Latest Project Mthatha Airport Temporary Terminal Building
Temporary Terminal Building Mthatha Airport Customer – Eastern Cape Department of Roads and Transport Commissioned as a temporary structure to operate as terminal building while main building is being refurbished 110mm Panel Technology, rational design approved 1000m² Structure, fully serviced Start date 20 Nov 2009 Practical completion certificate 03 Feb 2010 8 week build date Was supposed to be up for 9 months Customer so happy with structure, thoughts have changed for the structure to be up for a 3 year period, perhaps permanently Two more terminal buildings now being quoted for same customer