LHCC Comprehensive Review 26/6/06 D.J.A. Cockerill - RAL 1 Status of the CMS ECAL Endcaps LHCC Comprehensive Review, June 2006 D Cockerill EE  EE large.

Slides:



Advertisements
Similar presentations
Endcap assembly update C Buttar UK-SCT-MB RAL 2 nd Sept 04.
Advertisements

Status of EC-C assembly at Liverpool C Buttar EC PAR, Nikhef Nov 04.
PPRP September 2002 UK CMS 1 CMS Endcap Electromagnetic Calorimeter and Global Calorimeter Trigger, Physics & Computing Presented by Peter Hobson, Brunel.
US CMS Collaboration Meeting, May 19, Ren-yuan Zhu, Caltech PWO Crystal ECAL Ren-yuan Zhu California Institute of Technology May 19 th 2001.
2002 LHC Days at Split, Split, October 2002 D J A Cockerill - RAL 1 The ECAL Endcap Calorimeter for CMS D J A Cockerill RAL - UK 2002 LHC Days at Split.
CMS ECAL Annual Review - CERN Sept 2001 R M Brown - RAL 1 Test results from 500 preproduction VPTs R M Brown RAL - UK CERN 19 September 2001.
STFC RAL EE at SLHC CERN 15/04/08 R M Brown - RAL 1 EE at SLHC What do we expect at SLHC? EE Layout VPT vulnerability to radiation - Faceplate darkening.
LHCb VELO Production Visit November 9 th 2005 Introduction to staff Status Schedule.
VELO Module PRR preparation meeting28-feb-2006 LiverpoolMassimiliano Ferro-Luzzi 1 Introduction VELO overview Overall planning A bit of (recent) history.
LHC CMS Detector Upgrade Project US CMS Trigger Upgrade Introduction to Cost & Schedule Wesley Smith, U. Wisconsin Fermilab Directors Review 16 July 2013.
Hybrid pixel: pilot and bus K. Tanida (RIKEN) 06/09/03 Si upgrade workshop Outline Overview on ALICE pilot and bus Requirements Pilot options Bus options.
ECAL End Cap Schedule issues Justin Greenhalgh This presentation will be at under EE356.
CMS-UK Oversight Committee 17/5/04 D.J.A. Cockerill - RAL 1 The CMS ECAL Endcaps Crystal ECAL Endcap Calorimeter (EE) Preshower EE EE crystals.
CMS-UK Oversight Committee 18/11/03 D.J.A. Cockerill - RAL 1 The CMS ECAL Endcaps Crystal ECAL Endcap Calorimeter (EE) Preshower EE.
CMS ECAL Meeting Ecole Polytechnique June 2005 A.B.Lodge - RAL 1 ECAL End Cap CMS ECAL End Cap Trigger Meeting. Meeting held 29 th - 30 th June.
D Cockerill, RAL, 8 June 2005 Dee in testbeam ProposalP Bloch, C Seez, Y Sirois Dee calibration in test beam Last period of 2006, November Heavy ions,
CMS Week March presented by John Coughlan RAL FED Hardware Status Pre-Series Manufacture Final Production Plans.
Xenon Detector Status Liquid Xenon Group. 1 Outline Cryostat construction –Honeycomb panel test at Pisa –Assembly –Cryogenic test at SIMIC –Leak test.
Forward Detector Meeting, 11 Mar 2003Børge Svane Nielsen, NBI1 Si-FMD status Forward Detector meeting, CERN, 11 March 2003 Børge Svane Nielsen Niels Bohr.
Technical Board, 12 July 2005Børge Svane Nielsen, NBI1 Status of the FMD Børge Svane Nielsen Niels Bohr Institute.
ATLAS SCT Endcap Detector Modules Lutz Feld University of Freiburg for the ATLAS SCT Collaboration Vertex m.
José C. Da Silva OFF DETECTOR WORSHOP, April 7, 2005, Lisboa SLB and DCC commissioning for 904.
PPD CMS Away Day, Cosenors House, 29/9/05 D.J.A. Cockerill 1 DJAC: PPD CMS ECAL Hardware Tasks (i) The next 2.5 years (ii) The following 2.5 years To March.
Milestones and Schedule of SVD Construction Markus Friedl (HEPHY Vienna) on behalf of the Belle II SVD Collaboration BPAC October 2012.
LHCC referees meeting, 10 October 2005Børge Svane Nielsen, NBI1 Status of the FMD LHCC referees meeting, 10 October 2005 Børge Svane Nielsen Niels Bohr.
Saverio MINUTOLITIG meeting, 10 February Report on T1 installation activities and achievements made during this shutdown.
CMS ECAL End Cap EDR Meeting CERN 28 Nov. to 29 Nov 2000 A.B.Lodge - RAL 1 ECAL End Cap CMS ECAL End Cap Engineering Design Review. EDR meeting held 28.
J A Hill – EID RAL 1-2 September EE End Cap Mechanical Design ECAL EE End Cap Engineering CMS-UK Collaboration Meeting Brunel University September.
Saverio Minutoli INFN Genova 1 1 T1 Electronic status Electronics Cards involved: Anode Front End Card Cathode Front End Card Read-Out Control card VFAT.
EE and SE Installation Wolfgang Funk - CERN CMS 11/9/ ) Introduction 2.) Installation scenario 3.) SE schedule, manpower, cost estimates 4.) EE.
CMS ECAL End Cap Meeting CERN 19 June to 23 June 2000 A.B.Lodge - RAL 1 ECAL End Cap High Voltage Cards and 2000 Electrical/Thermal Model. Progress on.
Construction and Installation Readiness of TOTEM Roman Pots Detectors Federico Ravotti (PH/TOT) Gennaro Ruggiero (PH/TOT) LHCC minireview – 06 May 2009.
S. Zelepoukine CMS Electronics Status Report: ECAL Detector Control System S. Zelepoukine IHEP Protvino/ETHZ
June 29th 2005Ph. BUSSON LLR Ecole polytechnique, Palaiseau1 Plans for a new TCC for the endcaps Characteristics: reminder Preliminary list of tasks and.
Micromegas modules Towards the 7 module test. Micromegas panels Phase I: ‘Large Prototype’ Micromegas modules were built and tested in beam ( ):
CMS ECAL Elba May 2006 R M Brown - RAL 1 The Status of the CMS Electromagnetic Calorimeter R M Brown On behalf of the CMS ECAL Group.
CMS ECAL End Cap Meeting CERN 18 Oct to 22 Oct ECAL End Cap High Voltage and Fibre Optic Monitoring Systems Progress. Progress on High Voltage and.
RP detectors CTS Sensors now in production, full delivery between February and June 07 Production GUI and DB being finalised Test Procedure being defined.
U. Of Rochester DOE Review, July 15-16, 2002: P. de Barbaro, CMS1 CMS Project at UR Pawel de Barbaro University of Rochester DoE Review July 15-16, 2002.
Mechatronics Task Force, 26-nov-02 Olivier Teller, CERN EP-CMA1 Cooling Mechatronics Schedule.
ECAL – EE Design Status Presentation 19/7/06 D.J.A. Cockerill - RAL 1 EE Design Status D Cockerill CERN 19 July 2006.
The CMS Electromagnetic Calorimeter at the LHC
Status of NA62 straw electronics Webs Covers Services Readout.
LHCf: installation & commissioning Measurement of Photons and Neutral Pions in the Very Forward Region of LHC Oscar Adriani INFN Sezione di Firenze - Dipartimento.
Tracker Week October CCLRC, Rutherford Appleton Laboratory, Oxon, UK Imperial College, London, UK Brunel University,
All CMS 30 May07 TSV1 All CMS 3 30 May 2007 LHC machine CMS Progress Overall Schedule.
D0 PMG 6/15/00 PMG Agenda June 15, 2000  Overview (Tuts) u Detector status u Reportable milestones u Financial status u Summary  Response to DOE review.
PSD upgrade: concept and plans - Why the PSD upgrade is necessary? - Concept and status of the PSD temperature control - Concept of the PSD analog part.
CMS ECAL End Cap WACH4, 28 Nov 2002 D Cockerill - RAL (1) - Yield, e/MeV with production crystals and production VPTs - Pre-calibration precision using.
D. Greenfield CLRC1 UK-V End-cap Engineering 15 July 2003 Debbie Greenfield, RAL.
1 HBD: Update and Schedule Itzhak Tserruya DC Meeting, BNL, April 13, 2005 Outline:  Full scale prototype status  Light source test  Construction Schedule.
Dec
D0 PMG February 15, 2001 PMG Agenda February 15, 2001  Overview (Weerts) u Detector status u Reportable milestones u Summary  Operations Organization.
A.Cheremukhin (JINR, Dubna) CMS Preshower PRR, July 5-6, 2001, CERN1 Micro-module assembly -  -module elements - alignment of the silicon sensors to the.
Status of the PSD upgrade - Status of the PSD cooling and temperature stabilization system - MAPD gain monitoring system - PSD readout upgrade F.Guber,
PSD upgrade: concept and plans - Why the PSD upgrade is necessary? - Concept of the PSD temperature stabilization and control - Upgrade of HV control system.
Saverio MINUTOLITOTEM Electronics W.G., 9 December T1 electronics status.
Tile HCAL status Felix Sefkow CALICE Technical Board Review April 19, 2007.
Paolo Rumerio, CERN On behalf of the CMS Electromagnetic Calorimeter Group CALOR 2006 Chicago, June 5 th – 9 th, 2006 Commissioning of the CMS Electromagnetic.
ECAL Plenary 27/2/07 D.J.A. Cockerill - RAL 1 Status of the CMS ECAL Endcaps ECAL Plenary, 27 Feb 2007 D Cockerill  VPTs  Electronics and Integration.
July 20, 2007Anita Topkar, BARC PSD Production: Present Status Dr Anita Topkar BARC.
CMS-UK Oversight Committee 17/11/06 D.J.A. Cockerill - RAL 1 The CMS Electromagnetic Calorimeter UK Responsibilities Procurement and testing of VPTs Design.
SVD Status Markus Friedl (HEPHY Vienna) SVD-PXD Göttingen, 25 September 2012.
University of Wisconsin
CCS Hardware Test and Commissioning Plan
T1 Electronic status Conclusions Electronics Cards:
10/month is the present production rate 2 FTE + sporadic contributions
UK CMS Oversight Committee Mtg
PROGRESS on EE VPTs, Dees D Cockerill
Setup for testing LHCb Inner Tracker Modules
Presentation transcript:

LHCC Comprehensive Review 26/6/06 D.J.A. Cockerill - RAL 1 Status of the CMS ECAL Endcaps LHCC Comprehensive Review, June 2006 D Cockerill EE  EE large mechanics  VPTs and Supercrystal assembly  Electronics  Trigger  The “Dee4” project ES  ES mechanics  Micromodules and readout EE and ES Planning Conclusions

LHCC Comprehensive Review 26/6/06 D.J.A. Cockerill - RAL 2 The CMS ECAL Endcaps – EE/ES Tapered crystals Off-Pointing ~ 3 o from vertex Crystal Endcaps: 4 Dees (2 per endcap) Crystals Total mass 22.9 t Preshower 2Xo, 1Xo Pb, 2mm Si strips, 2 x 2 orthogonal layers

LHCC Comprehensive Review 26/6/06 D.J.A. Cockerill - RAL 3 EndCap EE All large mechanical pieces are at CERN Dry assembly of env. screen produced in Russia

LHCC Comprehensive Review 26/6/06 D.J.A. Cockerill - RAL 4 EE: VPT production & gluing, Supercrystals EE VPT to crystal gluing 2800 VPTs shipped from UK to CERN All tested upon receipt by Russia - INR Up to 50 EE crystals/VPTs glued each week 110 of current EE crystal stock (~350 xtals) done First “Russian” SC completed in June 2006 built using CRISTAL database

LHCC Comprehensive Review 26/6/06 D.J.A. Cockerill - RAL 5 EE electronics Preliminary results, ~ 3900 e- per channel Cross talk < 0.1% Meets EE requirements SC HV cards 105 pre-production cards completed All R & C components for EE delivered Motherboards 2 prototypes on Dee4 600 cards by end 2006 EE VFE cards RC feedback on MGPA tuned for EE Input diode for VPT spark protection 30 prototypes produced in Feb cards now under test 3130 cards by end July 06 FE cards 80 pre-production cards tested 800 cards produced by Sep 2006

LHCC Comprehensive Review 26/6/06 D.J.A. Cockerill - RAL 6 EE trigger Pseudostrip (5 crystal) allocations EE+ towards I.P Consequent trigger towers (TCC level) EE+ towards I.P

LHCC Comprehensive Review 26/6/06 D.J.A. Cockerill - RAL 7 EE : preparing for the assembly Ensuring correct cabling of the channels Trigger map (H.Heath) LED cabling tester from UVa

LHCC Comprehensive Review 26/6/06 D.J.A. Cockerill - RAL 8 EE data and trigger readout The fibre readout fan-out boxes (two layers) serving the EE DCCs and TCCs in the control room 900 readout fibres to correctly route per Dee

LHCC Comprehensive Review 26/6/06 D.J.A. Cockerill - RAL 9 “Dee4” project “Dee4” First large scale test of integration philosophy 20 SCs mounted on BP Dee4 by end 2006 Trigger mapping at motherboard 10 cooling blocks, main manifold “Dee4” to testbeam in May 2007 EE assembly has started “Dee4” will provide crucial assembly and test beam insights Dee1 assembly from September 2006

LHCC Comprehensive Review 26/6/06 D.J.A. Cockerill - RAL 10 (Preshower) ES: Engineering Windows ready with Paraffin : first elements to be installed before beam pipe closure First brazing of cooling screen Blanks for outer drums/patch panels

LHCC Comprehensive Review 26/6/06 D.J.A. Cockerill - RAL 11 ES: Silicon micro-modules Si sensors available All ceramics supports and Al tiles produced Small mod to allow for backplane bonding (follow. ES and Tracker experience) All ASICS available Problem with hybrids production First large series of PCBs not good ! Immediate action: change PCB manufacturing company Will probably eat a large part of schedule contingency

LHCC Comprehensive Review 26/6/06 D.J.A. Cockerill - RAL 12 ES: On and Off detector digital electronics Successful test of Mother boards pre-series including 12 boards token ring and test of several ladders →Production launched ESR for ES-DCC last May OptoRx: proto ok. Final version in a few weeks VME board end of Summer (collab. with TOTEM) MB tester (NTU) OptoRx

LHCC Comprehensive Review 26/6/06 D.J.A. Cockerill - RAL 13 EE Planning Dee 1End Sep 2007 Dee 2End Dec 2007 Dee 3Mid Mar 2008 Dee 4Mid Apr 2008 CMS window for Dee1 end Sep 07 EE+ mid Jan 08 EE- mid Mar 08

LHCC Comprehensive Review 26/6/06 D.J.A. Cockerill - RAL 14 EE planning Crucial to introduce as much parallel assembly and integration as possible Quality control at each crucial step Suggestion to carry out all SC mounting and Dee assembly in bldg 867 This offers many very attractive features - all major activities under one roof - proximity of expert teams - realisation of the EE trigger, from motherboard level to fibre readout level - multiple DAQ test systems, needed for EE QA, available locally - cooling capacity for one entire Dee - LV power Crystal Palace Advance preparation of all large mechanics - Dees into OPAL frames - dry assembly tests of Environmental screens - BP cooling installation - Mounting laser monitoring system

LHCC Comprehensive Review 26/6/06 D.J.A. Cockerill - RAL 15 ES planning Good progress with engineering/mechanics Bare micromodule production has started Problem with hybrid PCB production: change of producer necessary; will try to minimize impact on overall ES schedule Delay on system motherboards but production should start soon and should be faster than originally envisaged Important progress in DAQ (software and ES-DCC) and good advances in offline/physics software “Ready for Installation” dates so far unaffected by delays. Some contingency now exists due to revised V35 schedule but will probably be “eaten” by hybrid delay ES+ Dee1 assembly finished ES+ Dee2 assembly finished ES- Dee1 assembly finished ES- Dee2 assembly finished ES- RFI ES+ RFI

LHCC Comprehensive Review 26/6/06 D.J.A. Cockerill - RAL 16 EE - Conclusions EE and ES assembly has started Much progress with the EE large mechanics, VPTs, SC assembly, electronics, and trigger and data mapping “Dee4” will provide crucial assembly and test beam insights Dee1 assembly from September 2006 Good progress with ES engineering/mechanics Bare micromodule production has started We are on the learning curve for EE and ES assembly

LHCC Comprehensive Review 26/6/06 D.J.A. Cockerill - RAL 17 Additional info follows, next slide