Statewide Interoperable Radio Communications Internet Transport System (SIRCITS) to the Project Certification Committee Mike Neitzey, Program Manager Department.

Slides:



Advertisements
Similar presentations
Accredited Supplier Communications Plan FY09-10 Q1 to Q4 May 2009, v2.0 Home Access Marketing & Stakeholder Engagement Team.
Advertisements

Feichter_DPG-SYKL03_Bild-01. Feichter_DPG-SYKL03_Bild-02.
1 Copyright © 2013 Elsevier Inc. All rights reserved. Appendix 01.
1 Copyright © 2013 Elsevier Inc. All rights reserved. Chapter 28.
1 Copyright © 2013 Elsevier Inc. All rights reserved. Chapter 38.
Chapter 1 Image Slides Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
Doc.: IEEE 802 EC-12/0007r0 Submission March 2012 Jon Rosdahl, CSRSlide 1 Executive Secretary Agenda Items March 2012 Date: Authors:
Inter-American Commission on Human Rights Budget Proposal 2013 Presentation before the Committee on Administrative and Budgetary Affairs October 5, 2012.
New Jersey Election Law Enforcement Commission Pay-to-Play January 2013.
Jeopardy Q 1 Q 6 Q 11 Q 16 Q 21 Q 2 Q 7 Q 12 Q 17 Q 22 Q 3 Q 8 Q 13
1 CREATING AN ADMINISTRATIVE DRAW REQUEST (HBA) Complete a Checklist for Administrative Draw Requests (Form 16.08). Draw Requests amount must agree with.
1 CREATING AN ADMINISTRATIVE DRAW REQUEST (OCC) Complete a Checklist for Administrative Draw Requests (Form 16.08). Draw Requests amount must agree with.
Critical Approval Commissioner/ State Board of Education Commissioner/ State Board of Education Concept Conference s Concept Review Review and Approval.
School Board Approved Budget: FY Submitted to Board of Supervisors for Approval Rockingham County Public Schools March 28, 2012 Slide 2.
1 Solicitations/Advertisements Solicitations/Advertisements
SUBTRACTING INTEGERS 1. CHANGE THE SUBTRACTION SIGN TO ADDITION
MULT. INTEGERS 1. IF THE SIGNS ARE THE SAME THE ANSWER IS POSITIVE 2. IF THE SIGNS ARE DIFFERENT THE ANSWER IS NEGATIVE.
Addition Facts
Perry Points of Pride... Creating the New Perry Way Attractive 1. Become Attractive To All Community 2. Build Community Spirit Identity 3. Establish Our.
Budget Public Hearing and Budget Adoption Ralph Fortunato Director of Fiscal Services August 28, 2013.
Woodbridge High School Woodbridge School District Design Development for Woodbridge High School 22 May 2012.
SUPPLEMENTAL LEVY ELECTION TUESDAY, MAY 17, 2011 Joint School District No. 2.
BREAKOUT SESSION 2 Smart Grid 2-B: Grid Integration – Essential Step for Optimization of Resources Integrating Intermittent Wind Generation into an Island.
Break Time Remaining 10:00.
This module: Telling the time
Grant Management Seminar 1 District 5180 Club Certification & Grant Management Seminar.
Human Capital Investment Programme Disability Activation Project (DACT) WELCOME Support Workshop Thursday 7 th February
Office of Operations 2010 Fall Conference State Agency Compliance with Prompt Contracting Regulation Dan Agosto, John Moriarty & Patricia ODonnell.
PP Test Review Sections 6-1 to 6-6
6/26/ Virtual Town Hall Meeting June 26, 2013 Announcements & Updates to Policy Changes Karen Wong, Director Public Safety Communications Office.
University Park Elementary School Solar Project
VOORBLAD.
State and Local Implementation Grant Program to the Project Certification Committee Jacque Miller Mike Neitzey October 23, 2014.
Statewide Interoperable Radio Communications Internet Transport System (SIRCITS) to the Project Certification Committee Mike Neitzey, Program Manager Department.
15. Oktober Oktober Oktober 2012.
Copyright © 2012, Elsevier Inc. All rights Reserved. 1 Chapter 7 Modeling Structure with Blocks.
1..
1 ASPEN-SBM (State Based Marketplace) Project Certification February 19, 2014.
© 2012 National Heart Foundation of Australia. Slide 2.
Adding Up In Chunks.
FAFSA on the Web Preview Presentation December 2013.
SLP – Endless Possibilities What can SLP do for your school? Everything you need to know about SLP – past, present and future.
Strategy Review Meeting Strategy Review Meeting
Benjamin Banneker Charter Academy of Technology Making AYP Benjamin Banneker Charter Academy of Technology Making AYP.
7/16/08 1 New Mexico’s Indicator-based Information System for Public Health Data (NM-IBIS) Community Health Assessment Training July 16, 2008.
Addition 1’s to 20.
Unemployment Insurance UI Tax Project Certification Change Request Department of Workforce Solutions Presentation to Project Certification Committee June.
Unemployment Insurance UI Tax Project Certification Department of Workforce Solutions Presentation to Project Certification Committee December 16, 2009.
: 3 00.
5 minutes.
Week 1.
Regional Online Permitting Program. Overview Background and History Benefits Modules Offered Member Towns How to Join.
Woodbridge High School Woodbridge School District Schematic Design for Woodbridge High School 17 January 2012.
Clock will move after 1 minute
Solanco School District Preliminary Budget April 28, 2014.
1 Unit 1 Kinematics Chapter 1 Day
PSSA Preparation.
1 June 13, 2013YMPO RTP Technical Advisory Committee Meeting.
Select a time to count down from the clock above
August 2008 DOE Uranium Leasing Program 2008 Overview August 14, 2008 Steven R. Schiesswohl, Project Manager U.S. Department of Energy Office of Legacy.
Murach’s OS/390 and z/OS JCLChapter 16, Slide 1 © 2002, Mike Murach & Associates, Inc.
 Created by City Council in October Original purpose of the fund: To support housing opportunities for workforce families. $600,000 fund.  On.
Local Housing Assistance Plan Amendment State Fiscal Years Board of County Commissioners August 5, 2014.
Established in 1974 Service Area of 1,200 Square Miles Population of 440,000 People We Answer 700,000 Calls for Service Each Year 3 rd Largest PSAP in.
Statewide Interoperable Radio Communications Internet Transport System (SIRCITS) to the Project Certification Committee Mike Neitzey, Program Manager.
Presentation transcript:

Statewide Interoperable Radio Communications Internet Transport System (SIRCITS) to the Project Certification Committee Mike Neitzey, Program Manager Department of Information Technology August 28, 2013

Project History SIRCITS grant was awarded in August 2010 Received approval to add 9 sites to the DMW project September 2011 Contracts issued, began design phase November 2011 Environmental Assessment FONSI issued December 2011 Contract amendments for construction executed April 2012 LTE suspended May 2012 FirstNet Board established September 2012 Extension request submitted May 2013 Received an extension to September 30, 2013 to negotiate a Spectrum Management Lease Agreement (SMLA) with First Net Signed the SMLA on August xx, 2013 Submitted a request to extend the project to 2015 (final date to be determined, but no later than September 30 th ) Submitted a letter requesting that the suspension of funds be lifted in order to complete the 700MHz LTE phase of the project

Budget Status Budget allocated  Total - $55,700,000 Federal BTOP - $38,699,997 State Matching - $5,399,999 State In-Kind Matching $11,600,004 Budget status  Budget amendment moving $4,734,501 from LTE to DMW was approved  Total LTE Budget - $4,006,500 LTE equipment and build - $2,952,500 (suspended) Design - $1,054,000 (suspended)  New fund established due to expiration of the Budget Reference Code, new PO’s have been/are being approved

Budget Status Budget expenditures for quarter ending 06/30/2013 $3,442,398 Budget expended  As of 06/30/13 - $32,807,381 (cash) + $11,600,004 (in kind match) Total $44,407,385  Over $3,321,627 spent on design, planning, equipment, and construction during the quarter Area Budget Expended to date Remaining EncumberedUnallocated DMW $37, ,251,214.81$0.00$6,073, LTE $4,006,500.00$0.00 $4,006, Other Admin $14,309,003.00$12,542,065.46$$0.00$1,212, Total $55,700,000.00$44,407, $11,292,614.67

Budget Status What have we done?  Towers2,376,245  Shelters2,037,912  Generators527,856  Network4,792,240  Antennas3,403,700  Radios5,218,878  Batteries1,161,284  Construction7,090,686

DMW Status Design - Feasibility analysis, RF design, and Construction design were completed for all Sites Construction – Completed at 24 sites, nearly completed at 3 sites and soon to start at 2 sites Radios, antennas, waveguides and routers have been installed at over 60 sites Over 900 network miles are in production Installation & implementation are expected to be completed by the end of Q4CY13

LTE Status LTE Border Operations Project Briefed to FirstNet in December 2012 Up to 7 State sites and 2 Federal sites to be established (final selection will be based on Spectrum Analysis results, System Requirements, and System Design Use State DMW and Fiber backhaul Establish MOUs with Federal agencies Establish MOU with Texas to connect to Harris County LTE core

LTE Status SMLA with FirstNet has been signed Suspension lift and project extension requests have been submitted Starting to develop MOUs with Federal agencies and Texas

LTE Plan Design contract10/01/13-01/17/14 System Design01/20/14-04/11/14 700MHz LTE RFP03/24/14-08/08/14 Build & Implementation Contract08/11/14-10/14/14 B&I process11/12/14-03/03/15 System Integration Test03/04/15-08/18/15 Operational turnover08/19/15-09/30/15

Risk & Issues Weather and Fire restrictions continue to play a role in upgrade delays, but has been minimal at this time USFS Santa Fe insurance requirements has delayed the permitting process on 2 sites Demolition is now included as part of budget; Priority for State Land Office and BLM sites No funding for Purchase/move of LMR equipment (separate $1.5M funding)

Thank You……. Questions?