|Datum kernfysisch versneller instituut bestuur 1 Octopus V3 Michel Hevinga Oscar Kuiken Peter Schakel Remco Terol Ad van den Berg Ronald van Wooning KVI – Center for Advanced Radiation Technology Datum
|Datum kernfysisch versneller instituut bestuur Status ›7 boards produced and tested, OK ›agreement with sub contractor Neways for production at about 75 € pp ›issues: pins for the connectors to the PMTs have two different hole sizes; need to adapt the PCB 2 KVI – Center for Advanced Radiation Technology Datum Datum
|Datum kernfysisch versneller instituut bestuur Stress analysis ›Excel sheet as draft submitted to Stefane ›At this moment according to the current BOM ›Need more info: voltage range from the power board PMT specs 3 Datum
|Datum kernfysisch versneller instituut bestuur Planning 50 pre-serie 4 Datum