Needed for Team A on -End

Slides:



Advertisements
Similar presentations
André Augustinus 16 June 2003 DCS Workshop Safety.
Advertisements

LECC V. Bobillier1 Overview of LHCb Electronics installation aspects V. Bobillier; L. Roy; J. Christiansen CERN - LHCb.
GE1/1 Services and Strips PCB Andrey Marinov On behalf of CMS GEMs collaboration.
V. Bobillier1 Long distance cable installation status Calorimeter commissioning meeting.
1 5 December 2012 Laurent Roy Infrastructure / Electronics Upgrade -Cabling (long distance) -Rack and Crate (space, electrical distribution, cooling) -Detector.
Calo Piquet Training Session - Xvc1 DCS and DSS Cuvée 2015 – RUN2 Xavier Vilasís-Cardona.
Status of and Installation Plan for DC Gas Control System and Target Work Scheduling Meeting 4 August 2006 PSI W. Molzon, Feng Xiao.
Low Voltage Workshop, CMS Electronics Week CERN, 8 June 2010 W. Lustermann, ETH Zurich EB + EE LV systemOPFC MonitoringEB HV systemEE HV system.
21-Jan-2009CSC - ESSC Jan'091 Report on CSC for ESSC Prepared for CSC by Fred Borcherding FNAL.
1 OperationsOperations CSC is stable running since HI run has started. The low CSC occupancy in HI running allows us to operate all HV channels at nominal.
R. Boyd 1 February  Dr. M. Saleem  D. Jana  M. R. Meera Labbai  R. Boyd.
8/31/05DR Lynch1 HBD Preparations in the IR Don Lynch.
SB 1 Cables from PP to calorimeters Cabling being done by ITEP-Moscow and IAP-Bucarest team Summary for cables/connectors list, rack wizard.
7-Nov-08ESSC Nov 2008 > CSC Early Upgrades by Fred B. 1 CSC Early Upgrades Current plans for "early upgrades" and maintenance during 2009 and 2010 Description:
1 13 Octobre 2011 Laurent Roy ATCA Crate / Infrastructure in place -Rack in D3: dimension -Electrical power availability -Tell1 racks running in D3 (air.
V. Bobillier1 Cable installation status.
Activities of 2008) Jinsook Kim, Yongwook Baek 1.
FED optical cabling issues Matthew Pearson. Meeting with Jan and Francois at tracker week Discussed the TTC splitter and optical cabling paper design.
March 12 th 2013 Muon LS1 operation meeting1 Muon LS1 Status Outline Recap of last week P1 weekly schedule Muon related activities Open issues and discussions.
EMu Slice Test -- Status Frank Geurts FNAL/Rice
14 February 2007 G. Bohner, R. Bonnefoy, M. Crouau, P. Jacquet, C. Lacan, J. Lecoq, S. Monteil, P. Perret, G. Reinmuth, K. Suchorski LPC Clermont PS Very-Front-End.
Cables Ian Crotty 8 May 2012 Cables for the RE4 Upscope in CMS News. The HV cables are in the Integration DB (INB/904) The Hv order is confirmed. Need.
1 hcal installation and commissioning status pawel de barbaro, vitali smirnov, june 11, 2007.
6-Dec-05PC Commissioning1 Peripheral Crate (PC) Commissioning Status Fred Borcherding, CSC/EMU Group.
1 Top Level of CSC DCS UI 2nd PRIORITY ERRORS 3rd PRIORITY ERRORS LV Primary - MaratonsHV Primary 1 st PRIORITY ERRORS CSC_COOLING CSC_GAS CSC – Any Single.
1 04 April 2007 L. Roy Detector Safety System for infrastructure - General fire detection (barracks, cavern) - Sniffer system (smoke detection above the.
Detector Safety System overview DSS is a PLC based system designed to protect ATLAS detector from damages. Front end (hardware) 2 redundant PLC ~700 input.
Cables for the RE4 Upscope in CMS
Integration and Services RE3/1 and RE4/1
Cabling for LHCb Upgrade
Rack Design Proposal as of 01/03/2013
Integration and Services RE3/1 and RE4/1
Operation of CSC DCS Ryan Carroll Carnegie Mellon 29-Sept-2009.
DCS: Temperature Probes
Vito Palladino Straw Working Group 23/3/2015
DCS: Temperature Probes
CMS Area Working Group Meeting
EMU Slice Test Run Plan a working document.
Electrical and electronic systems projects
Chamber Design and Integration RE3/1 and RE4/1
Pierluigi Paolucci - I.N.F.N. Naples
CSC Electronics Installation and Commissioning CSCE I&C
B904 Status Report by Fred B.
TileCal ROD Commissioning Counting Room Installation
B904 Status Report by Fred B.
TPC Detector Control System
UK CMS Oversight Committee Mtg
HV-LV-DCS Status NEWS DCS Endcap Integration
CSC Hot Spares LV Modules (24 units needed) HV Modules Custom Modules
UXC55 ME Muon Endcap On Detector Layout
RPC Detector Control System: towards the final system
Fred’s Input to Rice Workshop
Pierluigi Paolucci & Giovanni Polese
19-April-05 Peripheral Crate Testing, Installation, and Commissioning PC I&C Feb ’06 EMU Fred Borcherding 16-May-19 PC I&C Feb'06.
YE+3 Changes YE+3 X4A51 S4F04 Additions for TS ME+4/2/x chambers
Equipment Management DB Rack Wizard USC55 Underground Counting Room
Rack installation and local tests for the MEBT Chopper Rack
Peripheral Crate Testing, Installation, and Commissioning
Prepared for CSC by Fred Borcherding FNAL
CSC Electronics Installation and Commissioning Oct ‘06
CSC Status Report Status reports;
B904 Status Report by Fred B.
CSC Electronics Installation and Commissioning CSCE I&C
CSC DSS Status Report by Fred B.
19-April-05 CSC ME1/1 Meeting
CSC Hot Spares LV Modules (24 units needed) HV Modules Custom Modules
CSC Electronics Problem Report CSCE I&C
ME I&C -- PC Electronics
Racks PC Rack >> 24 mini and 12 tall PC racks Mini Racks
CSC Shift Training and Operation + B904 Status
Presentation transcript:

Needed for Team A on -End 19-April-05 Needed for Team A on -End Pcrates FO, Fiber Optics Long fibers installed and being tested / measured > ~1 week to complete Need to install jumpers at rack > ~ 1week to complete Install bin covers > install w jumpers Install front covers > ibid Gas > in process HV > in process LV > Being connected – see Petr’s slide Cooling Water Ready for system water Air Turbines – in progress Air ducts – need to finish install Boards Inventory to check db Skew clear cables Some are not connected Protection installed FED crates Missing 9 modules On order ETA unknown Need FO jumpers installed VCC numbers from el db TTC > jumpers installed TF > jumpers installed 11-Nov-19 Commissioning Mtg -- Fred Borcherding

Commissioning Mtg -- Fred Borcherding 19-April-05 Projects (+ and -) Temperature sensors in cavern racks – hardware orders being collected by CMS LV Racks Sensor in inpt and output manifold of each cavern Maraton rack Sensor just above each Maraton crate Sensors in S4F04 rack also HV Racks – shares rack with LV Two sensors within rack below HE Pcrate Racks Sensor on input and output manifold or hose connection for mini-racks Sensor above each pcrate Disk and tower water flow and temperature > CMS responsibility? 24/7 operation >> can we go to 24/7 by start of CROT? DSS Work in progress +End close to Ready Electrical safety approval Petr is working on this CSC group approval > what is our criteria for unattended operation? DCS Monitoring? Alarms? What is status of +End? Duty shifters / on-call experts / remote people? Close all racks for airflow and protection Mini-racks materal on hand > fnish installation Tall tower racks > Some installed, need to design, procure and install remainder 11-Nov-19 Commissioning Mtg -- Fred Borcherding