October 28 th, 2013. Hwy 97 – Carson to Fox Mountain Road Four Lanning  Review Project Scope Problem Definition Objectives  Summary of Work Completed.

Slides:



Advertisements
Similar presentations
Syracuse City Council March 8, EIS Process & Schedule.
Advertisements

Reston Metrorail Access Group (RMAG) Status Report Board of Supervisors Transportation Committee September 20, 2011.
Some things cant wait for traffic Capital Beltway HOT Lanes Project New Travel Choices Ahead.
Reston Metrorail Access Group (RMAG) Status Report Board of Supervisors Transportation Committee November 29, 2011.
IntelliDrive for Safety, Mobility, and User Fee Project Cory Johnson Mn/DOT IntelliDrive Program Engineer.
US101: SE 16 th – SE 36 th Street (Lincoln City) )Project Community Advisory Committee July 11, 2007 Meeting.
Public Involvement Open Houses Develop Problem Statement Review plans, policies, regulations, and standards Identify and assess Alternate Mobility.
US101: SE 16 th – SE 36 th Street (Lincoln City) )Project Community Advisory Committee October 3, 2007 Workshop.
Oregon 62: I-5 to Dutton Rd. (Medford) Oregon 62: I-5 to Dutton Rd. (Medford) for Jackson County Planning Commission May 9, 2013.
Oregon 62: I-5 to Dutton Rd. (Medford) for Jackson County Planning Commission May 9, 2013.
A34 Corridor Strategy Strategic Route Improvements 25 th November 2004 working together with.
Project Description and Needs Lincoln Way Widening Addition of a center-turn lane and safety improvements to the grade and horizontal alignment. Needs.
Loading and Unloading Students
Linden Hills Small Area Plan WorkshopWorkshop April 24 & 25, 2013.
City of Oakland: Road Diet Experience
PUBLIC MEETING May 12, 2011 P U B L I C I N V O L V E M E N T Project Status PHASE III Construction PHASE II Contract Plan Preparation & Land Acquisition.
Who we are these people? Gabriela Vega – Transportation Planner, DDOT/PPSA George Branyan – Pedestrian Program Coordinator, DDOT/PPSA Trey Dickerson –
Southside Flood Protection Red River Channel Extension Clay County Courthouse September 8, 2008.
Great Western Corridor Feasibility Study
Hot Springs Public Meeting Reconstruction of US 18 & US 385
Paula J. Trigg, County Engineer Public Works and Transportation Committee April 2, 2014 OVERVIEW | SOURCE OF PROJECTS PROPOSED HIGHWAY IMPROVEMENT.
Drivers Education Journal # Please pick up all the handouts Get out a sheet of loose leaf paper and something to write with Write the.
Urban Transportation Council Green Guide for Roads Task Force TAC 2009 Annual Conference and Exhibition Vancouver.
I-96 Reconstruction/Bridge Repair Project City of Livonia and Redford Township Wayne County May 10, 2013 Association of the Council of Western Wayne Yankee.
Strategic Approach to a Walkable Edmonton Pro Walk / Pro Bike 2004: Creating Active Communities September 9, 2004.
U.S. 33 Northern Connector Alternative
JANUARY 9, 2002 SCAJAQUADA CORRIDOR STUDY Grant Street to Parkside Avenue City of Buffalo Fisher Associates Joseph Passonneau & Partners In Association.
2012 CSVA Conference VE Scan of Western Canada Projects – The Flexibility of VE for Decision Making.
Tysons 1 Operational Analysis of Dulles Toll Road Ramps to Tysons Board Transportation Committee Meeting September 17, 2013 Seyed Nabavi Fairfax County.
Clinton Street Bridge over the Maumee River ODOT Project DEF April 1, 2015 Stakeholder’s Meeting.
Board of County Commissioners November 8, Recommendation Project Background and Location Traffic Analysis Comparison of Alternatives Public Meeting.
Route 28 South of I-66 Corridor Safety and Operations Study Technical Committee Meeting #2 June 25,
U.S. 31 at CR 400 South Roundabout Information Meeting December 18, 2013 Clifty Creek Elementary Columbus, Indiana.
Virginia Street Bus RAPID Transit Extension Presentation to RTC July 17, 2015 Project Purpose Extend RAPID to UNR Improve pedestrian safety & access Create.
Clinton Street Bridge over the Maumee River ODOT Project DEF May 14, 2015 Public Meeting.
Schools Jobs Revenues Services Recreation Environment Transportation Transportation Connectivity Housing Public Safety Pontiac’s.
NE 203 rd Street & NE 215 th Street Intersection Improvements between US 1 & West Dixie Highway Florida Department of TRANSPORTATION Upcoming Project Development.
Limebank Road Environmental Assessment Study February 19, 2003.
US 1 COLLEGE PARK – SEGMENT 1 FROM COLLEGE AVE/REGENTS DRIVE TO MD 193 (UNIVERSITY BLVD) Presentation to College Park City Council August 5,
Barrington Road at Jane Addams Memorial Tollway (Interstate 90) Interchange Improvement Study Hoffman Estates Village Hall June 27, 2012.
The Ministry of Transportation and Infrastructure welcomes you to an Open House for: Trans Canada Highway No.1 Improvements in Salmon Arm Your comments.
County of Fairfax, Virginia Department of Transportation Richmond Highway Transit Center Feasibility Study Briefing with the Fairfax County Transportation.
Capital Improvement Program. During the Annual Strategic Action Plan (SAP) evaluation, long-term needs and priorities are identified by City Council Capital.
CITY OF RAINIER RAILROAD CROSSINGS 1. Project # 2 Team Members Portland State University City of Rainier Lars Gare, City Administrator ODOT Rail David.
1 Tower Road Project Update. 2 The Project Team requests the Alachua County Commission: Authorize staff to: Proceed with re-evaluating four (4) key issues.
Town of Cobourg Division Street Improvements Public Information Centre October 1, 2015 Image Courtesy of Google 2015.
Transportation and Transit Committee 4 December 2002 Albion Road Corridor Study.
CITY OF RAINIER RAILROAD CROSSINGS 1. Project # 2 Team Members Portland State University City of Rainier Lars Gare, City Administrator ODOT Rail David.
S.R. 930 and Green Street Intersection Improvement Project Tuesday, May 22, :00 p.m. Presentation Park Hill Learning Center Auditorium New Haven,
Route 55: Lauer Rd –TSP & Access Management. Agenda  Welcome and Introductions  Workshop Purpose  Project Introduction & Background  Citizen Advisory.
23 rd Avenue Corridor Greenway Community Open House November 6, 2013.
STA Safety Project PID #76439 December 12, 2006.
Fern Valley Interchange Project Development Team Meeting February 3, :00 – 11:00 p.m.
Northside Transportation Network Community Meeting November 17 th, 2010 UROC.
Rainier Avenue South Pilot Project Update Seattle Bicycle Advisory Board Project Manager Jim Curtin September 2, 2015.
Peachtree Road Transformation Project: Operations and Safety Analysis P.I Fulton County August 25, 2015 Buckhead CID 1.
CITY OF RAINIER RAILROAD CROSSINGS 1. Team Members Matthew DeGeorge Robert Acevedo Josh Crain Jim Harvey Heather Wenstrand 2.
U.S. 20 Intersection Improvement Project at Waverly Road Porter Town Hall Thursday, August 13, 2015.
East-West Corridor Connectivity Study – Study Recommendations November 17, 2009.
Planning Commission Study Session: Preferred Plan July 23, 2015.
RIVERSTONE CONNECTION STUDY Task Force Meeting #4 June 19, 2013.
Waterdown Road Corridor Class Environmental Assessment (Phase 3 & 4) Community Services Committee May 9, 2012.
County Road 19(Manning Road) & County Road 22 Improvements Environmental Study/ Preliminary Design Report November 2008.
MD 30 (Hanover Pike) at Mt. Gilead Road
All About the County Road 22 Roundabout
Secor Road Reconstruction Project Public Meeting #2
S.R. 44 Corridor Management Plan S.R. 44 Corridor Management Plan
Project Management Team Meeting #3
Highway 169 Bridge Replacement & Pavement Resurfacing
Parks Highway Reconstruction: Lucas Road to Big Lake Road
Presentation transcript:

October 28 th, 2013

Hwy 97 – Carson to Fox Mountain Road Four Lanning  Review Project Scope Problem Definition Objectives  Summary of Work Completed to Date Highway 97 Options City Side Road Connection  Next Steps  Question and Answer Period

Hwy 97 – Carson to Fox Mountain Road Four Lanning  Safety issues exists on Highway 97 between Carson Drive and Mackenzie Avenue  Safety concerns at Toop Road intersection with Highway 97 Traffic Statistics (between Carson and Mackenzie): Collisions (2003 to 2012): 2 fatalities, 27 injuries, 43 property-damage-only Most Common Type of Collision: 36% - 90° intersection type 14% - Off-road right and Off-road left 13% - Rear-end 37% - Other

Hwy 97 – Carson to Fox Mountain Road Four Lanning Contributing Factors to Collisions:  Driver Expectations due to speed change in the Transition Zone  Intersection Spacing and Configuration Current Spacing between Carson and Toop = 245m TAC Standard Spacing recommended minimum spacing between two signalized intersections is 500m based on 70 km/h

Hwy 97 – Carson to Fox Mountain Road Four Lanning  This project is part of the Phase 2 Cariboo Connector commitment to 4 lane 440kms from Cache Creek to Prince George  Design and construct 1.5 kms of Highway 97 between Carson Drive and Fox Mountain Road  Upgrade and improve 2 intersections  Access management Carson Drive and Toop Road

Hwy 97 – Carson to Fox Mountain Road Four Lanning  Address safety for pedestrians, cyclist and vehicle operators  To accommodate for future traffic growth over the 25 year design horizon  Improve mobility  Increased lane capacity  Improved turning movements  Longer left turn lanes and right turn lanes at intersections  Upgrade and improve intersection  Improve access to local street network providing access to schools and to the Cariboo Memorial Hospital  Improved lighting

Hwy 97 – Carson to Fox Mountain Road Four Lanning  1996 McElhanney Corridor Plan  1998 Hwy 97 Traffic Operations and Safety Review completed by Hamilton  2007 Hwy 97 Traffic Operations and Safety Review completed by Opus Hamilton  2009 City of Williams Lake, Hwy 97&11 th Ave/Toop Rd, Conceptual Design Report completed by L&M Engineering  2009 Cariboo Connector Technical Analysis Report completed by MoT Southern Interior Region Planning Group  2011 Urban Systems Ltd Project Development Report  2011 Preliminary Environmental Report completed by McElhanney no significant environmental impacts identified  2011 Archeology Investigation Assessment completed by Terra Archeology no archaeological concerns identified

Hwy 97 – Carson to Fox Mountain Road Four Lanning  2012 MoTI Consulted with City to Review the Planning Study  June 2012 USL completed planning study 13 options were developed 6 advanced to further analysis and evaluated using the Multiple Account Evaluation Method  June 2012 MoTI and the City of Williams Lake held a Planning Open House 2 Preferred options were presented to the Community  October 2012 MoTI retained Binnie and Associates and held an Initiation meeting to review the project scope and objectives  February 2013 Binnie presented Conceptual options that included elements from the previous planning report Concepts were reviewed by the Project Team  February 2013 MoTI Presented Conceptual Designs to the City Council

Hwy 97 – Carson to Fox Mountain Road Four Lanning  April 2013 an independent Engineering Firm McElhanney Consulting Services and EVM Project Services Ltd. completed a Value Analysis Study  April 2013 the Value Analysis reviewed 2 options The VA team recommended Option 2, with access management alternatives This then moved forward to the next stage of design  May 2013 MoTI Reviewed Design with City of Williams Lake

Hwy 97 – Carson to Fox Mountain Road Four Lanning 1.Maintains full movement signalized intersection 2.Protected T- intersection at Toop Road 3.McKinnon Road connection to Carson Drive will remain 4.Toop intersection will accommodate the eastbound to northbound left turn movement 5.The grade of Carson Drive will be slightly worse than existing conditions 6.Businesses on North Broadway will enter and exit directly into the bulbed intersection Option 1: Retain Signalised Intersection at Carson Drive

Hwy 97 – Carson to Fox Mountain Road Four Lanning 1.Relocation of the existing signalized intersection at Carson Drive to Toop Road 2.Partial T-intersection at Carson Drive 3.Full movement intersection at Toop where approach grades on the highway are flatter 4.McKinnon road connection to Carson Drive will remain and be improved 5.No pedestrian crossing at Carson 6.Impact on residential properties Option 2: Relocate the Signalized intersection to Toop Road

Hwy 97 – Carson to Fox Mountain Road Four Lanning VAP #9: Pro’s and Cons of local road alternative on west side of Toop 1.Provides traffic distribution on two collectors rather than just one 2.Direct emergency access to hospital 3.Solves close intersection spacing issues 4.Allows network continuity across the highway 5.No impact to Carson park and ride

Hwy 97 – Carson to Fox Mountain Road Four Lanning Evaluation Matrix from the Option evaluation report outlined: CriteriaOption 1 Signal at Carson Option 2 Signal at Toop Construction Benefits Property Acquisition3/42/4 Constructability4/43/4 Costs4/43/4 11/128/12 Operational Benefits Highway Mobility2/43/4 Traffic Operations2/43/4 Safety2/43/4 Network Connectivity4/43/4 Intersection Geometry1/43/4 Access to Property2/43/4 13/2418/24

Hwy 97 – Carson to Fox Mountain Road Four Lanning  After reviewing the two concepts with CoW, City Council endorced the relocation of the signalized intersection to Toop Road  June 2013 held a 2 nd Open House to present the intersection relocation to the community

Hwy 97 – Carson to Fox Mountain Road Four Lanning  July 2013 MoTI met with City to review feedback from the Community and decided to proceed with a 3 rd Open House to show Johnson connection  August 2013 City held 3 rd Open House

Hwy 97 – Carson to Fox Mountain Road Four Lanning

1.Make decision to proceed with option 2a or 2b 2.Complete Design 3.Complete geotech investigations 4.Complete environment and archeology investigations 5.Start property acquisitions 6.Consult with Stakeholders and Utility companies 7.Value Engineering 8.Road Safety Audit

Hwy 97 – Carson to Fox Mountain Road Four Lanning Any Questions? Please proceed to the podium to ask the Panel Or Visit