A factory produces two types of drink, an ‘energy’ drink and a ‘refresher’ drink. The day’s output is to be planned. Each drink requires syrup, vitamin supplement and concentrated flavouring, as shown in the table. The last row in the table shows how much of each ingredient is available for the day’s production. How can the factory manager decide how much of each drink to make? THE PROBLEM Linear Programming : Introductory Example
Syrup Vitamin supplement Concentrated flavouring 5 litres of energy drink 1.25 litres2 units30 cc 5 litres of refresher drink 1.25 litres1 unit20 cc Availabilities250 litres300 units4.8 litres Energy drink sells at £1 per litre Refresher drink sells at 80 p per litre THE PROBLEM
Syrup constraint: Let x represent number of litres of energy drink Let y represent number of litres of refresher drink 0.25x y 250 x + y 1000 FORMULATION
Vitamin supplement constraint: Let x represent number of litres of energy drink Let y represent number of litres of refresher drink 0.4x + 0.2y 300 2x + y 1500 FORMULATION
Concentrated flavouring constraint: Let x represent number of litres of energy drink Let y represent number of litres of refresher drink 6x + 4y 4800 3x + 2y 2400 FORMULATION
Objective function: Let x represent number of litres of energy drink Energy drink sells for £1 per litre Let y represent number of litres of refresher drink Refresher drink sells for 80 pence per litre Maximise x + 0.8y FORMULATION
Empty grid to accommodate the 3 inequalities SOLUTION
1 st constraint Draw boundary line: x + y = 1000 xy SOLUTION
1 st constraint Shade out unwanted region: x + y 1000 SOLUTION
Empty grid to accommodate the 3 inequalities SOLUTION
2 nd constraint Draw boundary line: 2x + y = 1500 xy SOLUTION
2 nd constraint Shade out unwanted region: 2x + y 1500 SOLUTION
Empty grid to accommodate the 3 inequalities SOLUTION
3 rd constraint Draw boundary line: 3x + 2y = 2400 xy SOLUTION
3 rd constraint Shade out unwanted region: 3x + 2y 2400 SOLUTION
All three constraints: First: x + y 1000 SOLUTION
All three constraints: First: x + y 1000 Second: 2x + y 1500 SOLUTION
All three constraints: First: x + y 1000 Second: 2x + y 1500 Third: 3x + 2y 2400 SOLUTION
All three constraints: First: x + y 1000 Second: 2x + y 1500 Third: 3x + 2y 2400 Adding: x 0 and y 0 SOLUTION
Feasible region is the unshaded area and satisfies: x + y x + y x + 2y 2400 x 0 and y 0 SOLUTION
Evaluate the objective function x + 0.8y at vertices of the feasible region: O: = 0 A: x 1000 = 800 B: x 600 = 880 C: x 300 = 840 D: = 750 O A B C D Maximum income = £800 at (400, 600) SOLUTION