Incorporating New Transmission Projects in the New York ICAP Market New York ICAP Working Group September 24, 2001 Frank A. Felder on behalf of TransÉnergie.

Slides:



Advertisements
Similar presentations
The Single Electricity Market in Ireland
Advertisements

1 TREATMENT OF CROSS- SOUND CABLE Installed Capacity Stakeholder Process Working Group Long Island Power Authority Proposal May 11, 2006.
Probabilistic Volatility in the Western Interconnection Matthew Elkins.
Guidelines for Good Practice on Information Management and Transparency EuroPEX Comments and Suggestions Brussels, 6 th of July 2006.
Demand Response in the Reliability Pricing Model Chuck Whitlock.
Energy and Telecommunications Interim Committee January 29, 2004.
Commonwealth Utilities Corporation Alan W. Fletcher Executive Director.
1 July 15, 2007Alcoa Energy Regulatory Affairs NARUC / FERC Demand Response Collaborative Perspectives of a Large End Use Participant of NYISO Programs.
Overview of Loss of Load Expectation (LOLE) and Unforced Capacity (UCAP) Dan Huffman FirstEnergy Solutions November 20, 2007 OMS Board Workshop Resource.
NARUC-FERC Demand Response Collaborative Meeting NARUC Fall Meeting Anaheim, CA T. Graham Edwards President & CEO November 11, 2007.
Forecasts and Assessments Presented to the Independent Power Producers’ Society of Ontario Pat Doran, Supervising Technical Officer Independent Electricity.
Utility Regulation March 10, 2011 Raj Addepalli Deputy Director, Electric, Office of Electric,Gas and Water New York State Department of Public Service.
Market Overview in Electric Power Systems Market Structure and Operation Introduction Market Overview Market Overview in Electric Power Systems Mohammad.
Ludington Pumped Storage Plant and Wind Power Operational Considerations David Lapinski Consumers Energy Company June 16, 2009.
Regulatory Flexibility Committee Competitive Procurement September 18 th Joe Kerecman Director Government and Regulatory Affairs
Electric Generation Reliability Remarks Before the Pennsylvania Public Utility Commission 2011 Summer Reliability Assessment Meeting June.
PacifiCorp Participation in the California ISO. 2 Full participation provides significant benefits beyond those of the Energy Imbalance Market EIM BenefitsFull.
Welcome New York Independent System Operator. (Pre-NYISO) Regulated Market Physical contracts Regulated industry Cost Based System Two Party Deals Bundled.
2006 Reliability Study Scope Name Date. DRAFT 2 Purpose of Study Assess the PEC and Duke transmission systems’ reliability Develop a single reliability.
Energy Action Plan “Report Card” and the AB32 “Umbrella” CFEE ROUNDTABLE CONFERENCE ON ENERGY Julie Fitch California Public Utilities Commission Director.
Demand Response in Midwest ISO Markets February 17, 2008.
© 2001 Utility Management Consulting, Inc. All Rights Reserved Distributed Resources Interconnection Policies: A Report to EEI Members Presentation of.
Power Plant BI POWER GENERATION Evolution of Plant Ownership From Regulated Era Regulated Utility Monopolies To “Partially” Deregulated Era Independent.
OSC Meeting April 27, Transmission Cost Allocation Overview.
The Regulatory Assistance Project 177 Water St. Gardiner, Maine USA Tel: Fax: State Street, Suite 3 Montpelier, Vermont.
1 Planning Reserve Margin Dan Egolf Senior Manager, Power Supply & Planning.
MICROECONOMICS: Theory & Applications By Edgar K. Browning & Mark A. Zupan John Wiley & Sons, Inc. 10 th Edition, Copyright 2009 PowerPoint prepared by.
“Demand Response: Completing the Link Between Wholesale and Retail Pricing” Paul Crumrine Director, Regulatory Strategies & Services Institute for Regulatory.
Demand Response Workshop September 15, Definitions are important Demand response –“Changes in electricity usage by end-use customers from their.
Enhancing Reliability of the North American Transmission Grid Enhancing Reliability of the North American Transmission Grid Presented By Dejan J Sobajic.
ERCOT Generation Adequacy Study TAC Meeting February 7, 2002.
SM April Peak Week Operations Review Presentation to ISO Business Issues Committee May 22, 2002.
Study Unit 9 Decision Analysis and Risk Management.
DISTRIBUTED GENERATION, RENEWABLE ENERGY AND SUSTAINABILITY. IMPACT ON POWER QUALITY AND NETWORK PLANNING “Inauguration of the 6th Framework Programme”
RGGI Workshop on Electricity Markets, Reliability and Planning Topic Session 3: RGGI Design, Markets and Reliability – Issues Relating to System Operations.
Demand Response as Capacity in New York National Association of Regulatory Utility Commissioners Winter Committee Meetings Washington, DC February 17,
Electric Reliability Council of Texas (ERCOT) A Success Story… In Progress Ingmar Sterzing United States Association of Energy Economics (USAEE) Pittsburgh.
SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX.
Utility Procurement: What’s Next? IEP 2015 Annual Conference
Electric Capacity Market Performance with Generation Investment and Renewables Cynthia Bothwell Benjamin Hobbs Johns Hopkins University Work Supported.
Updated 1/28/2011. Renewables Integration Plans and Challenges March 8, 2011 Jay Caspary ·
2nd Workshop on PGI in NEA, May , Shenzhen, China 1 “RFE-NEC-DPRK-RK” POWER GRID INTERCONNECTION Sergei Podkovalnikov Energy Systems Institute,
PacifiCorp & CAISO Regional Transmission Organization Presented by Scott Gutting President, Energy Strategies, LLC Independent Energy Producers Annual.
SPP.org 1. Status Update: Retail Open Access for ETI within SPP Stakeholder Meeting June 20 th, 2008 Austin, TX.
Business Case NPRR 351 Floyd Trefny Amtec Consulting Brenda Crockett Champion Energy Services.
Transmission arrangements for distributed generation DCMF 9 April 2008 Pre consultation document.
Planning for Texas’ Energy Future Select Committee on Electric Generation Capacity and Environmental Effects Bob Kahn President & CEO February 6, 2008.
Update on the North Carolina Transmission Planning Collaborative January 30, 2007 For the North Carolina Utilities Commission and the North Carolina Public.
Proposed framework for charges for generators connected to the Distribution network Please note that the contents of this presentation are proposals at.
PJM©2014www.pjm.com A System Operator’s Resilience Wish List Tom Bowe Executive Director Reliability and Compliance PJM Interconnection
PacifiCorp and CAISO Expanding Regional Energy Partnerships
Capacity, Demand and Reserves Report Bill Bojorquez Board of Directors Meeting May 16, 2007.
The RGGI Auction Allocation Process: Concerns and Recommendations Presented by James H. Savitt, Ph.D To The RFF Auction Workshop in NYC 20 July 2006.
Transmission Pricing Webinar 12 October Agenda for Webinar Introductions Purpose Potential Areas of Change – Overview –Revenue Proposal –Business.
©2003 PJM 1 Presentation to: Maryland Public Service Commission May 16, 2003.
BGE Smart Grid Initiative Stakeholder Meeting September 17, 2009 Wayne Harbaugh, Vice President, Pricing and Regulatory Services.
Overview of the NYISO Demand Response Programs
ERCOT – Southern Cross Transmission ROS/WMS Working Group Assignments
Regional Transmission Organizations
Benefits of ICAP Reliability Economics
Transmission: the Critical Link
Evolving Economic Dispatch in SPP
The Need for Compensatory Standby Rates
Transmission As Enabler
New England Resource Adequacy
Alternative ICAP Proposal
INTERCONNECTED SYSTEM GENERATING CAPACITY RELIABILITY EVALUATION
NYS Department of Public Service
Probabilistic Volatility in the Western Interconnection
Planning Reserve Margin
Presentation transcript:

Incorporating New Transmission Projects in the New York ICAP Market New York ICAP Working Group September 24, 2001 Frank A. Felder on behalf of TransÉnergie US Ltd September 24, 2001

Frank A. Felder, Independent Consultants 2 Presentation Summary Current NYISO rules do not permit new transmission projects from receiving ICAP credit New transmission projects reduce the need for installed reserve margins (IRM) Not allocating ICAP credit to new transmission projects reduces reliability, increases costs to consumers, and is discriminatory

Frank A. Felder, Independent Consultants 3 Current NYISO Rules Current NYISO Tariffs do not credit new transmission projects with the associated reduction in installed reserve margin (IRM) that these projects create –No credit for reduction in overall IRM –No credit for reduction in locational ICAP requirements for applicable projects Recent rule changes more accurately reflect the ICAP value that different resources provide –Change from ICAP to UCAP –Expanded participation by small generator and load management resources in the ICAP market

Frank A. Felder, Independent Consultants 4 New Transmission Projects Reduce the Installed Reserve Margins The adequacy of the generating capacity in a power system is normally improved by interconnecting the system to another power system. Each interconnected system can then operate at a given risk level with a lower reserve than would be required without the interconnection. This condition is brought about by the diversity in the probabilistic occurrence of load and capacity outages in the different systems. The actual interconnection benefits depend on the installed capacity in each system, the total tie capacity, the forced outage rates of the tie lines, the load levels and their residual uncertainties in each system and the type of agreement in existence between the systems. Roy Billinton and Ronald N. Allan, Reliability Evaluation of Power Systems (2nd Edition), p. 117.

Frank A. Felder, Independent Consultants 5 New Transmission Projects Reduce the Installed Reserve Margins - Examples Between Control Areas Within a Control Area Within a Control Area and Between ICAP Subzones #1 #2 #3 Key Transmission line Control Area Subzone boundary

Frank A. Felder, Independent Consultants 6 New Transmission Projects Reduce Installed Reserve Margins Even if loads in the two connecting areas are perfectly correlated, new transmission projects reduce IRM due to the largely independent outages of generation units in both areas Connecting an area with excess generation to an area short of generation reduces the IRM in both areas (i.e., reliability benefits do not flow only in the direction of power flows) In general, transmission projects have larger availabilities than generation projects

Frank A. Felder, Independent Consultants 7 New Transmission Projects Should Receive Appropriate ICAP Credit Granting ICAP credit to transmission enhances reliability and reduces customer costs –Transmission projects may provide greater reliability benefits than similarly situated generation projects and could be less expensive –Granting ICAP credit only to generation projects makes generation more attractive to investors than transmission projects, irrespective of which alternative provides the lowest cost –As a result, the additional reliability benefits and potential cost reductions of transmission projects will not occur

Frank A. Felder, Independent Consultants 8 New Transmission Projects Should Receive Appropriate ICAP Credit (cont) Granting ICAP credit to transmission places all solutions on equal footing –Non discriminatory treatment allows all solutions -- generation, distributed generation, load management initiatives, and transmission projects -- to compete to provide consumers with inexpensive delivered electricity –Non discriminatory treatment allows all solutions to be fairly compensated for the reliability value that each provides