PS magnet status D Bodart 25/06/2019.

Slides:



Advertisements
Similar presentations
Tagger and Vacuum Chamber Assembly Procedure. Outline. Assembly procedure for tagger and vacuum chamber. Support stands. Alignment.
Advertisements

Daniel Schoerling TE-MSC-MNC 1 Review of AD-ELENA TL dipole Daniel Schoerling on behalf of WP 2.2 ELENA IIC meeting 27 th February 2014.
Muon g-2 Muon g-2 Experiment Quarterly Report Aria Soha All Experimenter’s Meeting March 2, 2015.
Magnets for the ESRF upgrade phase II
Vacuum System Elements for BESSY II Vacuum Equipment All vacuum elements are produced at BINP in accordance to the European standards and satisfy the.
Tagger and Vacuum Chamber Assembly Procedure. Preassembly of second bottom yokes and poleshoes. a) Install special support. b) Place the second bottom.
TAGGER MAGNET DESIGN Presented by Tim Whitlatch Hall D Tagger Magnet Design Review July 10,
Robert Ruland MMF Layout, Workflow October 14, 2004 MMF Review 1 MMF Layout, Workflow Robert Ruland Magnetic Measurements Facility.
CERN 4 th /5 th December 2012 Todays speaker Paul Allen 1.
ILC Main Linac Superconducting Cryogen Free Splittable Quadrupole Progress Report V. Kashikhin for Superconducting Magnet Team.
Superconducting Large Bore Sextupole for ILC
BROOKHAVEN SCIENCE ASSOCIATES Abstract Magnet Design Workshop: Magnet Design and Analysis Charles Spataro, NSLS-II Project NSLS-II is a new 3Gev synchrotron.
11 T Dipole informal coil and assembly readiness review Long coil and fabrication tooling development status and plans September 22 nd, 2013 – F. Savary.
SPS scrubbing experience: electron cloud observables L. Mether on behalf of the LIU-SPS e-cloud team LIU SPS scrubbing review, September 8, 2015.
Daniel Schoerling TE-MSC-MNC 1 Magnets Daniel Schoerling on behalf of WP 2.2 and WP 2.16 ELENA Project Review 14 th – 15 th October IT.
1 BROOKHAVEN SCIENCE ASSOCIATES Abstract Magnet and Girder Integration Lewis Doom, NSLS-II Project National Synchrotron Light Source II (NSLS-II) will.
Injector PP Setup Plan and Status November 18, 2008 Haixin Huang.
Shear Problem Defined There are no bolts on the inboard side of the coil structure to account for shear forces. Bottom Line: friction alone will not prevent.
Beekeeping Equipment What you Really Need Vs. What you Think You Need Vs. What you Want.
SBS Magnet John J. LeRose. Assembly drawing of 48D48 magnet as used at BNL (vertical field)
BI.DIS10: Magnets & generators R. Rosol, L. Sermeus, T. Stadlbauer, TE-ABT LIU review, 20 November
LAV construction status – M. Moulson (Frascati) – Photon Veto WG – CERN – 12 Jul 2011 LAV construction status: a snapshot 2 A1 Arrived at CERN 29 Jun.
SBS Magnet and Infrastructure Status Robin Wines July 2015.
ABT LIU Project Review 2015 BI.KSW: Magnet November 20 th 2015 L. Feliciano TE/ABT.
Low Energy RHIC e - Cooling 1 IP2 64 m LEReC-I (1.6-2MeV): Gun to dump SRF gun used as a booster cavity.
CLIC Stabilisation Day’08 18 th March 2008 Thomas Zickler AT/MCS/MNC/tz 1 CLIC Quadrupoles Th. Zickler CERN.
Michał Matusiak Sławomir Wronka
Proton Plan PMG 5/25/06 David Harding Booster Correctors Status and CR David Harding.
ABT review on the LIU-PSB Systems PSB KSW Magnets September 10 th 2014 L. Feliciano TE/ABT.
LSC May 2013 Outcome of the magnets tests from the PS, Leir and transfer lines Dominique Bodart.
Cold Mass and Assembly Tooling Design, Procurement Status and Assembly Plan Igor Novitski Fermilab 15 T Dipole Design Review April 2016 April 28-29,
1 VV Support Fixture FPA Stage 1 PDR Review August 10, 2005 T. Brown.
DDBA magnets Chris Bailey Low emittance rings Sept Frascati.
EuCARD-WP7-HFM meeting 15 November 2011 Status of construction of FRESCA2 dummy coil assembly Attilio Milanese, Juan Carlos Perez.
High energy beam transport.
George Mahler, Steven Trabocchi, J. Tuozzolo, Stephen Brooks
Some Design Considerations and R &D of CEPCB Dipole Magnet
2016/9/30 Yasuhiro Infra/CFS mini-ws
Procurement Status Miao Yu 11/19/2013.
PANAGIOTIS FARANTATOS(TE/MSC-MNC)* WP3, ESR 4: New Magnet
Status of HESR 18th March Gießen Dieter Prasuhn.
Roadmap for triplet cryostats
Brief Status SPS Prototype PSB Prototype Installed in LS1
Status of the CLIC DR wiggler design and production at BINP
The design schemes of the low field dipole magnets
Uppsala University Contract UH2015/09 - UA2016/05 Job nr. 5973/7200
EFREMOV INSTITUTE SAINT PETERSBURG RUSSIA
Target and Horn status report
ELENA electron cooler and SEM grids status
Spectrometer Solenoid Fabrication Status and Schedule
Magnets for the ESRF upgrade phase II
Pierre-Alexandre Thonet
Beam Wire Scanners (PS prototype and LIU series)
Proposal for the modification of building 151 in view of the LS2 PS main magnet and TT2 consolidaiton projects Dominique Bodart TE-MSC-MNC 29/09/2017.
Beam Injection and Extraction Scheme
Beekeeping Equipment What you Really Need Vs. What you Think You Need
ELENA Magnet Installation Planning
The Knowledge Sharing Center is an independent and non-profit knowledge platform.
KICKER STATUS G-2 meeting March 5, 2014
PERMANENT MAGNET QUADRUPOLE FOR THE LINAC 4 CCDTL
III. Correction Dipoles MDG Accessories for all Magnets V. Summary
High Precision Magnet Production for NSLSII at IHEP
Experimental equipment Edgar L. Black February 17, 2019
LCLS Undulator System Status and Schedule
GROUP 12 CAS – Erice - March 2017 Andrea DE FRANCO
LCLS Undulator System Status and Schedule
ThomX – Commissioning Meeting – 25/01/2018
IR Beam Transport Status
SAME 15 existing quadrupoles (QFS, QDS, QFL)
Progress on cryostat design and production
Presentation transcript:

PS magnet status D Bodart 25/06/2019

Status of the injection bumpers Production of the pre-serie magnet: 29/01/2018 Placement of the contract for production serie: 18/11/2018 Status of the production: All equipments available and machined. Magnets are under assembly Inspection of the manufacturing: Yokes and coils are within specifications IP2 covers available, support fixture ready for installation Fig. 1 Assembly of the magnet yokes compensation coils Fig. 2 finished coils Fig. 3 finished magnet supports Fig. 4 Assembly of the coil ends

Status of the injection bumpers Planned delivery of the four bumper: 07/2019 Certification of the magnets: 07/2019 Magnetic measurements: 08/2019 Ajustement of the sextupolar compensation: TBC with Marco (mail 19/06). The sextupolar component generated by the chamber is almost not visible (10 -4 ) order with current configuration. Adjustment range of the coils is within 102 of the required span. Measurements of the tuning resistances has been performed to choose the ones matching with the generated field. NB: to install the magnets the vacuum chambers shall be installed. Fig. 5 finished magnet yokes

Status of the BGI vertical magnet Placement of the contract for production serie: 18/06/2019 Status of the production: Steel is currently shipped for lamination cutting. Kick-off meeting with production company was done on 20/06/2019. The company SEF has built the BGI horizontal version and knows the constraints of the manufacturing in terms of assembly integration and performances. Integration of the magnet is finished including installation of the vacuum chamber in the magnet. Fig. 6 top view of the BGI setup Fig. 7 side view of the BGI (outer ring)