LHC Cryogenics Status and Perspectives

Slides:



Advertisements
Similar presentations
VELO Module PRR preparation meeting28-feb-2006 LiverpoolMassimiliano Ferro-Luzzi 1 Introduction VELO overview Overall planning A bit of (recent) history.
Advertisements

The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Cryogenic system in P4: Possible options S. Claudet & U. Wagner LHC Workshop, “Chamonix XlV” January 2005 (Mostly for RF & beam scrubbing)
Going towards LHC Run2 CRYOGENICS 5 th Evian Workshop 2-4 June 2014 SESSION 4 - Systems 2 - Status and commissioning plans (HW perspective) Krzysztof Brodzinski.
The Use of Small Coolers for Hydrogen and Helium Liquefaction
SC - 04Feb'13Cryo Heaters Review Cryogenic Heaters Review Operation use and wishes S. Claudet - A. Suraci LHC Cryogenic Operation.
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab Roy Preece Rutherford Appleton Lab October 28, 2011 MICE Collaboration Meeting.
LHC Experimental Areas Forum - 03/07/ ATLAS Helium Cryogenics Nicolas Delruelle on behalf of the AT / ECR group.
Large-capacity Helium refrigeration : from state-of-the-art towards FCC reference solutions Francois Millet – March 2015.
LHC Machine Status Report Roberto Saban LHCC June 4 th 2014.
CRYOGENICS AND POWERING
HC review - 12 May 2005Luigi SERIO - AT/ACR/OP1 SECTOR COOL DOWN AND CRYOGENIC COMMISSIONING L. Serio.
Workshop Chamonix XIV Shortcuts during installation and commissioning: risk and benefit H. Gruehagen, G. Riddone on behalf of the AT/ACR group 18 January.
LHC Cryogenics: “From cool-down & HWC to operation with beam” S. Claudet, for LHC cryogenics Extended LTC, 3 Mar’08.
Introduction to LHC cryogenic system (layout, architecture) Preparation before cool-down (Purge, flushing) Transient operations to reach nominal operating.
1 Second LHC Splice Review Copper Stabilizer Continuity Measurement possible QC tool for consolidated splices H. Thiesen 28 November 2011 K. Brodzinski,
11/07/20071 Hardware Commissioning Forum: DFBs R. Rabehl AT-ACR.
Arnaud Vande Craen (TE-MSC) 27/02/20131 EUCARD : ESAC Review – CEA Saclay.
Cryogenics in SPS & LHC (2 K / 4.5 K) LHC-CC11, 14 November 2011 L. Tavian, CERN, TE-CRG With the contribution of N. Delruelle, G. Ferlin & B. Vullierme.
Cryogenic update before Fermilab meeting (and after the helium tank review) Coordination meeting 6 th May 2015 K. Brodzinski HiLumi-LHC-CC-Cryo-PPT-18_v1.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
S. Claudet - 31st May 2007Power refrigeration for LHC Power refrigeration at 4.5K & 1.8K for the LHC S. Claudet, CERN AT-ACR.
HC review, A. Perin, 12-MAY DFB Project LHC hardware commissioning review May 2005 Hardware commissioning of the DFBs and DSLs and connection.
LHC Cryogenics HWC day 19 March 2009 Serge Claudet TE-CRG-OA (LHC Cryo OP)
Process Definition of the Operation Modes for Super-FRS Magnet Testing CSCY - CrYogenic department in Common System, GSI, Darmstadt Y. Xiang, F. Wamers.
8 th November 07-OP Workshop Machine Checkout E. VEYRUNES CRYOGENICS 8 th November 2007 OP Workshop Machine Checkout E. VEYRUNES AB/OP 2008 AB/OP CRYO.
Luigi Serio CRYOGENICS PERFORMANCE AND OPERATION L. Serio, on behalf of the LHC Cryogenics Operation and Cryogenics Performance Panel.
Commissioning of REX Jose Alberto Rodriguez, BE-OP-PSB (167538) on behalf of the ISOLDE operations team.
LHC Cryogenics for sector 45 and Perspectives S. Claudet, for LHC cryogenics HWC Review, 28 Fev’08.
Cryogenics for crab cavities – SPS/LHC 2 nd HiLumi LHC meeting – Frascati (Italy) 15 November 2012 K. Brodzinski and L. Tavian on behalf of cryogenic team.
[R. Alemany] [CERN AB/OP] [Engineer In Charge of LHC] HWC Workshop ( ) Consolidation and major changes that have impact on the powering circuits.
4 December 2007Sylvain Weisz - LEMIC1 Status of LHC installation.
CHAMONIX XV QRL installation and first experiences of operation G. Riddone on behalf of the QRL team AT/ACR-cd Acknowledgements to AT/ACR-op and AT/ACR-in.
Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project.
Can we change a magnet without warming-up a full arc ? Serge Claudet, With help from P. Cruikshank & J-P. Tock (Chamonix Jan’10)
D. Delikaris, TE-CRG, LSC 25th Meeting Page 2 October 18 th, 2013 LS1 Committee (LSC)- 25 th Meeting D. Delikaris, TE-CRG Cryogenics activities.
Cryogenic Summary - K. C. Wu Testing D2L102 in MAGCOOLJune, 02 Difference between D2L102 and D2L101 Operating Summary Cooldown to 100 K and 6 K Test Condition.
TE-CRG Activities D. Delikaris, TE-CRG.
MPP Meeting 07/03/2007 MPP Main Ring Magnet Performance Panel Meeting Wednesday 7th March 2007 Agenda: 1)Matters arising 2)Recommendations for the case.
LHC Machine Advisory Committee Meeting no.19 QRL status 16 June 2006 G. Riddone, AT-ACR On behalf of the QRL team.
Cooling Circuit Design Steve Virostek Lawrence Berkeley National Lab February 29, 2012 MICE Coupling Coil Cryostat Design Review Lawrence Berkeley National.
A. Perin TE-CRG, 06 April LMC 08 April 2009 Consolidations related to pressure protection on DFBs and DSLs A. Perin, TE-CRG.
5-year operation experience with the 1.8 K refrigeration units of the LHC cryogenic system G. Ferlin, CERN Technology department Presented at CEC 2015.
LHC Cryogenics From cool-down to 1st beams Serge Claudet (LHC Cryo OP), On behalf of cryo teams involved.
LHC Cryogenics, equipment & interventions around P3/P7 S. Claudet, “volunteer” for TE_CRG 16 Oct’14.
Workshop on cryogenic & vacuum sectorisation of the SPL Vacuum Sectorisation Paul Cruikshank, CERN Technology Department (TE) Vacuum Surfaces & Coatings.
The Large Hadron Collider The 19 th Sep 2008 incident [R. Alemany] [CERN AB/OP] [Engineer In Charge of LHC] NIKHEF Seminar ( )
Development of Cryo-Module Test Stand (CMTS) for Fermi Lab (R.L.Suthar, Head,CDM, BARC) Cryo-Module Test stand (CMTS) is a very sophisticated equipment.
Training LHC Powering – Blanca Perea Solano From Individual System Tests to Powering to Nominal Blanca Perea on behalf of Hardware Commissioning Coordination.
ESS Cryomodule Status Meeting – Introduction | | Christine Darve Introduction to Cryomodules for the ESS 2013 January, 9 th Christine Darve.
WP10 General Meeting, Giovanni Volpini, CERN 1 December 2015 Test progress INFN 1.
S A Griffiths CM42 June 2015 Electrical & Control.
Roadmap for triplet cryostats
IT-4189 Supply and installation of a cryogenic distribution system
Status of LHC installation & New Installation Schedule
on behalf of the RF group
The LHC - Status Is COLD Is almost fully commissioned
LS1 Committee January 24th, 2014
CRYOGENICS – strategy, unavailability root causes and limitations
Coordination of Hardware Commissioning
Hollow e- lens, Cryogenic aspects
Status of the cryogenic system for B180
Status of the BLHC ….work in progress! Mike Lamont CERN/AB 18/01/2008
TEST PLANS for HL LHC IT STRING
CTF Users’ Perspective
HiLumi P1/P5, Cryogenic interfaces for sc links, DFX 2nd review
Guidelines defined early Dec 2012
Conceptual design of the Cryogenic System of Comprehensive Research Facility for Key Fusion Reactor Core Systems Liangbing Hu Sep.4.
Cryogenic management of the LHC Run 2 dynamic heat loads
J. Fleiter, S. C. Hopkins, A. Ballarino
Presentation transcript:

LHC Cryogenics Status and Perspectives Serge Claudet, on behalf of the LHC Cryogenics group LHC - MAC22 05 Dec 2007

Content Introduction Main facts from sector 7-8 (January to July 2007) Last projects towards completion Identified weak points (@MAC21) and status Cryo HWC activities since Mid 2007 Action plans Summary S. Claudet - 06Dec'07 LHC-MAC22 - Cryogenics

S. Claudet - 06Dec'07 LHC-MAC22 - Cryogenics

LHC Sector 4-5 scheme 4.5 K 1.9 K 3.3 km 4’700 t @ 1.9K ≈ 10t/15tHe S. Claudet - 06Dec'07 LHC-MAC22 - Cryogenics

Content Introduction Main facts from sector 7-8 (January to July 2007) Last projects towards completion Identified weak points (@MAC21) and status Cryo HWC activities since Mid 2007 Action plans Summary S. Claudet - 06Dec'07 LHC-MAC22 - Cryogenics

LHC sector 7-8 - First cool-down S. Claudet - 06Dec'07 LHC-MAC22 - Cryogenics

Availability for HWC: From 7-8 to others Cryo Maintain LSS: 85% (Since 1st May) Cryo Maintain ARC: 66% (Since 1st June) DFBMs DFBAs Availability for the powering phase for sector 7-8 and expected one for the coming sectors Target LSS: 90% (incl. time lost for quench recovery) Target ARC: 80% (incl. time lost for quench recovery) + Cryogenic tuning to be minimised ?!? S. Claudet - 06Dec'07 LHC-MAC22 - Cryogenics

Heat inleaks Average distributed heat inleak at 1.9 K: 0.2 W/m 20 % of cells operating with degraded insulation vacuum Average distributed heat inleak of cells with good vacuum: 0.14 W/m 33 % below the design estimation Average global thermal shield heat inleak: 6.6 W/m 15 % below the design estimation S. Claudet - 06Dec'07 LHC-MAC22 - Cryogenics

LHC Cryogenics: duration of cool-down phases Design LHC 7-8 Final 9 d 21 d 3 d 14 d 1 d 80 K 20 K 4.5 K 1.9 K Total 14 d / 2 wks 70 d / 10 wks ELQA 4 d 7 d 28 d / 4 wks Excluding ELQA or extra-works : Sketches intended to illustrate achievements and medium term expectations S. Claudet - Jul’07 Proposed for schedule: 8wks-6wks-4wks S. Claudet - 06Dec'07 LHC-MAC22 - Cryogenics

Content Introduction Main facts from sector 7-8 (January to July 2007) Last projects towards completion Identified weak points (@MAC21) and status Cryo HWC activities since Mid 2007 Action plans Summary S. Claudet - 06Dec'07 LHC-MAC22 - Cryogenics

Superconducting links (DSL) Few hundred meters link between DFBL’s and stand-alone magnets S. Claudet - 06Dec'07 LHC-MAC22 - Cryogenics

Many non conformities from contractor, repaired by CERN Problems with leaks at the factory-made welds on belows Many non conformities from contractor, repaired by CERN => Impact on sector 3-4 S. Claudet - 06Dec'07 LHC-MAC22 - Cryogenics

Global pressure test of magnets and cryolines Sector 7-8, 25 Nov 2006 Six sectors May’07 to Nov’07 Remaining 1 sector in Dec’07 S. Claudet - 06Dec'07 LHC-MAC22 - Cryogenics

Content Introduction Main facts from sector 7-8 (January to July 2007) Last projects towards completion Identified weak points (@MAC21) and status Cryo HWC activities since Mid 2007 Action plans Summary S. Claudet - 06Dec'07 LHC-MAC22 - Cryogenics

On-going actions & plans @ MAC21 LN2 logistics to be continued; turbine and flow controls to be improved for 20 K phase Heat loads to be further checked and analysed JT valves to be checked and replaced (8x27) LHe level / anti-condensation for DFB’s to be finalised Instrumentation & controls to be available & more reliable Test of specific tool QUI to separate installation/operation Helium inventory & strategy to be confirmed OK, Faster at sector 4-5, to be continued When conditions OK Done for 8 arcs, singularities being treated OK, to be continued OK, to be continued Done, no longer required Defined, to be implemented S. Claudet - 06Dec'07 LHC-MAC22 - Cryogenics

DFB Commissioning: levels and anti-condensation LT836 LT837 LT864 LT865 LT866 LT867 ≈ 5 m S. Claudet - 06Dec'07 LHC-MAC22 - Cryogenics

Dry air protection of 600A chimneys of DFBAH Consolidation of DFBs Protective box Liquid helium level gauges Installation of calibrated level gauges. Installation of a protective box around the level gauges Anti-condensation system 6 kA, 13 kA, 600 A dry air protection: current lead insulating flange + top of chimney flange, connected in series. Interim solution for sector 4-5 120A active heating system + dry air (depending on tests) Configuration of LG 6 kA, 13 kA (322) 600 A (178) 120 A (36) Dry air protection of 600A chimneys of DFBAH LHC-MAC22 - Cryogenics S. Claudet - 06Dec'07

Commissioning DFBs of sector 4-5 IR4R IR5L DFBMK: boil-off cross-check to be finalized DFBML: released for ELQA DFBMG: released for powering DFBAH LCM: liquid level confirmed abnormal behaviour of several control valves for 600A CL DFBAH HCM: liquid level confirmed - abnormal reading of temperature sensors of 13kA CL #1 DFBAI HCM: liquid level cross-checking in progress Liquid level control to be tuned. DFBAI LCM: liquid level confirmed abnormal behaviour of several control valves for 600A CL. Several valves had to be replaced by caps! DFBLD: boil-off performed - Liquid level control to be tuned. LHC-MAC22 - Cryogenics S. Claudet - 06Dec'07

S. Claudet - 06Dec'07 LHC-MAC22 - Cryogenics

Content Introduction Main facts from sector 7-8 (January to July 2007) Last projects towards completion Identified weak points (@MAC21) and status Cryo HWC activities since Mid 2007 Action plans Summary S. Claudet - 06Dec'07 LHC-MAC22 - Cryogenics

Flushing sectors before cool-down Dust Debris Kapton Reports And possible shorts in diodes ! But the sooner the best !!! S. Claudet - 06Dec'07 LHC-MAC22 - Cryogenics

LHC - 1st cool-down sector 4-5 Cool-down stopped twice due to leaks during cool-down P5 P4 Two hoses in DFBA’s became leaky during cool-down 6 weeks stand-by: looks promising S. Claudet - 06Dec'07 LHC-MAC22 - Cryogenics

LHC Sector 4-5: 1st cool-down (2007) Cool-down to 1.9K Cryogenic tuning 1st leak and repair Powering tests 2nd leak and repair S. Claudet - 06Dec'07 LHC-MAC22 - Cryogenics

LHC 45: Cryogenic tuning toward 1.9K With contractor Cryogenic tuning at 1.9K Stops due to external sources Stops due to 1.8K units with small air leak in cold sub-atmospheric circuit Last 4 weeks (6Nov’07 to 5Dec’07) S. Claudet - 06Dec'07 LHC-MAC22 - Cryogenics

Cool-down of other sectors 7-8 & 4-5: 1st cool-down in 2007 5-6: 300K-80K Nov-Dec 2007 Short in diode and repair 7-8 & 8-1: start wk51 for Jan’08 5-6 & 6-7: Restart wk05 2008 And four remaining sectors Feb’08 to Apr’08 S. Claudet - 06Dec'07 LHC-MAC22 - Cryogenics

Content Introduction Main facts from sector 7-8 (January to July 2007) Last projects towards completion Identified weak points (@MAC21) and status Cryo HWC activities since Mid 2007 Action plans Summary S. Claudet - 06Dec'07 LHC-MAC22 - Cryogenics

On-going actions & plans Cool-down process & Heat loads to be further checked and analysed Refrigeration: Ex-LEP upgrade consolidations and 1.8K units Instrumentation & controls to be terminated and consolidated LHe level / anti-condensation for DFB’s to be deployed He guard along sectors to be consolidated Few other consolidations to be evaluated Operation procedures and teams know-how to be re-inforced Strategy for Helium inventory defined, to be implemented S. Claudet - 06Dec'07 LHC-MAC22 - Cryogenics

Summary The LHC cryogenic system is progressively being commissioned, with signs of “learning curve” Consolidation program started (JT valves, DFB’s, controls, helium) and to be continued 2007 has been a difficult year of commissioning, and most likely 2008 will be a difficult year towards the expected first beams and collisions Looking forward to “routine” operation !!! S. Claudet - 06Dec'07 LHC-MAC22 - Cryogenics