Lafayette Airport Commission New Terminal Program Update September 11, 2019
Terminal Program Update Funding FAA Grants announced for terminal building and airside Upcoming grant award $10.5M for taxiway upgrade LA DOTD Currently managing grants Meeting to finalize CIP LA FP&C Coordinating with FP&C on bid packages for terminal construction FP&C currently reviewing design packages Terminal Program Update Funding
Terminal Program Update Funding EDA Grant Application $2M grant announced for long and short-term parking lots TSA OTA Application Submitted Grant Application, unfunded in 2019 Airlines Working with airlines to discuss leasable space QTA/Ready Return Met with rental car agencies on construction progress to date. Upcoming meetings regarding rates and charges Concessions Terminal Program Update Funding
Terminal Program Update Funding Grant Funding Summary Terminal Program Update Funding
Terminal Program Update Projects QTA Rental Car Quick Turn Around Facility (QTA) Construction: Notice to Proceed (NTP) 4/15/19; Scheduled Completion Q1 2020 Upcoming Construction Activities Masonry block work, electrical, retaining wall Terminal Program Update Projects QTA
Terminal Program Update Projects QTA Rental Car Quick Turn Around Facility (QTA) Construction: Terminal Program Update Projects QTA Last Month Current
Terminal Program Update CMAR Projects Description GMP Actual Start Planned Subst. Comp. Project 1 - RTR Cable Relocation 1 Nov. 2018 Apr. 2019 (actual) Project 2 – RTR Facility May 2019 (actual) Project 3 – Terminal Building Foundations and Underground Utilities 1, 4 Jan. 2019 Jun. 2019 (actual) Structural Steel/Elevators/Escalators 2 Jul. 2019 Nov. 2019 Building Shell, MEP and Finishes 5, 6 Nov. 2019 (planned) Q3/Q4 2022 Project 4 – Airside Improvements TBD Project 5 – Enabling Parking Nov. 2018 (planned) Jul. 2019 (actual) Project 6 – Terminal Civil 4 - 6 Jun. 2019 Terminal Program Update CMAR Projects
Project 2 RTR Facility Project 2 – RTR Facility Substantially complete – punch list items completed Project 2 RTR Facility
Project 3 Terminal Building Airside – Concourse Area
Project 3 Terminal Building Steel erection and steel decking – ongoing Project 3 Terminal Building
New Terminal Program Day 271 Day 301
New Terminal Program Steel and Deck Erection Deck 2 Deck Roof Slab 2
New Terminal Program 1 year perspective from the ground breaking ceremony
Project 5 Enabling Parking Final Acceptance Project 5 Enabling Parking
Project 6 Terminal Site Civil Underground utilities – ongoing Loop Road - ongoing Project 6 Terminal Site Civil
Terminal Program Update FP&C Projects Group 1 Description Planned Start Planned Subst. Comp. Package 1 – Audio Visual Q1 2020 TBD Package 3 – Generator Equipment Package 4 – Jet Bridges Package 8 – Bag System Package 10 – Technology
Terminal Program Update FP&C Projects Group 2 Description Planned Start Planned Subst. Comp. Package 2 – Parking Lot Canopy TBD Package 5 – Terminal Building Demo Package 6 – Triturator Package 7 – Furniture Package 9 – Signage