WCCUSD Bond Program Construction Update El Cerrito High School Stadium 07/15/2014
El Cerrito High School Stadium Conceptual Design
El Cerrito High School Stadium Project Team General Contractor Wright Contracting Architect of Record WLC Architects Construction Manager Hector De Leon Project Engineer Maria Zupo Inspector of Record Kris Gilbert
El Cerrito High School Stadium Site Plan
El Cerrito High School Stadium General Information Contract Amount $13,438,000 Notice of Award 11/21/13 Notice to Proceed 01/27/14 Duration 608 days Completion Date 09/27/15 Change Order $10,285.00 (0.07%)
El Cerrito High School Stadium Progress Update Site retaining walls at Ashbury and Colusa Fence piers at Colusa Building retaining walls and foundations Site grading and compaction Underground utilities
Backfilling at Ashbury
Site Walls and Foundation
Building Footings
Retaining Wall Construction at Colusa
Retaining Wall Construction at Ashbury
Retaining Wall Construction at Ashbury
Tree Planting
El Cerrito High School Stadium Ashbury Avenue Elevation