Status of the BI Work Package in the LIU-PSB frame

Slides:



Advertisements
Similar presentations
IEFC Workshop – 22/03/2011 JJ Gras on behalf of BE-BI 1.
Advertisements

BI Outlook for BI Day 2012 Based on latest (last Monday) feedback from EN/EL XXX As foreseen originally Partially ‘As foreseen originally‘ Postponed.
PSB extraction and transfer kickers 01/10/2014 LIU-PS ABT review1 L. Ducimetière, L. Sermeus.
Matching and Synchrotron Light Diagnostics F.Roncarolo, E.Bravin, S.Burger, A.Goldblatt, G.Trad.
Status of the BI Work Package in the LIU-PSB frame Jocelyn TAN, BE-BI Thanks to the contributions of the WU holders: J. Belleman, P. Odier, F. Roncarolo,
Linac4 FBCT’s 18/ L4 BI BCT review Lars Søby On the behalf of: M. Andersen, D. Belohrad, L. Jensen, Franco Lenardon and J. C. Allica Santamaria.
Linac-4 current situation and outlook U. Raich, F. Roncarolo, F. Zocca.
New injection region 1L1 Engineering Change Request PSB-L-EC-0001 EDMS Wim Weterings PLI Meeting Wednesday 14 th January 2015.
The Stripping Foil Test Stand in the Linac4 Transfer Line
Work Effort in the LHC Injector Complex for the Upgrade Scenarios B. Mikulec Thanks to all the valuable input from the LIU project leaders and LIU work-
LIU-ABT systems: SPS B.Balhan, J.Borburgh, H.Day 20 th November 2015.
Based on Lars’ progress report of LIU SPS BI Status of follow-up 13/10/2015Lars K. Jensen, V. Kain1.
BI.DIS10: Magnets & generators R. Rosol, L. Sermeus, T. Stadlbauer, TE-ABT LIU review, 20 November
Beam Instruments PSB + Transfer Lines B. Mikulec, J-F. Comblin.
LIU-PSB Configuration Management EDMS Documentation, Layout and ECRs Thomas Birtwistle EN-MEF-DC.
ABT LIU Project Review 2015 BI.KSW: Magnet November 20 th 2015 L. Feliciano TE/ABT.
Status of the BI Work Package in the LIU-PSB frame Jocelyn TAN, BE-BI Thanks to the contributions of the WU holders: J. Belleman, P. Odier, F. Roncarolo,
Overview Consolidation projects for PS LIU-PS Main observable review Conclusion Acknowledgements S. Gilardoni R. Steerenberg G. Metral H. Damerau BI colleagues.
LIU-PSB BIS presentation / Christophe Martin TE-MPE-EP 28/02/ Beam Interlock System for Transfer Lines & PS Booster Christophe Martin TE/MPE/EP.
LIU-SPS action list for BE/BI L. Jensen with input from BL, PI, QP, PM 27/08/2015Lars K. Jensen BE/BI/SW1.
LIU-SPS progress for BE/BI L. Jensen on behalf of BE/BI 27/08/2015Lars K. Jensen BE/BI/SW1.
L4 BCC – 1 Sep 2011 F. Roncarolo, U. Raich L.Soby, J.Tan, C.Zamantzas, F. Lenardon, C.Vuitton, G-J.Focker.
LS1 Mid-Point Status Report of the PSB Low Level RF, Transverse Feedback & High Level RF. Autumn 2013 A. Akroh, M.E. Angoletta, A. Blas, L. Arnaudon, A.
Agenda 1 BOSS Meeting - 27/5/ : :10 Introduction and aims of the workshop 10‘ 09: :25 Priorities from OP for PSB and transfer lines 15'
INJECTORS BLM SYSTEM: PROGRESS REPORT Christos Zamantzas on behalf of the BLM team. MSWG 28/08/2015.
Linac4 Project Meeting 1/2011 3/3/2011 M. Vretenar Update on schedule and structure 1.
Status of the BI Work Package in the LIU-PSB frame Jocelyn TAN, BE-BI Thanks to the contributions of the WU holders: J. Belleman, P. Odier, F. Roncarolo,
PS-LIU status S. Gilardoni – BE/ABP H. Damerau – BE/RF LIU-PT 27 Aug
PSB HW Commissioning Meeting 8 February 2016 A. Akroh, B. Mikulec.
PSB extraction and transfer kickers LIU TE-ABT review, 20 November L. Sermeus.
LIU Critical Key activities in Long Shutdown 1 (2013) LIU-PSB: assuming LINAC4 connection in LS2 –Beam dump consolidation If not done: operation will be.
ELENA installation progress F. Butin / ELENA collaboration.
Wim Weterings Remy Noulibos
26/11/2015 LIU-PSB meeting, Status of BE and BT kickers and septa 2 Extraction and Recombination Septa and Kickers status Jan Borburgh, M. Atanasov, W.
LIU and TE/VSC activities Status September 2016 LIU-SPS aC coating & flange impedance reduction Paul Cruikshank on behalf of TE-VSC LIU & TE-VSC, 19/9/2016.
Status of the BI Work Package in the LIU-PSB frame
Linac4-PSB 160 MeV connection readiness review
LIU – EVM status and next steps
BE-CO Activities for LIU-CPS and LIU-SPS
Brief Status SPS Prototype PSB Prototype Installed in LS1
EYETS David Hay EN-OSS.
ELENA installation and commissioning status
LHC-RF activities in LHC PT 4 TS2 YETS LS2
LIU Wire Scanner Milestones June 2017
LIU / HL-LHC Cost and Schedule Review
EC Activities Status for LIU September 2017
LIU – EVM status and next steps
Injectors BLM system: PS Ring installation at EYETS
LIU–PLI report LIU PSB meeting.
News from EVM.
EC Activities Status for the LIU
BE-BI Software for LINAC4
LIU–PLI report LIU SPS meeting.
BE/RF-IS Contribution to LIU C. Rossi and M. Paoluzzi
Status of the BI Work Package in the LIU-PSB frame
ELENA tune measurement
WPs concerned by L4 connection:
LIU and TE/ABT/PPE activities
Overview & baseline of LS2 and roadmap for CRG
Injectors BLM system: PS and PSB Ring installations at EYETS
LIU Wire Scanner Series Costs
PSB-PS instrumentation for LIU
Linac4-PSB 160 MeV connection readiness review ( TE/VSC )
CONSOLIDATION CPS-BL SYSTEM
LIU-SPS review for BI (no BWS)
ATS Consolidation Day 22nd May 2019 Beam Instrumentation
East Hall under construction
Monday 152 bunch operation summary
SPS Injection BIS - Draft requirements
LIU EL-FC ACTIVITIES Updated on 28/11/2017
Presentation transcript:

Status of the BI Work Package in the LIU-PSB frame J. Tan Thanks to the contributions of S. Prodon, and the WU holders: J.C.Allica, M. Bozzolan, S. Burger, M. Gasior, P. Odier, F. Roncarolo, C. Zamantzas

BE-BI LIU-PSB review 09-05-2019 Outline Active work units (- BWS) EVM analysis from S. Prodon Summary BE-BI LIU-PSB review 09-05-2019

BE-BI LIU-PSB review 09-05-2019 Active work units: BC 64020 Diamond BLMs in 1L1, OP request to replace OASIS by new aqn. chain Feasible : all components are available. Similar system as in SPS: OP to check if it fulfills their requirements. A new functional specs now under engineering check. Different from LHC/SPS system. Under study by BI on how to integrate this smartly. Budget : 50kCHF will be given back from CO, investigating how to fit ADC cost with this amount. Injection line BLMs: L4 baseline BLM Locations: received from LIU Plan 10198: Completion of L4T line installation after sector test Plan 11400: Installation of Beam Loss monitors in LT/LTB/BI lines Action : DIC done ECR on going (looking forward to getting integration drawings) Extraction line BLMs: WU 126825, until 12-2019 On track, cables pulled, installation started Statement unchanged BE-BI LIU-PSB review 09-05-2019

BE-BI LIU-PSB review 09-05-2019 Active work units: BC 64021 Watchdog BR.TMD in 8L1, Part 2: WU 91542, until 12-2018. Hardware upgrade : Cal. Current amplifier to be produced this year WD FESA class : on going, debugging in LAB. DCCT electronics upgrade, Part 2: WU 91543, until 12-2019. Electronics for L4 intensities: Prototype now under test. Production in 2019 Budget: 30kCHF foreseen for 2019, OK Tune pick-ups: WU 161665, until 12-2019. Installed in YETS, commissioned and operational Budget: 5kCHF 2019 for electronics, OK Stripline PU upstream BI.SMV10: WU 191503, until 12-2019. Parts under production. Readiness for installation: Sept 2019 ECR 2003464: approval accepted Budget: OK Inductive PU upstream PI.SMH42: WU 191504, until 12-2019. Spare part passed vacuum acceptance test. Readiness for installation: April 2019 ECR 2084600: draft state BE-BI LIU-PSB review 09-05-2019

BE-BI LIU-PSB review 09-05-2019 Active work units: BC 64022 BTVs at extraction, BT.BTV10-30, WU 91547, until 12-2019 Ready Budget: 5kCHF 2019, OK New Tank for BI.BTV30, Part 2: WU 93002, until 12-2019 Budget: 22kCHF foreseen for 2019, OK H0/H-detectors, WU 91544, Completed TbT profile meas. for injection matching: WU 96106, until 12-2019 One tank installed. Commissioning after LS2 - priority now shifted to PS Acquisition board: PS version validated with beam Budget: Should be OK (TbC) BE-BI LIU-PSB review 09-05-2019

LIU-PSB EVM Curves Schedule variance -3.8 months: ~4 months delay: TbT : delay of aqn chain BWS : delay of three components 07/09/2019 S. Prodon

LIU-PSB EVM Metrics from Project Start to Date 2019 64020: BLM Cost to completion update PV = 1,155 k CtC = PV 07/09/2019 S. Prodon

LIU-PSB EVM Metrics from Project Start to Date 2019 64021: BPM & BCT Cost to completion update PV = 1,251 k CtC = PV 07/09/2019 S. Prodon

LIU-PSB EVM Metrics from Project Start to Date 2019 64022: Profile monitors Cost to completion update PV = 615 k CtC = PV 07/09/2019 S. Prodon

LIU-PSB Active Workunits 6 WUs active 07/09/2019 S. Prodon

LIU-PSB Active Deliverables 07/09/2019 S. Prodon

BE-BI LIU-PSB review 09-05-2019 Summary Watchdog (BR8.TMD) Cal. Current amplifier to be produced this year DCCT Prototype electronics under test. Final version to be produced this year TbT profile measurements Acquisition board: PS version validated with beam. Budget BC 64020 : balanced budget, 50 kCHF transferred from CO for acq chain ???? BC 64021 : balanced budget BC 64022 : balanced budget 6 remaining active WUs are on track BE-BI LIU-PSB review 09-05-2019