Procedure for MEBT installation in the accelerator tunnel at ESS Aitor Zugazaga, Alexander Conde, Javier Martin Zamudio, 4 June 2019
PACKAGING LIST Tracking of goods Unload instructions List of Items delivered : ESS-MEBT-DL19003-PACKINGLIST-XX; valuable for: Tracking of goods Unload instructions Organizing of goods at facilities
DELIVERY Loading organizing Items will be sent by truck by 4PL Central Station Nordic AB; valuable for: Loading organizing
DELIVERY Minimizing risks during loading and transport. Packing structures designed specifically for each RAFT; valuable for: Minimizing risks during loading and transport.
ESS TEAM SUPPORT For the installation of the MEBT support from ESS teams is required: Rigging team for placing the RAFTS on the Main Bench Alignment team and hardware for RAFT installation and checking Vacuum team and hardware for RAFT installation and checking Electricity (220V) will be needed during this phase.
ALIGNMENT All RAFTs must be aligned when placing on the Main BENCH All QUAD position must be checked RAFT 8: BSM
RAFT 8 BSM To be done by INR
VACUUM Assembly inside RAFTS RAFT 1: Wire Scanner RAFT2 (x3): Ion Pump + Gauge +Coupler RAFT 4: Wire Scanner + Ion Pump + Valve + Burst disk + Gauge + NPM? (x2) + Feedthroughs RAFT 6: Wire Scanner RAFT 8: Faraday Cup + 2x EMU Grid + BSM + NPM? (x2) Connection between RAFTS 9x CF40: RFQ-RAFT1-RAFT2-RAFT3-RAFT4-RAFT2-RAFT6-RAFT8-RAFT2-RAFT9 1x CF63: RAFT9-DTL
Damaged bellow seen during disassembly RAFT 1 Wire Scanner Aluminium wire Not to be done Damaged bellow seen during disassembly
RAFT 2 Ion Pump + Gauge CF63 CF40
Component under manufacturing RAFT 2 Coupler CF63 Not to be done Component under manufacturing
RAFT 4 Wire Scanner + Ion Pump + Valve + Burst disk+ Gauge CF40 Aluminium wire CF40 CF63 CF40
Component under testing RAFT 4 Feedthroughs (4x) Not to be done Component under testing CF63
RAFT 4 2x NPM? Not to be done CF63 CF63 CF63 CF63
RAFT 6 Wire Scanner Aluminium wire Aluminium wire
RAFT 8 Faraday Cup + 2x EMU Grid CF100 CF100 CF100
RAFT 8 BSM To be done by INR CF40
RAFT 8 2x NPM? CF100 Not to be done CF100 CF100 CF100 CF100
To be done when the RFQ is installed CF40 RFQ-RAFT1 Not to be done To be done when the RFQ is installed
CF40 RAFTX-RAFTY
CF40 RAFTX-RAFTY
CF40 RAFTX-RAFTY
To be done when the DTL is installed CF63 RAFT9-DTL Not to be done To be done when the DTL is installed
COMPLETE ASSEMBLY THANK YOU 22-SAR MEBT Vacuum test