf of OSS members 01/11/13LSC - EN-MEF-OSS1.
Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 20/09/2013LSC - EN-MEF-OSS1.
LS1 Day: The Injectors S. Baird EN/MEF Thanks to R Brown, N Gilbert, D McFarlane & V Chohan, IEFC workshop…. LS1 Day: The Injectors 1.
Update on the PSB Cooling and Ventilation Systems
SPS-FIRE The SPS Fire Safety Project Planning Status
YETS & LS2 Works EN-EL / Power distribution
K. Foraz on behalf of OSS members
Proposition de routing des cables :
BE-ICS activities for LIU Project
SPS LS1 Planning meeting (N019) 04/09/13
YETS & LS2 Works EN-El on LHC / Power distribution
BE-ICS Activities during the LS2 Period (15 min)
TE-MSC activities in SPS during LS2
EYETS David Hay EN-OSS.
BA6 – crab cavity activities in EYETS
Activités SPS pour BE/ICS Systèmes d’Alarmes YETS
LHC-EYETS 2016/17 Coordination meeting #18
K. Foraz on behalf of OSS members
SPS - EYETS 2016/17 Vacuum systems planning
EN-EL-FC Activity Jeremy Blanc, EN-EL-FC.
BE-ICS activities for LIU Project
LHC Beam Vacuum activities during YETS LS2
EHN1: CE Integration process updating
De-cabling strategy during YETS
Crab Cavities Activities
TE/EPC activities for LINAC 2, PSB, PS & TT2 during EYETS
EN-HE SPS works during EYETS
SPS EN-CV Planning LS (initial draft)
SPS Planning for the EYETS Meeting 8 (07/12/2016)
SPS Planning for the EYETS Meeting 9 (14/12/2016)
SPS LS1 Planning meeting (No.34) 16/04/14
EYETS 2016/2017 Activities SPS Access system Maintenance and Evolutions Access system EYETS 2016/2017 EDMS:
NA CONSOLIDATION & SAFETY SYSTEMS
SPS activities during LS2 TE-EPC (Power Converter Group)
Short LHC-TS week 38 Confirmed by LMC on 16th August
EN-HE L2 – PS – PSB – TT2 works during YETS
YETS & LS2 Works EN-EL / Power distribution
TE-MSC activities in SPS during YETS
K. Foraz on behalf of OSS members
BE-ICS work for SPS Safety Systems
PS Booster Report from: David HAY, Cyrille BEDEL 12-Jan-2018
Business opportunities related to CERN electrical network
Undulator System Installation
Experimental Areas – LS2 planning
SPS 1 and 5 during W J.MEIGNAN EN-ACE-OSS 09/01/2019.
SPS Planning meeting for LS2 #19 Vacuum sectors & Magnet campaign situation Antonio Grande EN-ACE 06-Mar-2019.
SPS 1 and 5 during W J.MEIGNAN EN-ACE-OSS 23/01/2019.
SPS 1 and 5 during W J.MEIGNAN EN-ACE-OSS 20/02/2019.
SPS Planning meeting for LS2 #18 Vacuum sectors situation
SPS Planning meeting for LS2 #16 Vacuum sectors situation
SPS 1 and 5 during W J.MEIGNAN EN-ACE-OSS 06/03/2019.
EN-HE SPS during LS2 J-L GRENARD on behalf of EN-HE 23/1/2019.
North Area Safety Review 2019
SPS 2, 3, 4 and 6 during W D.MCFARLANE EN-ACE-OSS 26/06/2019.
SPS Planning meeting for LS2 #25 Vacuum sectors status
WP1: Status and Plans Francisco Sanchez Galan (EN-EA-PE)
SPS Planning meeting for LS2 #26 Vacuum sectors status
Linac4 Connection Broken Line 07/08/19
Presentation transcript:

SPS 2, 3, 4 and 6 during W23-26 2019 D.MCFARLANE EN-ACE-OSS 12/06/2019

SPS 2: Works ongoing W23/24 BA2: Surface Les nids de poules seront traités mardi prochain. Le BA2 restera accessible pendant les travaux. Il serait préférable afin de ne pas nuire à la qualité de la prestation de limité les passages. Transformer consolidation for MBE.2103M (x3 replace by 1) RMT112/A2 Tirage de cables reseau Ethernet et terminaisons locales de ces cables Underground (All Zones) Install Safety Lights & Cable Trays Shaft/TA supprimer pompe eau usee tunnel Installation PPS fibre optique en fond de puit BA2 TT20: Dry riser installation Arc 2+ Vacuum controls consolidation aC coating 17/04/2019 J.MEIGNAN

SPS 2: Works Scheduled W25/26 BA2: Surface MACAO power converters replacement Dismantling of old converters Ncod Transformer consolidation for MBE.2103M (x3 replace by 1) RMT112/A2 Underground: Install Safety Lights & Cable Trays Maintenance préventive des éclairages minimums Shaft/TA Dry riser testing Supprimer pompe eau usee tunnel TT20 Modification of magnet supports?? Arc 2+ aC coating 17/04/2019 J.MEIGNAN

SPS 3: Works ongoing W23/24 BA3: surface De-cabling campaign HV works Transformer maintenance Upgrade of the “Faraday cage” RF powering consolidation Shaft/TA: De-cabling campaign: (morning shift) Coax lines (Afternoon shift) Arc 3-: aC coating LSS3: De-cabling campaign (morning shift) CV piping works (LSS3+) (Afternoon shift) Coaxial lines LSS3+ (Afternoon shift) Helium Recovering line removal The passage of the TIDGV (Tuesday the 11th June at 18:30) 17/04/2019 J.MEIGNAN

SPS 3: Works scheduled W25/26 BA3: surface De-cabling campaign HV works Transformer maintenance Upgrade of the “Faraday cage” RF powering consolidation Shaft/TA: De-cabling campaign: (morning shift) Coax lines (Afternoon shift) Arc 3-: aC coating LSS3: De-cabling campaign (morning shift) CV piping works (LSS3+) (Afternoon shift) Coaxial lines LSS3+ (Afternoon shift) 17/04/2019 J.MEIGNAN

SPS 4: Works ongoing W23/24 All areas: Cabling campaign (BA/shaft/TA/LSS) BA4: EIS upgrade on 2 converters (400V) Maintenance chiller Trane Tirage de cables reseau Ethernet (2019) LSS4: Maintenance sur boite froide Hélium TS45 BB4/ECA4: Transformer consolidation for RBI.410010 (x1 replace by 1) RMT310/B4. MACAO power converters replacement TT40/TI8 Mise a la terre de 20 racks CIWRA situes sous la ligne faisceau du TI8 et TT40 TI8 Smoothing (Vertical) 17/04/2019 J.MEIGNAN

SPS 4: Works scheduled W25/26 All areas: Cabling campaign Maintenance préventive des éclairages minimums BA4: EIS upgrade on 2 converters (400V) Tirage de cables reseau Ethernet (2019) LSS4: Maintenance sur boite froide Hélium TS45 BB4/ECA4: Transformer consolidation for RBI.410010 (x1 replace by 1) RMT310/B4. (TAG41) Access control commissioning of the zone 1st & 2nd stage (access to TI8 possible via TT40.) 1st Stage: 20th & 21st June 2nd Stage 27th & 28th June TT40/TI8 Mise a la terre de 20 racks CIWRA situes sous la ligne faisceau du TI8 et TT40 TI8 Smoothing (Vertical/horizontal) 17/04/2019 J.MEIGNAN

SPS 6: Works ongoing W23/24 BA6: Cast Resin Transformer maintenance Transformer refurbishment RMT117/A6 Surface works FS sprinklers All underground areas: FS WP2 fire detection installation Shaft/TA: FS WP4 Dismantle old Sprinkler system FS WP4 Sprinkler installation LSS6: Sprinkler installation FS WP1 Fire Doors (TBC) Arc 6+: Dry riser Installation 17/04/2019 J.MEIGNAN

SPS 6: Works scheduled W25/26 BA6: Cast Resin Transformer maintenance Transformer refurbishment RMT117/A6 Surface works FS sprinklers Short cable campaign for Access system All underground areas: Maintenance préventive des éclairages minimums FS WP2 fire detection installation Shaft/TA: FS WP4 Dismantle old Sprinkler system FS WP4 Sprinkler installation Lift/Monte-charge maintenance (17/06/19) LSS6: FS WP1 Fire Doors (TBC) Arc 6+: Dry riser Installation 17/04/2019 J.MEIGNAN

Any questions?