Sunday 12th 00:29 Stable beam fill #1864. Initial lumi 1.1e33

Slides:



Advertisements
Similar presentations
PROFIBUS controller problem (SEU) on cryo valve on DFBMH (600 A circuit RQ6.L7B1/2). Loss of cryo maintain ==> Beam dump. End of fill #1975 after ~2.5.
Advertisements

Wednesday 12 th September Pumping, removal of vacuum equipment from tunnel in the morning TOTEM & ALFA, RP movement tests: OK 11:50 pre-cycle started,
21/05/2012LHC 8:30 meeting Overview Week 20 Injectors, LHCb polarity, Beam-Beam Coordinators: Bernhard Holzer, Jan Uythoven.
Monday 29 October 08:48 V/dM scan CMS end of fill #3236. Check of “fast scan”. 10:06 V/dM scan finished, start of RF studies, reducing RF voltage. 11:10.
LHC 8:30 meetingEBH 1  Cryogenics recovery in point 8  Meanwhile a couple of accesses:  MKI investigation on noise in IP2  Insulation Vacuum.
RF observation from Saturday morning Observation of beam induced voltage/power following the two klystron trips: 03:18 3B1 just at end ramp, 1.26E14 p.
Friday 2 nd November 08:45 Stable beams Fill 3253 Initial luminosity ~7.3e33 cm-2s-1 09:45 Increase RF voltage from 10 MV to 12 MV 12:00 ADT to wideband.
Tuesday 24 th July - morning 10:15 Operator dump of fill 2873  Initial luminosity: 5.83e33 cm-2s-1  12 hours stable beams  151 pb-1 delivered  Initial.
07:00 Dump fil #2219, 123 pb -1 delivered. Trim TDI parking position to +/- 55 mm in the collimator BP trimmed the temperature kicker limit to 62 degrees.
LHC Status Sat Morning 30-June Bernhard Holzer, Jan Uythoven Status Friday Late: preparing restart some issues... LHCb dipole tripped / router problem.
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
Machine Coordinators: G. Arduini, J. Wenninger
Monday :00 Stable beams 9_6_6_6 13:40 Access.
Monday fill with 1092 bunches (6 h stable beams)
Wednesday 17th August Rocky, short fills, initial luminosities are good LHCb polarity change to negative seems ok 18/08/2011 LHC 8:30 meeting.
Monday 11/07: Recovery Plenty of accesses.
LHC Morning Meeting - G. Arduini
Tue :25 Beams dumped due to RF vacuum interlock
Saturday 12:00 Fill 1992 in stable beams.
Summary of Week 11: 14 – 21 March
LHC Status Su Morning 17-April R. Assmann, B. Holzer et al
Tuesday 08:30 Fill 2700 dumped by QPS on RCBXH2.L1
Thursday 17th May 01:11 Fill #2633 dump in squeeze arc circulator load channel Ad1B 03:16 Fill #2644 Stable beams, lumi 5.2e33 cm-2s-1 04:38 Dumped by.
Wednesday 31 October: Morning
Summary of Week 16 G. Arduini, J. Wenninger
Note: squeeze in Atlas, CMS, LHCb and Alice on going
Friday day 00:51 Fill #1862 Beams lost to inner triplet skew quad power converter fault. Delivered lumi 33 pb-1 Access required for repair RQSX3.L1 converter.
Sunday morning Recovering from 400 kV disturbance.
Friday 11/5 08:00 RF communication problem solved. Ready to inject but beam not available from the injectors. Injection line collimators opened from 4.5.
Friday :00 machine setup for luminosity run. Better b-to-b stability from injectors. 01:58 stable run with 228 bunches 11:00 luminosity leveling.
04-05/08/2010 End of physics at ~11:00 after 18.5 hours ~120 nb-1.
Saturday – Morning 7:36 beams dumped
Yesterday’s morning’s controls issues
Finally.... We had to wait a long time.... We had many problems....
Sunday/Monday & :30 Stable beams. Fill #1851.
Thursday morning 08:45 Stable beams fill 2855 for ATLAS/CMS VdMs.
Monday 24 October hours of 25ns MD
Monday 14:00 beam dump Access:
Rocky last 24 hours Losses Q6.R5 Orbit SIS TCDQ OK! Power converters
Thursday 26th July 13:21 Fill 2880 beam dumped
Wednesday 13th 9:30 Stable Beams… with 1 pilot and 2 nominals
Friday 07:00 Fill 1729 dumped. Movement device allowed flag switching to FALSE. From the logs, it seems the energy went to FFFF/7860 GeV. To be confirmed.
Fill 1743 Peak luminosity ~6.7 e32 Integratated lumi ~20 pb-1
Monday 6th 07:39 Dump fill #1854, RQ6.L2 tripped, followed by access
Saturday Wire scans at end of fill 1253 B1H : 4.2 B1V : 4.3 B2H : 5 B2V : 7.2 Beams dumped (after ~14h of collisions) Some issues during refill.
Monday morning 09:40 Dump fill 2838, integrated ~130 pb-1.
Cold compressor speed S45
Monday 11th June 08:10 Beam dumped in the ramp by OP. OFB did not start its function and kept the injection orbit. 08:50 Switch LHCb polarity to negative.
Monday Fill 1803 into stable beams at 9:30. Dump at 19:45.
Friday morning 08:00 Stable beams with 840b.
Sat 15/10 New record bunch population profiting of the scrubbing period on Friday. Nb~1.42x1011p/bunch  110 MJ at 3.5 TeV. Filling slowed down by ZS sparking.
LHC Status Fro Morning 9-Sep
Wednesday 6th April Injection of 50 ns up to 108 bunches (3 x 36).
Saturday 24 September 2011.
Monday 26th September 7:30 Beam dump, QSP on RQX.R1, lost cryo in ITR1, 91 pb-1. Cryo recovery, needed about 1.5 h. Setting of TI2 collimators to 5 sigma.
Friday h55 Stable beams. Fill #1841. Lumi ~1.2e33.
Tuesday 24/5 Fill # :00 Stable beam fill # bunches
Monday 27th August & night
Wednesday 26 October 2011.
Wednesday morning / afternoon
Wednesday morning Waiting for PS – problem on RF cavity.
Saturday 28th 08:17 Fill #1812: Stable beams, peak luminosity ~1.1x1033 cm-2s-1 19:00 Go to adjust for RF-checks; Record fill lumi of 31.7 pb-1 for CMS.
Saturday Luminosity production 1380 bunches
Saturday 26 November 2011.
Tuesday
Thursday 10:00 Fill 1986 in stable beams.
Wednesday 8th (I) 09:22 Fill #1855. Beams dumped by Alice dipole trip Stable beams for 10.5 hours; int. lumi 31 pb-1 After investigation EPC could not.
Wednesday Following the struggle with the vacuum in IR2 over the night, drop intensity to 1.2E11/bunch. Fill first B1 – pretty quiet – then B2 – quite.
Tuesday
Presentation transcript:

Sunday 12th 00:29 Stable beam fill #1864. Initial lumi 1.1e33 07:17 beam dumped by trip of RD2.L1 Integrated lumi 23 pb-1 10:30 Cryo maintain back 11:30 Injecting - some injection steering 13:56 Stable beam fill #1865. Initial lumi 1.1e33 03:22 Beams dumped, collimator interlock Integrated lumi 42 pb-1 05:00 Access for change of power converter 07:13 Injecting probe beam 13/06/2011 LHC 8:30 meeting

Trip of RD2.L1 Bus-bar quench, following cryo valve control problem Heaters fired, quenched RD2.L1 Vacuum valves in around RD2.L1 following vacuum spike, 2.1 s after dump request by PIC Michel Combe 13/06/2011 LHC 8:30 meeting

Fill #1865 – LHCb levelling problem We went for too high with the optimize all routine for LHCb which went up to 600 (ub.s)^-1! It looks like we were heads on in Vertical and completely OFF in Horizontal. The Optimize All (in H plane) put us too much in collisions. We tripped LHCb. Put manually LHCb to 250 (ub.s)^-1 on request of LHCb, with levelling OFF Smoothly restarted the leveling 1/2 hour later @ 300 (ub.s)^-1 Short term improvements to prevent this in the future Richard Jacobsson 13/06/2011 LHC 8:30 meeting

Including fill #1865: @ 915 pb-1 13/06/2011 LHC 8:30 meeting

Integrated efficiency indicator MKI profiting from the longer bunch lengths Like cryo, collimators,.... Temperatures Bunch length 13/06/2011 LHC 8:30 meeting

Plan Physics 1092 x 1092 bunches, trains 144 bunches Not for today rMPP approval procedure OK After RF main power coupler conditioning, which would otherwise be at the limit Outstanding End of fill: TCL adjustment Q’ decay following long fill 13/06/2011 LHC 8:30 meeting