CSC Electronics Installation and Commissioning Oct ‘06

Slides:



Advertisements
Similar presentations
H2 Layout for EMU a brief report of a couple of visits by Darin A., Jay R., and FG.
Advertisements

P. Paolucci - I.N.F.N. di Napoli / Joint RPC-Trigger meeting EASY Crate board/cratechannel/crate (max power) power/crate# crate/rackpower/rack#
Commissioning of CSCs and Peripheral Crates Task L M. Ignatenko UCLA October
LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation.
June 2004 Andrea Gaddi, PH-CMI USC Installation Commissioning Task Force 1st Run Meeting, June 3rd, 2004.
Electrical Integration WBS Eric J. Mannel Columbia University Electronics Project Engineer VTX and FVTX.
The MINER A Operations Report All Experimenters Meeting Howard Budd, University of Rochester July 8, 2013.
Electrical and Optical Cables Installation at P5 What When How H. Breuker
Saverio Minutoli INFN Genova 1 1 T1 Electronic status Electronics Cards involved: Anode Front End Card Cathode Front End Card Read-Out Control card VFAT.
Endcap Integration Workshop: June 11-14, CSC Commissioning Andrey Korytov.
1 5 December 2012 Laurent Roy Infrastructure / Electronics Upgrade -Cabling (long distance) -Rack and Crate (space, electrical distribution, cooling) -Detector.
Status and plans for online installation LHCb Installation Review April, 12 th 2005 Niko Neufeld for the LHCb Online team.
W. Smith, DOE/NSF Review, August, 2006 CMS Trigger - 1 SORT ASICs (w/heat sinks) EISO Bar Code Input DC-DC Converters Clock delay adjust Clock Input Oscillator.
GIF in EHN1- layout, construction and schedule Adrian Fabich, EN-MEF-LE GIF users meeting, 12 th February 2014.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
T.Y. Ling EMU Meeting CERN, September 20, 2005 Status Summary Off-Chamber Electronics.
CSC Track-Finder Plans for Commissioning at Bat.904 and Point 5 Darin Acosta University of Florida.
Сессия Ученого Совета ОФВЭ 27 декабря 2006 Проект CMS в 2006 Ю.М.Иванов В.В.Сулимов.
Experimental Areas Studies Lessons learnt at CMS M Gastal & CMS Technical Coordination (A Ball, W Zeuner)
CF 16/Feb/20031 H8 Beam Test in 2003 ─ Preparation status TGC-Japan electronics group.
8/31/05DR Lynch1 HBD Preparations in the IR Don Lynch.
André Augustinus Infrastructure  Turbines  Radmon  Thermocouple readout  Netgear redundancy  Other cavern items  Cooling CRs  Other CR and surface.
Infrastructures and Installation of the Compact Muon Solenoid Data AcQuisition at CERN on behalf of the CMS DAQ group TWEPP 2007 Prague,
CMS Upgrade Workshop, FNAL, Oct 28-30, O.Prokofiev Update ME4/2 Chambers and Tooling A construction of new ME4/2 prototype at CERN Factory tooling,
EMu Slice Test -- Status Frank Geurts FNAL/Rice
T0 DCS Status DCS Workshop March 2006 T.Karavicheva on behalf of T0 team.
Cables Ian Crotty 8 May 2012 Cables for the RE4 Upscope in CMS News. The HV cables are in the Integration DB (INB/904) The Hv order is confirmed. Need.
1 hcal installation and commissioning status pawel de barbaro, vitali smirnov, june 11, 2007.
6-Dec-05PC Commissioning1 Peripheral Crate (PC) Commissioning Status Fred Borcherding, CSC/EMU Group.
RICH Readout Plans F. Bucci, M. Piccini on behalf of the RICH WG.
Cables for the RE4 Upscope in CMS
University of Wisconsin
Cabling for LHCb Upgrade
Integration and Services RE3/1 and RE4/1
09/02/2006 Muon week HV and LV systems status for Magnet Test S. Braibant, P. Giacomelli, M. Giunta.
HF Test station at P5 A.Mestvirishvili.
CMS Area Working Group Meeting
RHICf Japan meeting General status
T1 Electronic status Conclusions Electronics Cards:
ProtoDUNE Installation Workshop - DAQ
EMU Slice Test Run Plan a working document.
Chamber Design and Integration RE3/1 and RE4/1
CSC Organization in 2013 Jay Hauser To be updated at
10/month is the present production rate 2 FTE + sporadic contributions
CSC - HV, LV - Present Status and Future Plans Toward Phase 2
CMS RPC Endcap RE1 Status Report
Pierluigi Paolucci - I.N.F.N. Naples
Trigger M&O Progress -- Florida, Rice, UCLA, Wisconsin
CSC Electronics Installation and Commissioning CSCE I&C
Regional Cal. Trigger Milestone: Production & Testing Complete
New Calorimeter Trigger Receiver Card (U. Wisconsin)
Trigger M&O Progress -- Florida, Rice, UCLA, Wisconsin
B904 Status Report by Fred B.
HV-LV-DCS Status NEWS DCS Endcap Integration
UXC55 ME Muon Endcap On Detector Layout
RPC Detector Control System: towards the final system
Fred’s Input to Rice Workshop
Current Module LT Testing Capability
Pierluigi Paolucci & Giovanni Polese
19-April-05 Peripheral Crate Testing, Installation, and Commissioning PC I&C Feb ’06 EMU Fred Borcherding 16-May-19 PC I&C Feb'06.
Equipment Management DB Rack Wizard USC55 Underground Counting Room
Plans for the 2004 CSC Beam Test
Peripheral Crate Testing, Installation, and Commissioning
Prepared for CSC by Fred Borcherding FNAL
CSC Electronics Installation and Commissioning CSCE I&C
19-April-05 CSC ME1/1 Meeting
Needed for Team A on -End
ME I&C -- PC Electronics
Racks PC Rack >> 24 mini and 12 tall PC racks Mini Racks
CSC Shift Training and Operation + B904 Status
Presentation transcript:

CSC Electronics Installation and Commissioning Oct ‘06 19-April-05 CSC Electronics Installation and Commissioning Oct ‘06 Fred 13-Nov-19

19-April-05 CMS Schedule The schedule has been presented elsewhere – present again to point out significant events for Electronics Installation USC55 6-Oct -- Racks and safety available 6-Oct – Ready for PC’s in farm Oct-Dec -- Phase 1 >> Sub-detector crate installation in racks and individual sub-detector commissioning ( no detector ) Jan-March’07 -- Phase 2 >> integration of sub-detectors ( no detector ) 7-Jan’07 – Mini-DAQ and USC control room installed UXC55 Oct-Jan’07 – Lowering of YE+3,2,1 SX5 Nov – YE-3,2,1 moved to alps end of building against wall 13-Nov-19

EMU Electronics Installation 19-April-05 EMU Electronics Installation Would like to have Contact person for electronics installation from each EMU sub-system List of what will be installed Some idea of necessary prerequisites from CMS and rest of EMU Why All of CMS needs to meet the IMB requirements for labels on all hardware pieces Need inventory, db listing, and labels on each piece BEFORE it can be lowered on disk OR installed downstairs Need to coordinate efforts from all Need to schedule and/or prioritize different activities need the same resources or geographic area 13-Nov-19

Have so far … Need similar list from each EMU sub-group 19-April-05 Have so far … Need similar list from each EMU sub-group Need complete list Need existing names and serial numbers 13-Nov-19

SX5 Now through ‘start of lowering’ After ‘start of lowering’ 19-April-05 SX5 Now through ‘start of lowering’ Upload all +Z electronics into Equipment Management DB Required by CMS before lowering Working on getting installed PC Electronics in now Also need HV, Gas, etc. Continue I&C on –Z PC Portable test stand Need ‘only’ - wall power, network cable, access to PC After MTCC >> Remove MTCC electronics and racks and set up all plus disks for lowering After ‘start of lowering’ -Z end will move at some time, when? How much space will there be around and between disks? Expand scope of I&C with portable test stand Include more ‘fast site’ type tests Move ‘slice test’ to –Z ?? Lower priority than underground activities 13-Nov-19

UXC55 After lowering +Z (after Nov ’06) 19-April-05 UXC55 After lowering +Z (after Nov ’06) Install and commission ‘missing’ PC’s Install 4 bottom racks Test – using portable test stand Need wall power, network cable, access to PC Need 2nd test stand? Revisit other PC’s Repair any possible damage Install any missing hardware Retest – using portable test stand 13-Nov-19

UXC55 cont. Begin FULL installation and commissioning Install 19-April-05 UXC55 cont. Begin FULL installation and commissioning Install LV, CANBus, HV, Gas, …. Initiate ‘slice test’ type setup underground Need USC55 Cables from USC55 <-> UXC55 Schedule is dependent up Utilities Cable installation and cable chains 13-Nov-19

USC55 Prepare Racks Install Crates Install boards & Commission 19-April-05 USC55 Prepare Racks Put in rails, patch panels Can start almost immediately Utility services not finished Install Crates Wait to start until after ‘many’ other sub-detectors have installed theirs Cleaner more stable environment Install boards & Commission Sometime … 13-Nov-19

USC55 Rack Layout Lower Floor - USC55 From TY Ling 13-Nov-19 19-April-05 USC55 Rack Layout CSC FED Racks CSC FED Crate CSC HV Racks CSC Track Finder Rack Lower Floor - USC55 From TY Ling 13-Nov-19