Long Island Interconnection Working Group Meeting August 22, 2019

Slides:



Advertisements
Similar presentations
1 Smart Grid Vision Electric Grid Modernization Steering Committee Grid Facing Technology Subcommittee January 14, 2013.
Advertisements

Distributed Intelligence Provides Self-Healing for the Grid
DOD Microgrids The Missing Link: Microgrid Applications Michael Dempsey P.E. Burns & McDonnell June 12, 2013 © 2013 Burns & McDonnell. All Rights Reserved.
Project 1.4 Operational Strategies and Storage Technologies to Address Barriers for Very High Penetration of DG Units in Intelligent.
DISTRIBUTED GENERATION ISLANDING - IMPLICATIONS ON POWER SYSTEM DYNAMIC PERFORMANCE Sandhya P Prabhu April 19, 2006.
Disconnect Switches There are many purposes for disconnect switches in substations and power lines. They are used to isolate or deenergize equipment for.
Chapter 7 SYSTEM PROTECTION
Interconnect Protection of Dispersed Generators
1 Power Quality Mary Santori, P.E. Senior Engineer September 12, 2013.
Applying the Distribution System in Grid Restoration/NERC CIP-014 Risk Assessment Srijib Mukherjee, Ph.D., P.E. UC Synergetic.
CLEMSON UNIVERSITY DG CONFERENCE UPDATE ON THE CURRENT STATUS OF DG INTERCONNECTION PROTECTION WHAT IEEE 1547 DOESN’T TELL YOU ABOUT INTERCONNECTION PROTECTION.
Frankfurt (Germany), 6-9 June 2011  PV in Spain: Basically Large plants connected to MV or HV Mainly in rural areas (generation exceeds consumption) 3,000.
Need for protection Power system must be kept in operation continuously without major breakdowns This can be achieved in two ways: 1.Implement a system.
Doc.: IEEE /0121r1 Submission January 2010 Craig Rodine, Electric Power Research InstituteSlide 1 Some High-Level Smart Grid Requirements Date:
Power Quality Impacts of Distributed Generation Roger C. Dugan Sr. Consultant Electrotek Concepts, Inc. Tennessee Tech. February 9, 2004.
Queensland University of Technology CRICOS No J Protection of distributed generation connected networks with coordination of overcurrent relays.
1 Distributed Generation and Power Quality-Continued.
Submitted to: Submitted by:
A SEMINAR ON 400 KV GSS(RRVPNL) BIKANER.
ECE 498HZ: Power Distribution System Analysis
Uninterruptible Power Supply Improves Reliability at The Australian Synchrotron Sean Murphy – ARW 2013 Melbourne.
Loop-Sectionalizing Automation Scheme Colin Hawthorne 4/26/2016.
SYNERGY INSTITUTE OF ENGINEERING AND TECHNOLOGY
Protection of Power Systems
STUDY OF ELEMENTS OF A 220/132/33KV SUBSTATION
Project WECC-0100 Standards Briefing WECC-0100 SDT April 7, 2016 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.
Protection and Relay Schemes
Announcements Design Project has firm due date of Dec 4
Power Quality at Solar Distributed Generation Facilities
Sub Station.
Protection of Power Systems
Introduction to Electric Power System and A. C. Supply
IG BASED WINDFARMS USING STATCOM
2011+ NEC Article Arc Energy Reduction. Where the highest continuous current trip setting for which the actual overcurrent device installed.
Inverter Disconnects During Transmission Disturbances
Interconnect Protection of Dispersed Generators
Advanced Fuse-Saving Techniques
EAS Lessons Learned Summary
NERC Published Lessons Learned Summary
the CERN Electrical network protection system
Basics of electrical engineering
THREE-PHASE GROUND-FAULT BASICS
Grid feeding monitoring relay
Circuit Breakers & Reclosers
Passive Shunt Compensation
Series Capacitor Compensation
APPLICATIONS Reference: Textbook-Chapter 6,8 & 9 'Power Electronics',C
Project WECC-0100 Update Load Modeling Task Force
ELECTRICAL INSTALLATION AND MAINTENANCE (EIM) 5 INSTALL ELECTRICAL PROTECTIVE DEVICES FOR DISTRIBUTION, POWER, LIGHTING, AUXILIARY, LIGHTNING PROTECTION.
PRC-006-RFC-01 Automatic Under Frequency Load Shedding Requirements
Chapter 7 System Protection
Working with Utilities Sean W. Carr, P.E., PMP®
EU-IPA12/CS02 Development of the Renewable Energy Sector
Electric braking Powerpoint presentation by:- Poonam sharma
Distributed Generation (DG) Modeling Criteria
Protective Relaying Conference
A Tutorial on the Application and Setting of Collector Feeder Overcurrent Relays at Wind Electric Power Plants By: Stephanie Mercer.
ELECTRICAL POWER-II Electrical engineering sixth semester
Distributed Energy Resources (DER) Experiences at CenterPoint Energy
University of Ljubljana, Faculty of Electrical Engineering - Slovenia
Agenda Introduction of Protective Relays
EET 323 – Electrical System Design Lecture 9: Grounding
Interconnection of AES With The Grid
Power System Protective Relaying-Part One
Nathan Kassees, P.E. Sr. Engineer Oncor Electric Delivery
Review of Distribution Network Protection
Project WECC-0100 Update Load Modeling Task Force
HIGH VOLTAGE ENGINEERING Presented By P.Sindhu Asst.Prof EEE Dept
Substation Equipment's
Presentation transcript:

Long Island Interconnection Working Group Meeting August 22, 2019 PSEG Long Island’s Distributed Energy Resource (DER) Direct Transfer Trip (DTT) Requirements Long Island Interconnection Working Group Meeting August 22, 2019

Disclaimer Requirements for interconnection of DER to the LIPA system are defined in the PSEG Long Island’s Smart Grid Small Generator Interconnection Technical Requirements and Screening Criteria for Operating in Parallel with LIPA’s Distribution System document, as currently published. This presentation is intended to be informative, only, and does not modify, supplement, or interpret the requirement document as currently published.

Background Distribution feeders must be de-energized by opening their circuit breaker at the substation to: Clear faults Eliminate dangerous conditions Perform maintenance (where live-line work cannot be performed) Reconfigure circuits Conventional distribution systems have been designed assuming that the utility substation is the sole source of energization Interconnection of DER1 presents the potential for “islanding”; i.e., energization of disconnected circuits by DER In certain circumstances with substantial risk of islanding, PSEG-Long Island requires implementation of “direct transfer trip” (DTT) DTT is a communicated signal transmitted when the substation circuit breaker is going to open, telling DER to turn off 1 DER = Distributed Energy Resource, inclusive of generation and storage connected to the distribution system

When is DTT required? For any DER, of any technology or size1 when DER penetration exceeds 50% of applicable load (Screens P8 & S1) Penetration measured as ratio of aggregated DER capacity to load between substation and next ASU downstream Applicable load is daytime minimum load (10 am – 4 pm) for solar, overall minimum load for other DER types For synchronous generators > 500 kVA For inverter-based generation  1,000 kVA regardless of penetration, or as otherwise deemed necessary For induction generators, as determined necessary 1DER less than 50 kVA are not subject to technical review and are thus excluded

Why is DTT required?

DTT is required solely for protection of the LIPA system and its other customers

Feeder reclosing practices Automatic circuit breaker reclosing is used on all overhead feeders in the LIPA system Sequence: Short circuit fault occurs Feeder protection detects fault and opens feeder breaker Breaker is reclosed after a short delay to test if fault is still present If fault remains, process repeated several more times with longer delays Delays used on LIPA system for the first reclose: Electromechanical reclosers have no intentional delay, i.e. “instantaneous” which actually is  200 ms. Microprocessor relays set to 300 ms delay

Why is reclosing used? The large majority of overhead distribution feeder faults are “temporary” in nature If a circuit with a temporary fault is de-energized, the fault will “self heal” Temporary fault causes: Flashover across an open-air gap, such as from a lightning strike Animal across an insulator Swaying tree branches Reclosing is critical to maintaining customer reliability Majority of faults are eliminated without an “outage” Yields a substantial increase in the SAIFI metric on which utility performance is evaluated

DER coordination with feeder reclosing The feeder must be essentially de-energized when feeder is reclosed to avoid severe transient impacts Doesn’t the fault “de-energize” the feeder? NO! Most faults are on one or two phases, leaving unfaulted phases energized Arcing faults may self-interrupt when the strong short-circuit source provided by substation is disconnected Therefore, DER must not continue energization of feeder beyond the short “instantaneous” reclosing delay Coordination of DER with utility feeder reclosing is clearly required by IEEE 1547 (both 2003 and 2018 versions)

Won’t DER trip due to the fault? Faults detectable by utility protection systems may not dip feeder voltage more than 10% - 20%, Particularly at DER locations on the main feeder and/or near the feeder head The undervoltage clearing time specified by PSEG-LI for voltages between 50% and 88% of nominal is 5.0 seconds More sensitive or faster tripping times are not feasible or acceptable Eliminates capability for DER to ride through transmission disturbances Widespread loss of DER output can threaten bulk power system security

What about built-in inverter anti-islanding functions? DER tested for compliance to UL-1741 are only evaluated for island detection in 2.0 seconds There are no certifications of AI (anti-islanding) performance for shorter times AI testing is limited to single DER with a load Many DER AI schemes use some form of destabilization to drive voltage or frequency to trip points Shortest trip points are 0.16 seconds; 40 ms margin is far too little time for the destabilization to succeed Research testing indicates typical AI detection times in the hundreds of milliseconds even with substantial generation/load imbalance Inverter anti-islanding functions are not effective in coordinating with instantaneous reclosing

What can happen if DER maintains energization? The primary concern regarding DER reclosing mis-coordination is the substantial risk of out-of-phase reclosing With feeder islanded, there is nothing to keep the island in phase with the grid Island phase angle can drift 1260/second without hitting the shortest frequency deviation trip point Angle deviation can be up to 252 at time of LIPA breaker reclose Worst-case is 180 deviation = twice normal voltage across LIPA breaker when it recloses

But aren’t inverters self-protected from this? Unlike synchronous generators, which can easily be damaged by out-of-phase reclosing, inverters are designed for self-protection However, this is not the issue. Out-of-phase reclosing can damage LIPA system assets and customer load devices Severe transient overvoltages Theoretically, up to three times nominal Realistically, 2 – 2.5 times nominal Potential damage to surge arresters and customer loads Motor load mechanical system torque transients Large transformer and motor inrush currents, potentially causing protective device nuisance operation

Why are DTT requirements based on DER size? Risk of islanding depends on the aggregate DER capacity, relative to load, on the feeder DTT implementation costs are independent of DER rating Requiring DTT for small DER that drive the aggregate DER rating over the penetration threshold for islanding creates an undue and disproportionate burden on the small DER Requiring DTT for large DER preserves hosting capacity for small DER

Summary It is essential that DER coordinate with LIPA distribution system reclosing, as required by IEEE 1547 Inverter anti-islanding functions do not coordinate with the reclosing delays used on LIPA system feeders Direct transfer trip (DTT) is necessary to protect the LIPA system and its customers when even transient DER islanding is possible

Questions?