LHC Progress Friday 30 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
Advertisements

Lumi scan limits checked (in preparation for next fill VdM scans).  Trims of up to 150 um per beam in IP1 & IP2 both planes both beams were done (IP5.
Thursday 20 th April 01:53 RCBV17.R7B2 tripped as happened few days ago: SIS intercepted. 05:54 Stable beams, 1380b, still RF problems B1, abort gap cleaning.
:00 meetingEBH 1  6:39 beam dump by BLM 655ms RS on BLMEI.05L4.B2E10_MBRB (which is downstream of BSRT B2).  The losses increased during.
LHC Status Tue Morning 22-Aug
Saturday Coordinators weekend: Mike Lamont, Eva Barbara Holzer
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
Monday Recover after trip of RB.A81  Cause of the trip not clear. MP3? 09:00-13:00 Re-inject and Injection verification. In parallel investigations on.
Sunday 28 Nov. 00h00: Stable beams # x 121 b. Peak lumi 2.0e e25 cm-2 s-1. 09h52: Dump fill # delivered 440 (mb)-1. RCBCH8.L5B1 trip.
Wednesday September 14th
Thursday 25/11/10 & Night Work on: 16:15 Inject fill #1520
Friday 07:00 Power glitch on the EDF network. Point 8 affected.
Tuesday 11th September LHCb dipole presently fault off
Monday fill with 1092 bunches (6 h stable beams)
Monday 11/07: Recovery Plenty of accesses.
Thursday 09:30 VdM scan for CMS, standard ADT gain.
02/08/ :35: Lost access chain in point 2 (PX24 PAD)  Dump after ~14.5 hours ~100 nb-1.
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Tue :25 Beams dumped due to RF vacuum interlock
LHC Morning Meeting - G. Arduini
Saturday 12:00 Fill 1992 in stable beams.
Tuesday 08:30 Fill 2700 dumped by QPS on RCBXH2.L1
LHC operation in week 39 Coordination: Mike Lamont, Jan Uythoven, Malika Meddahi Thanks to OP crews, HW and SW teams + patient customers Aims for the week.
Thu 19/5 06: :00 Investigations from vacuum and cryogenics
Summary of Week 16 G. Arduini, J. Wenninger
Scrubbing progress - 09/12/2012
Friday 31st August & night
Thursday 10th May - morning
Wednesday 8th August & night
Saturday 4.12 Beam in the SPS at 09:30 Beam in the LHC at 10:00
LHC Morning Meeting - G. Arduini
Wednesday 30th November 10:00 Access PZ33 for RP, Cryo, EPC, ELQA
Friday 14th December - morning
Monday Morning – recovery from cryo.
Friday :00 machine setup for luminosity run. Better b-to-b stability from injectors. 01:58 stable run with 228 bunches 11:00 luminosity leveling.
Wire almost entirely through beam before BLM triggers dump
Tuesday 22 November 2011.
Friday Morning 7:30 injection for fill 2908
Friday AM Some oscillations of the cryo conditions in MSR8 perturbed the setup for injection. RF frequency interlock fixed – required a reset of RF controls.
Friday 16/3 08:30 – 10:15 Access for QPS and EPC (BI in point 4)
Programme for VDM measurements Friday Oct 15
Wednesday 10/5 Cryo recovery until 18:30
Aims for the week Recover from technical stop and precycle at 10A/s
Thursday Physics fill 1250 (with 13b) dumped at 10.30
Thursday morning 08:45 Stable beams fill 2855 for ATLAS/CMS VdMs.
Monday 14:00 beam dump Access:
Rocky last 24 hours Losses Q6.R5 Orbit SIS TCDQ OK! Power converters
90m "proper" VdM scans in the 90m/10m optics
Tue/Wed 12/ :00 Probe beam back again
TE-EPC PIQUET BAD MANIPULATION
Saturday Wire scans at end of fill 1253 B1H : 4.2 B1V : 4.3 B2H : 5 B2V : 7.2 Beams dumped (after ~14h of collisions) Some issues during refill.
Friday 8/10/10 - Morning Planned to keep fill until the afternoon
LHC Status Tue Morning 22-Aug
Saturday :42 stable beams fill 3541
Monday Fill 1803 into stable beams at 9:30. Dump at 19:45.
Friday morning 08:00 Stable beams with 840b.
LHC Morning Meeting - G. Arduini
LHC - Week 38 Technical stop: Katy Foraz
Saturday 2nd October BLM threshold follow-up - Bernd Dehning and Joerg Wenninger Following MPP approval, Bernd Dehning has increased the BLM thresholds.
Wednesday h18: 228b fill lost just before start of ramp.
Monday 26th September 7:30 Beam dump, QSP on RQX.R1, lost cryo in ITR1, 91 pb-1. Cryo recovery, needed about 1.5 h. Setting of TI2 collimators to 5 sigma.
Weekend Summary Friday Saturday Sunday C. Gemme, INFN Genova,
Friday 15th February - morning
Thursday 20th July - morning
Monday 27th August & night
Tuesday End of fill 1393 Movement of suspicious Roman pots OK
Wednesday 6.10 Morning: Quench test at 450 GeV
HI2011 Commissioning Status
Monday 152 bunch operation summary
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

Friday 1st October : Van der Meer scans 7:00 – 12:00 : Filling 19 single bunches/beam, ~8e10p/bunch! Every ~10 minutes TT60 MBB PC tripped due to over temperature. Reset it each time. Required intervention only done while ramping (PO piquet was working all day long) Communication between the database and the injection sequencer during setting requests active. Initially wrongly thought it had been a problem with the CBCM. Several releases of the injection sequencer were necessary to make all the different modes work again. However, now the IQC RF bucket check always fails as the injected scheme is not correct in the DB. It is masked for the time being. 13:30 – 16:30: Stable beams. Done ATLAS vdm scans and only half of the CMS scans. Could not make the vdm scans in LHCb and ALICE, and also no length scale calibrations, no longitudinal scans, etc. 11/4/2019 LHC status

Friday 1st October : Recovering ~16:30 : Beams dumped. Electrical perturbation. SVCs at point 2, 6 and 8 were tripping, producing the trip of sector 81, the main dipoles of sector 12, 34 and 67, the ATLAS toroid and also one RF module. The electrical service was very efficient in reconnecting all SVCs ~19:30 LHC back in service ! Start pre-cycle started and ramping up of all exp. magnets Until 23:00: Recovering beam conditions in the machine– Chromaticity evolution at 450 GeV for beam 2. MBB TT60 PC was preventing from injecting B1 Following corrections: chroma correction +12 in H and -12 in V; chroma correction of +3 in V after 40 min; Chroma values after about 2 hrs of about 8.5 in H and 1.5 in V. 11/4/2019 LHC status

Friday 1st October – Recovering . Mirko Pojer 11/4/2019 LHC status

Friday 1st to Saturday 2nd 0ct – to stable beams 23:00 – 07:00 : Alick and Ron on shift : Great work done in re-establishing stable beams Injection of 152b x 152b, with 8b+8b injection filling pattern Careful monitoring of the beam parameters from the injectors and injection oscillations Vacuum expert in CCC G. Schneider during the whole process 11/4/2019 LHC status

Friday 1st to Saturday 2nd October Alick Macpherson 11/4/2019 LHC status

ATLAS 11/4/2019 LHC status

ALICE 11/4/2019 LHC status

CMS 11/4/2019 LHC status

LHCb 11/4/2019 LHC status

Saturday 2nd October 5:08 – 7:08 : stable beams 11/4/2019 LHC status

Saturday 2nd October 7:08: Dump beams. UFO point 2 11/4/2019 LHC status

11/4/2019 LHC status

TODAY Refill in progress Physics fill 152b x 152b Tomorrow: Physics 152b 11/4/2019 LHC status

11/4/2019 LHC status