Time Series for Oil Facility on East Timbalier Island Aerial Video Survey Program Pontchartrain Institute of Environmental Sciences University of New Orleans Karen A Westphal
The Aerial Video Survey Program has been acquiring photography and video of the northern Gulf of Mexico shoreline since Oblique aerial photography does not produce exact matches due to variations in altitude, camera angle and distance from the shore (and different photographers). Photos that matched well were scaled and aligned to illustrate the landscape changes that have taken place between time periods. Occasionally a pointer or symbol was added to assist with the visual comparison. The Aerial Video Survey Program has been acquiring photography and video of the northern Gulf of Mexico shoreline since Oblique aerial photography does not produce exact matches due to variations in altitude, camera angle and distance from the shore (and different photographers). Photos that matched well were scaled and aligned to illustrate the landscape changes that have taken place between time periods. Occasionally a pointer or symbol was added to assist with the visual comparison.
Location of East Timbalier Island, Louisiana East Timbalier Island is in BICM region “Lafourche Delta” and BICM segment 39 “East Timbalier Island”
July 10, º 04 ’ 44"/90 º 24 ’ 25 ” - View to northeast
July 23, º 04 ’ 44"/90 º 24 ’ 25 ” - View to northeast
July 9, º 04 ’ 44"/90 º 24 ’ 25 ” - View to northeast
July 14, º 04 ’ 44"/90 º 24 ’ 25 ” - View to northeast
June 25, º 04 ’ 44"/90 º 24 ’ 25 ” - View to northeast
July 9, º 04 ’ 44"/90 º 24 ’ 25 ” - View to northeast
June 16, º 04 ’ 44"/90 º 24 ’ 25 ” - View to northeast
July 26, º 04 ’ 44"/90 º 24 ’ 25 ” - View to northeast
August 27, º 04 ’ 44"/90 º 24 ’ 25 ” - View to northeast
October 5, post-Hurricane Lili 29 º 04 ’ 44"/90 º 24 ’ 25 ” - View to northeast
September 13, º 04 ’ 44"/90 º 24 ’ 25 ” - View to northeast
September 30, post-Hurricane Katrina 29 º 04 ’ 44"/90 º 24 ’ 25 ” - View to northeast
February 26, º 04 ’ 44"/90 º 24 ’ 25 ” - View to northeast (42 º )
April 20, º 04 ’ 15"/90 º 17 ’ 13 ” - View to northeast (44 º )
8 Years 1984 1992
10 Years 1992 2002
4 Years 2002 2007
23 Years 1984 2007
Relevant Coastal Restoration Projects East Timbalier Island Sediment Restoration, Phase 1. State Project Number: TE- 25 Project Priority List (PPL): 03 Federal Sponsor: National Marine Fisheries Service (NMFS) Project Type: Barrier Island Construction Completion Date: 2000 Description: The objective of this project is to strengthen and thus increase the life expectancy of East Timbalier Island. The project called for the mining of 890,000 cubic yards of sediment and placement of the material in three embayments along the landward shoreline of East Timbalier Island. The project also included aerial seeding of the dune platform, installation of sand fencing, and dune vegetation plantings have been completed. East Timbalier Island Sediment Restoration, Phase 2. State Project Number: TE- 30 Project Priority List (PPL): 04 Federal Sponsor: National Marine Fisheries Service (NMFS) Project Type: Barrier Island Construction Completion Date: 2000 Description: The project goal is to strengthen and increase the life expectancy of East Timbalier Island by placing dredged material along its landward shoreline. Additional rock has been placed on the existing breakwater in front of the island which will help protect the created area from erosion. East Timbalier Island Sediment Restoration, Phase 1. State Project Number: TE- 25 Project Priority List (PPL): 03 Federal Sponsor: National Marine Fisheries Service (NMFS) Project Type: Barrier Island Construction Completion Date: 2000 Description: The objective of this project is to strengthen and thus increase the life expectancy of East Timbalier Island. The project called for the mining of 890,000 cubic yards of sediment and placement of the material in three embayments along the landward shoreline of East Timbalier Island. The project also included aerial seeding of the dune platform, installation of sand fencing, and dune vegetation plantings have been completed. East Timbalier Island Sediment Restoration, Phase 2. State Project Number: TE- 30 Project Priority List (PPL): 04 Federal Sponsor: National Marine Fisheries Service (NMFS) Project Type: Barrier Island Construction Completion Date: 2000 Description: The project goal is to strengthen and increase the life expectancy of East Timbalier Island by placing dredged material along its landward shoreline. Additional rock has been placed on the existing breakwater in front of the island which will help protect the created area from erosion.