DSC ChMC Switching Programme Update 10th July 2019

Slides:



Advertisements
Similar presentations
1 Project Smart Metering Portfolio Foundation & DCC Day 1 Updates April 2013.
Advertisements

UK Link Technology Refresh
XRN4361 – UK Link Release 2 - Delivery
Market Trials ChMC 8th August 2018.
Overall Project RAG Status
DSC ChMC CSS update 13th June 2018
Amendment Invoice Task Force Progress Report
Overall Project RAG Status
Overall Project RAG Status:
Amendment Invoice Task Force Progress Report
UIG Task Force Progress Report
Action/ Deadline/ Event
Cutover & Implementation Aggregated Programme RAG
DSC ChMC CSS update 7th November 2018
Amendment Invoice Task Force Progress Report
Overall Project RAG Status
DSC ChMC CSS update 10th October 2018
Key Value Indicators (KVIs) Version 1.1 (amendments from V1.0 in red)
2019 Release Planning Options inc Modification 0621 / GB Charging Project DSC Change Management Committee update July 2018.
Release 3 Update November 2018.
DSC ChMC CSS update 8th August 2018
CSS Update for CoMC 19th September 2018
DSC ChMC CSS update 6th July 2018
DSC ChMC CSS update 11th December 2018
Chris Warner UNC Modification Panel 21 December 2017
Chris Warner 5th February 2018
Release 3 Plan Options Analysis
Overall Project RAG Status
DSC ChMC CSS update 13th February 2019
Overall Project RAG Status:
Release 3 Update 13th February 2019.
DSC Governance Sub Group Recommendations
DSC ChMC CSS Consequential Update 13th March 2019
Amendment Invoice Task Force Progress Report
Overall Project RAG Status:
XRN Nov 19 Release - Status Update
Release 3 Update 07th March 2018.
Release 3 Scope & Proposed Plan
Change Management Committee – Retail & Networks Update
Amendment Invoice Task Force Progress Report
Created by: Ramona Lewis-Dailey
UIG Task Force Progress Report
UK Link Future Release 3: Track 1 Implementation Approach for Approval at ChMC 2nd October 2018.
Overall Project RAG Status
DSC ChMC CSS update 09th January 2019
DSC ChMC CSS update 12th September 2018
Release 3 Update 07th March 2018.
Created by: Ramona Lewis-Dailey
4340 – UK Link Future Release 1.1
UK Link Future Release 3: Track 1 Implementation Approach for Approval at ChMC 2nd October 2018.
UIG Task Force Progress Report
UIG Task Force Progress Report
DSC ChMC Switching Programme Update 10th July 2019
XRN Nov 19 Release - Status Update
UIG Task Force Progress Report
DSG Governance Group Recommendations.
UIG Task Force Progress Report
XRN4914 MOD Retrospective Data Update Provision
DSC ChMC Switching Programme Update 10th July 2019
Overall Project RAG Status:
XRN Nov 19 Release - Status Update
UIG Task Force Progress Report
DSC ChMC Switching Programme Update 11th September 2019
DSC Change Committee Update
DSC CoMC Switching Programme Update September 2019
UIG Task Force Progress Report
UIG Task Force Progress Report
DSC CoMC Switching Programme Update 17th July 2019
DSC ChMC Switching Programme Update 9th October 2019
SwitchStream: Product update
Presentation transcript:

DSC ChMC Switching Programme Update 10th July 2019

Switching Programme We continue to track at an amber status from a switching programme perspective, we are still pending clarification from the CSS physical design and closeout of open actions at CSSC DSG meetings. The next release of the physical design was released on Thursday 1st August, Xoserve have reviewed and commented on this design document. Review and comment discussion and tracking continues via the Ofgem Design forum, the next meeting is being held on Monday 12th August. This is the last design forum for review of the physical interface document prior to planned approval on the 23rd August at Programme Design Authority. Sunday 21st July saw the release of the full end to end Core system and Services Integration Approach document (CSSIA). The review of this document was an industry wide activity with parties only having five days for review and comment with the deadline being Friday 26th July 2019. Xoserve have reviewed this document and returned our comments within the deadline. The document is a fair document with the lower level detail being worked up in a number of areas at various technical working groups. These groups are yet to be set up but from our discussions with the SI we understand these will commence shortly and will run through the Autumn period.

Switching Programme A revised CSS Integrated plan (CSSIP) has been released by Netcompany. Xoserve and Netcompany met week commencing Tuesday 23rd July for a detailed walk through of the CSSIP to understand how Xoserve’s consequential plan links into the CSSIP. This was a very constructive and collaborative meeting during which Xoserve walked through our consequential delivery plans highlighting dependencies and issues against some of the CSSIP tasks. Joint actions have been taken for corrective action and CSSIP update where required. PWC are hosting two Industry forums for a walkthrough the revised CSSIP. This event is being held on two dates one in London and one in Solihull. The dates are as follows: 8th August – Solihull 9th August - London

Switching Programme Xoserve’s detailed design phase continues with the majority of external industry workshops completed. The following workshops and topics remain: 16th August Data Enquiry File Formats and API’s 4th September and 17th September are both pencilled in contingency dates Next meeting I will present to you the topics we have covered and the high level design recommendations that have passed into our build phase. These decisions have been recorded within HLSO slide decks and will be updated and published within the relevant BRD’s. We will begin to issue change packs from later this month.

Funding status

CSSC Funding Status

Funding via Budget Planning process for BP21 CSSC Financial Update BP19 covers CSSC until FY 2020 Funding via Budget Planning process for BP21 2019 2020 FY 21 Internal Xoserve assessment of costs Based on impacts due to CSS Design & Programme updates Transition & Service Mgmt Impacts External Testing Impact assessment Dates to be confirmed CSSC Funding Update Dec 19 Based on analysis CSSC Funding Update Mar 20 Based on analysis of testing requirements CSSC Funding Update July 20 Based on Transition & Service Management CSSC Funding Update Jun 2019 Planned CoMC financial updates dependent on Programme dependencies