1 page 1 C O U P L E D NWE Day-Ahead Project 1 st NWE Stakeholder Workshop London 9 th December 2011 ENTSO-E Regional Group Northwest Europe.

Slides:



Advertisements
Similar presentations
Handling of grid losses of HVDC cables in NWE Market Coupling - EMCC proposal for compensation of grid losses – NWE day-ahead meeting, Copenhagen, 22/08/2012.
Advertisements

Draft Cross-regional Roadmap for Day-Ahead Price Coupling NWE Day-ahead price coupling project meeting 15 June 2011.
Cross-regional roadmap for Day-Ahead Market Coupling XXI Florence Forum Florence, 5 December 2011.
4th CSE ERI Stakeholders Group meeting AEEG – European regulatory affairs 15 maggio 2012 Overview of the regional work programme towards 2014.
Day-Ahead Market Coupling Proposal for algorithm approval process 8 th ACER Coordination Group for ERI Brussels, 9 th January 2012.
Draft cross-regional roadmap for Day-Ahead Market Coupling Work in progress, This version: 22 September 2011 updated after 5 th AESAG, 20 September 2011,
Coordinated Market Coupling for GB. 2 Service Provision specified to create a GB Hub with open access to : All GB connected ICs to coordinate XB Capacity.
Vision for the internal electricity market
TITRE 28/03/2012 NWE IG meeting – Amsterdam Schiphol NWE day-ahead price coupling – cost issues.
SWE IG Meeting Paris, CRE XBID Overview Supported by.
Florence Forum Multi Regional Day-Ahead Price Coupling Towards Implementation of the PCG Target Model December 10-11, 2009.
NWE Day-ahead price coupling project Cost Issue 2 nd IG Meeting 26 October APX ENDEX.
Cross-Regional Roadmap for Intraday DRAFT Updated 31/10/2011.
Cross-regional roadmap for Capacity Calculation XXI Florence Forum Florence 5 December 2011.
1 Intraday in the CWE region NWE and Bilateral initiatives Common RCC CSE - CWE 28 September 2010.
Disclaimer Some elements of the following presentation are extracted from documents approved by the 11 CWE Project Parties. However, this presentation.
1 page 1 NWE Intraday - Joint TSO and PX presentation London.
Bente Danielsen, ERGEG Transparency Project Team leader Alain Taccoen, ENTSO-E WG Market Information and Transparency, convenor Florence Forum June 2010.
The role of ACER In the Regional Initiatives Steve Gordon Head Of the Gas Department North West Regional Initiatives 2011.
09/12/2011 NWE Stakeholders Group meeting-London Getting to 2014 A contribution from the Regional Initiatives Process Christophe Gence-Creux Head of the.
FUI Feedback on PCG Target Model and roadmap propositions FUI Stakeholder Group Meeting Paris, 4 th November 2009 These comments reflect the general views.
Baltic Energy Market Interconnection Plan (BEMIP)
Click to edit Master title style TITRE CEE IG – 20/02/2014 ACER Long-Term Rights Task Force Current status of the discussion with ENTSO-E.
1 page 1 C O U P L E D Joint TSO-PX presentation NWE Day-Ahead Price Coupling IG meeting May 9 th 2012 Copenhagen Joint Presentation from TSOs and PXs.
Intraday projects - Commitment of the parties towards an integrated intraday market.
3. Update on status and implications of NWE intraday project (selection of the solution for the platform) 11 th Implementation Group Meeting 1 st March.
Intraday conclusions of NWE IG 9 May. Short term way forward (phase 1) PXs and TSOs confirmed commitment to 2012 intraday project based on ELBAS solution.
IFE-CASC long term auctions Project status Implementation Group Meeting - Lisbon,
Adeline Lassource (CRE) Charlotte Ramsay (OFGEM) 10 th FUI SG, London, 11 th March 2011 Progress with market integration: European initiatives and impact.
Progress with coupling FUI and CWE region
1 page 1 C O U P L E D NWE TSO Day Ahead Project NRA – TSO – PX meeting, 15 June 2011 ENTSO-E Regional Group Northwest Europe C O U P L E D.
Implementation of PCR for Day-Ahead Price Coupling in NWE Andrew Claxton NWE Stakeholders’ Workshop 9 December 2012.
ERGEG Advice Comitology Guidelines on Fundamental Electricity Data Transparency Florence Forum 13 December 2010 Bente Danielsen.
Day-Ahead Market Coupling Algorithm approval coordination NWE IG, Schipol, 28. March 2012.
Update on Ofgem’s interconnector policy consultation FUI IG, London, 13 th September.
The Capacity Allocation & Congestion Management Network Code An overview & status update Antonio Lopez-Nicolas Manager - Markets.
1 page 1 C O U P L E D Joint TSO-PX presentation NWE Day-Ahead Project Status Update 2 nd IG meeting NRA meeting October 26 th Joint Presentation from.
1 page 1 C O U P L E D Joint TSO-PX presentation NWE Day-Ahead Price Coupling IG meeting March 28 th 2012 Amsterdam Joint Presentation from TSOs and PXs.
1 XVI Florence Forum Jose Sierra Madrid, 4 June 2009 Chair, RIG ERGEG Electricity Regional Initiative Update & Progress.
EURELECTRIC Views on the Regional Integration process CSE Stakeholder Group Meeting EURELECTRIC Views on the Regional Integration process Marco Foresti,
SWE Day- Ahead market coupling 7 April 2014 Implementation Group meeting – Paris.
Draft Cross-regional roadmap for intraday Work in progress, for discussion 13 July 2011.
Status of Implementation of PCR for Day-Ahead Price Coupling Florence Forum 5 December 2012.
Draft cross-regional roadmap for Day-Ahead Market Coupling - Work in progress - NWE day-ahead price coupling project IG meeting 26 October 2011.
PCR Status report AESAG, September Supported by:
ENTSO-E’s Network Development Plans and Network Codes: How a strong European grid supports security of supply, affordable electricity prices through market.
Stakeholder Group Meeting 26. May 2010 Action Plan of the Region 2010 Finn Dehlbæk.
Continuous Cross-Border Implicit Intraday Trade Status update XXI. Florence Forum Dec 05th, 2011.
José Sierra, RIG Chair Rafael Gómez-Elvira (RIG Chair Team) XIX Florence Forum 14 December 2010 ERGEG Electricity Regional Initiatives Status Review.
0 Congestion management Congestion management Giedrius Radvila AB “LIETUVOS ENERGIJA” Minifora Vilnius.
Cross Border Intraday on the North Italian Borders Introduction Forum Rome, 13 th March 2012.
1 The regulators’ view on the Central West REM: Emphasis on the completion of existing initiatives Presentation for the Mini-Forum 20 June 2006.
European Commission views on intra-day and balancing markets
Achievements and next steps in the Central-South Region Central-South Region 3rd SG meeting Milan, November 16 th 2010.
General support to Northern Europe ERI priorities. Urges the Northern Europe RCC to proceed – not only with - Optimizing the use of interconnectors - Transparency.
Nord Pool Spot update 11th Baltic Electricity Market Mini-Forum October 01, 2010 Hando Sutter, Nord Pool Spot AS.
1 Market coupling Commission de Régulation de l’Electricité et du Gaz Fonctionnement Technique des Marchés September 2010 Common CSE – CWE RCC Meeting.
Electricity Regional Initiative Central- South Region Progress with developing regional electricity markets By: Carlo Crea, Secretary General The Regulatory.
The Regional Initiatives deliver concrete results in the regions but will the regions join up? Ms Asta Sihvonen-Punkka ERGEG’s Electricity Focus Group.
Status Report of the Electricity Regional Initiative Ms Asta Sihvonen-Punkka ERGEG Electricity Focus Group (EFG) Chair The Regional Initiatives: Progress.
Development and Implementation of a Coordinated Model for Regional and Inter-Regional Congestion Management Development and Implementation of a Coordinated.
1 page 1 C O U P L E D NWE Day Ahead Project Update FUI IG Mtg – London 13 th September 2010 ENTSO-E Regional Group Northwest Europe C O U P L E D.
Joint Proposal for a Day Ahead Market Coupling Initiative between GB and Mainland by National Grid, RTE, ELIA and TENNET   Results of a joint study on.
NWE Day-Ahead Price Coupling
Status of Implementation of PCR for Day-Ahead Price Coupling
Supported by: PCR Status report AESAG, September
Context 12 TSOs in North West Europe (NWE) have commenced a project to facilitate a single price coupling across a region covering CWE, Scandinavia and.
NWE Day-Ahead Price Coupling
Supported by: PCR Status report AESAG, September
Baltic Energy Market Interconnection Plan (BEMIP)
Presentation transcript:

1 page 1 C O U P L E D NWE Day-Ahead Project 1 st NWE Stakeholder Workshop London 9 th December 2011 ENTSO-E Regional Group Northwest Europe

2 page 2 C O U P L E D Introduction 19 th European Electricity Regulatory Forum (December 2010): The Forum agreed that price coupling in north-west Europe (CWE, Nordic regions and GB) should be developed and implemented by end 2012, as a first step for pan European price coupling. 20 th European Electricity Regulatory Forum (May 2011): The Forum supported the continuation of the NWE project for both day-ahead and intra-day markets, in order to meet the target date of ACERs roadmap requests the TSOs and PXs to deliver a single European price coupling by 2014 First step is to deliver NWE (CWE, Nordic, GB) by the end of 2012

3 page 3 C O U P L E D NWE TSOs and PXs recognise the importance of NWE as a pragmatic implementation project All TSOs and PXs in NWE have already taken the commitment to replace ITVC in June 2012 when ITVC was launched in November 2010 NWE has a central role due to geography and advanced development The solution should ensure extendibility of day-ahead price coupling to other regions The time schedules are challenging and the NWE TSOs and NWE PXs, as well as the regulators, need to focus to have a smooth and efficient achievement of the NWE price coupling Introduction

4 page 4 C O U P L E D Towards a European power market The Nordic market – 2000 Including Estonia 2010 Central West Europe – 2010 ITVC – 2011 Including embedded solution for BritNed cable to GB via APX and Price Coupling on SwePol via NPS

5 page 5 C O U P L E D Towards a European power market The Nordic market – 2000 Including Estonia 2010 (and full Baltic prel. end 2012) Central West Europe – 2010 ITVC – 2011 Including embedded solution for BritNed cable to GB via APX and Price Coupling on SwePol via NPS North West Europe – 2012 Including Price Coupling on SwePol via NPS, and NPSs work with the local TSOs on establishing day-ahead markets in Latvia and Lithuania 2300 TWh

6 page 6 C O U P L E D Towards a European power market The Nordic market – 2000 Central West Europe – 2010 ITVC – 2011 North West Europe – 2012 European solution – TWh

7 page 7 C O U P L E D Status on the NWE work 13 TSOs covering the Nordic, BeNeLux, France, Germany and GB NWE TSOs have signed agreement with CASC as TSO’s administration and project manager NWE TSO organization is in place NWE TSOs delivered their requirements for the NWE algorithm TSO share of the design cost of NWE solution is agreed between the NWE TSOs

8 page 8 C O U P L E D Status on the algorithm requirements - PCR assessment The PCR project parties have selected the day-ahead market coupling algorithm CWE COSMOS, currently in use in the CWE region, as starting point for the development of the NWE algorithm NWE TSOs have checked how far their algorithm requirements are met and to which extent further development work is needed to create the prototype for the NWE region Assessment shows, in general –majority of the requirements are in operation or has already been developed and tested in CWE context –however, all these requirements shall be tested in NWE context –a couple of requirements need further development and investigation before implementation and testing, because they have not been addressed before ENTSO-E is working to deliver their assessment of the PCR algorithm as a starting point for Europe by January 2011

9 page 9 C O U P L E D NWE TSO organization Steering Committee (TSO SC) Chair: Bente Hagem TSO Project Manager Corne Meeuwis (CASC) Project Day ahead Chair: Frederik Johnsen (CASC) Project Legal Chair: Pierre Bernard (Elia) Project Intraday Chair: Lucy Sarkisian, Co-convener Marie Dufourg

10 page 10 page C O U P L E D Status on the NWE work TSOs - PXs Monthly coordination meetings between the TSOs and PXs since September in order to achieve: A joint project with a common Steering Committee Develop and sign agreement (All Party Cooperation Agreement (APCA)) to handle cost sharing, governance etc. between the TSOs and PXs Development and implementation of a NWE market coupling solution

11 page 11 page C O U P L E D Status on the NWE work TSOs - PXs Little progress has been made in the cooperation with the PXs the last months. The joint project is striving to achieve: –A joint PX proposal for a complete NWE market coupling solution –A joint PX budget for the design and implementation phase –A detailed joint project plan –A common view on major governance issues NWE TSOs are still waiting for a common proposal from the NWE PXs As a result of this, and in order to keep the time schedule, the NWE TSOs will also investigate fallback strategies to the joint PCR project

12 page 12 page C O U P L E D The way forward In the NWE TSO SC meeting 14 th December the TSO will discuss: The 21 st Florence conclusions Possible common position from the PXs The way forward, including fallback strategies The NWE TSOs will do their utmost to deliver the NWE price coupling according to the time schedule in ACERs roadmap

13 page 13 page C O U P L E D The first phase is the price coupling in North West Europe