Status of the BI Work Package in the LIU-PSB frame J. Tan Thanks to the contributions of S. Prodon, and the WU holders: J.C.Allica, M. Bozzolan, S. Burger, M. Gasior, P. Odier, F. Roncarolo, C. Zamantzas
BE-BI LIU-PSB review 09-05-2019 Outline Active work units (- BWS) EVM analysis from S. Prodon Summary BE-BI LIU-PSB review 09-05-2019
BE-BI LIU-PSB review 09-05-2019 Active work units: BC 64020 Diamond BLMs in 1L1, OP request to replace OASIS by new aqn. chain Feasible : all components are available. Similar system as in SPS: OP to check if it fulfills their requirements. A new functional specs now under engineering check. Different from LHC/SPS system. Under study by BI on how to integrate this smartly. Budget : 50kCHF will be given back from CO, investigating how to fit ADC cost with this amount. Injection line BLMs: L4 baseline BLM Locations: received from LIU Plan 10198: Completion of L4T line installation after sector test Plan 11400: Installation of Beam Loss monitors in LT/LTB/BI lines Action : DIC done ECR on going (looking forward to getting integration drawings) Extraction line BLMs: WU 126825, until 12-2019 On track, cables pulled, installation started Statement unchanged BE-BI LIU-PSB review 09-05-2019
BE-BI LIU-PSB review 09-05-2019 Active work units: BC 64021 Watchdog BR.TMD in 8L1, Part 2: WU 91542, until 12-2018. Hardware upgrade : Cal. Current amplifier to be produced this year WD FESA class : on going, debugging in LAB. DCCT electronics upgrade, Part 2: WU 91543, until 12-2019. Electronics for L4 intensities: Prototype now under test. Production in 2019 Budget: 30kCHF foreseen for 2019, OK Tune pick-ups: WU 161665, until 12-2019. Installed in YETS, commissioned and operational Budget: 5kCHF 2019 for electronics, OK Stripline PU upstream BI.SMV10: WU 191503, until 12-2019. Parts under production. Readiness for installation: Sept 2019 ECR 2003464: approval accepted Budget: OK Inductive PU upstream PI.SMH42: WU 191504, until 12-2019. Spare part passed vacuum acceptance test. Readiness for installation: April 2019 ECR 2084600: draft state BE-BI LIU-PSB review 09-05-2019
BE-BI LIU-PSB review 09-05-2019 Active work units: BC 64022 BTVs at extraction, BT.BTV10-30, WU 91547, until 12-2019 Ready Budget: 5kCHF 2019, OK New Tank for BI.BTV30, Part 2: WU 93002, until 12-2019 Budget: 22kCHF foreseen for 2019, OK H0/H-detectors, WU 91544, Completed TbT profile meas. for injection matching: WU 96106, until 12-2019 One tank installed. Commissioning after LS2 - priority now shifted to PS Acquisition board: PS version validated with beam Budget: Should be OK (TbC) BE-BI LIU-PSB review 09-05-2019
LIU-PSB EVM Curves Schedule variance -3.8 months: ~4 months delay: TbT : delay of aqn chain BWS : delay of three components 07/09/2019 S. Prodon
LIU-PSB EVM Metrics from Project Start to Date 2019 64020: BLM Cost to completion update PV = 1,155 k CtC = PV 07/09/2019 S. Prodon
LIU-PSB EVM Metrics from Project Start to Date 2019 64021: BPM & BCT Cost to completion update PV = 1,251 k CtC = PV 07/09/2019 S. Prodon
LIU-PSB EVM Metrics from Project Start to Date 2019 64022: Profile monitors Cost to completion update PV = 615 k CtC = PV 07/09/2019 S. Prodon
LIU-PSB Active Workunits 6 WUs active 07/09/2019 S. Prodon
LIU-PSB Active Deliverables 07/09/2019 S. Prodon
BE-BI LIU-PSB review 09-05-2019 Summary Watchdog (BR8.TMD) Cal. Current amplifier to be produced this year DCCT Prototype electronics under test. Final version to be produced this year TbT profile measurements Acquisition board: PS version validated with beam. Budget BC 64020 : balanced budget, 50 kCHF transferred from CO for acq chain ???? BC 64021 : balanced budget BC 64022 : balanced budget 6 remaining active WUs are on track BE-BI LIU-PSB review 09-05-2019